Work Zone Rule Virtual Workshop - PowerPoint PPT Presentation

About This Presentation
Title:

Work Zone Rule Virtual Workshop

Description:

Work Zone Rule Virtual Workshop Rule State of the Practice Overview Assessing the State of the Practice FHWA has identified several ways to assess the state of ... – PowerPoint PPT presentation

Number of Views:135
Avg rating:3.0/5.0
Slides: 17
Provided by: opsFhwaD
Learn more at: https://ops.fhwa.dot.gov
Category:

less

Transcript and Presenter's Notes

Title: Work Zone Rule Virtual Workshop


1
Work Zone Rule Virtual Workshop Rule State of
the Practice Overview
2
Assessing the State of the Practice
  • FHWA has identified several ways to assess the
    state of the practice and effects of the Rule
  • Review of 2008 Work Zone Self Assessment (WZSA)
    results
  • Review of responses to five supplemental
    questions added to the 2008 WZSA
  • Discussions with State and local agencies

3
What have we learned?
  • Rule has brought about positive changes in
    practices and more focus on managing work zones,
    specifically in the following areas
  • Work Zone Policy
  • Impacts Assessment
  • Significant Project Identification
  • Training
  • TMP Development and Implementation
  • Data Collection and Analysis

4
2008 WZSA Results
  • Largest increases were in practices related to
    Subpart J
  • Classifying projects based on impacts
    (Significant Projects) 25
  • Training law enforcement personnel 21
  • Establishing a policy to develop TMPs 20

5
WZSA Rule Supplemental Questions
  • Supplemental question scoring scheme

6
Work Zone Policy
  • Biggest change - Agencies have pulled together
    several disparate policy documents and
    procedures/guidelines into one WZ
    policy/guidelines.
  • Some agencies did not have a policy for MOT in
    work zones and have now developed one as a result
    of the Rule.
  • 21 agencies (41) have reported that as a result
    of their WZ Policy, they are taking a more
    consistent approach to planning, designing, and
    constructing road projects

7
Work Zone Policy (cont.)
  • Many agencies mentioned they are now considering
    WZ impacts earlier in the project development
    process.
  • Some agencies have established goals and measures
    for WZ performance (e.g., queues, delay time) as
    a result of the Rule.

8
Impacts Assessment
  • The agency is seeing enhanced consideration and
    management of WZ safety and mobility impacts -
    starting during planning and continuing through
    project completion
  • 24 agencies (47) experienced this as a result of
    the Rule
  • 3 of those agencies cited the Rule as causing a
    significant change in this area

9
Impacts Assessment (cont.)
  • While planning and designing road projects, the
    agency is expanding planning beyond the project
    work zone itself to address corridor, network,
    and regional issues particularly when
    congestion is an issue.
  • 19 agencies said the Rule had caused this to
    occur
  • 17 agencies said the Rule had not caused change
    because most of those agencies (16) were already
    doing this

10
Impacts Assessment (cont.)
  • Agencies also indicated that they are more often
    using analytical tools to determine WZ impacts
  • 10 to 15 increase in score each of the past 2
    years on the 2 related WZ SA questions
  • During planning to assess impacts of future
    construction/maintenance activities
  • To assess impacts when developing TCPs

11
Significant Project Identification
  • Agencies are thinking more about project impacts
    and are more likely to have a process in place to
    classify projects based on expected impacts
  • As a result, they are better able to assess and
    manage WZ impacts
  • WZ SA shows a 25 increase in score between 2007
    and 2008 in this area
  • Several States said that they organize a team to
    develop the plan for mitigating the impacts of
    significant projects

12
Training
  • Training has been significantly affected by the
    Rule
  • 27 agencies (53) said that as a result of the
    Rule they had updated/changed training for their
    staff (designers, planners, construction staff,
    etc.) to address broader consideration of WZ
    impacts and management in the scheduling, design,
    and implementation of projects
  • 11 of those agencies said they had made
    significant changes in training
  • WZ SA question on law enforcement training saw a
    21 increase in score from 2007 to 2008

13
Training (cont.)
  • The agency has updated/changed training for its
    staff (designers, planners, construction staff,
    etc.) to address broader consideration of work
    zone impacts and management in the scheduling,
    design, and implementation of projects.

14
TMP Development and Implementation
  • Most agencies (90) now have a policy for
    developing TMPs to help manage the WZ impacts of
    a project
  • WZ SA shows a major score increase (20) from
    2006 to 2007 and again from 2007 to 2008
  • Some agencies have developed TMP teams and tools

15
Use of TMP Strategies
  • The agency is expanding WZ management beyond
    traffic safety and control to address mobility
    through the consideration and use of
    transportation operations (TO) and public
    information (PI) strategies.

16
Data Collection and Analysis
  • Increasing number of agencies report they are
    establishing measures and collecting data to
    track WZ congestion and delay
  • Likely related to the addition of operational
    data to data provision when the Rule was updated
  • Agencies establishing measures to track WZ
    congestion and delay increased 26 (from 23 to 29
    agencies) between the 2007 and 2008 WZ SA, which
    continued a significant increase of the year
    before
  • WZ SA indicates a 21 score increase between 2006
    and 2007 and a 15 increase from 2007 to 2008 for
    the question on collecting data to track WZ
    congestion and delay
  • Several agencies have started tracking queues
Write a Comment
User Comments (0)
About PowerShow.com