1
CD DERIVED BIOMASS ENERGY FACILITIES
DEVELOPMENT OPERATIONAL ISSUES PRESENTED
BY Dammon M. Frecker Vice President, Energy
Industrial Services ESS Group, Inc. Wellesley,
MA 781.489.1146 dfrecker_at_essgroup.com

www.essgroup.com
October 28, 2008
2
OVERVIEW
  • Project Concepts
  • Motivators Incentives
  • Licensing Requirements
  • Project Developments Operating Concerns
  • Existing Proposed Projects

3
PROJECT CONCEPTS
  • PROJECT SIZE
  • Typically 15 40 MW
  • Balance revenue, fuel risk, technology and
    impact considerations.
  • 15 30 acres
  • Power island, fuel receiving and storage, water
    treatment, ash handling, administration
  • FUEL REQUIREMENTS
  • 20 MW Plant gt 600 TPD (200,000 TPY)
  • Clean/unadulterated wood?
  • Limits on CD Wood fraction?

4
PROJECT CPROJECT PPPROJECT CONCEPTS
FLUIDIZED BED COMBUSTOR
http//www.energyproducts.com/fluidized_bed_boiler
s.htm
5
PROJECT CONCEPTS
  • IMPACT MITIGATION
  • Enclosed wood storage and conveyors
  • Pollution Control Train
  • SNCR (SCR?) for NOx Control
  • ESP, Fabric Filter (Baghouse) for PM Control
  • Scrubbers (?) for acid gas control
  • Carbon Injection (?) for metals control
  • Enclosed ash handling
  • Enclosed wood grinding
  • Dry Cooling?
  • Zero Liquid Discharge?
  • Rail Access?
  • LOCATION, LOCATION, LOCATION

6
MOTIVATORS INCENTIVES
  • MassDEP Waste Ban
  • Increased wood supply?
  • Renewable Energy Requirements
  • Programs in place in MA, CT and NY
  • Provide added revenue stream
  • Lower Cost Fuel Supply
  • Increasing costs of oil and gas
  • Opportunity for CD wood tipping fee?

7
MOTIVATORS INCENTIVES
  • Climate Change/Greenhouse Gas Initiatives
  • Biomass combustion considered carbon neutral
  • Opportunity for offsets?
  • Production Tax Credits
  • Open-Loop Biomass approved (0.015/kW-hr)

8
MOTIVATORS INCENTIVES
  • Fuel Diversity
  • Increased reliance on natural gas
  • Concerns with gas supply and oil costs
  • Energy Demand
  • ISO-NE forecasted potential shortfalls in 07 and
    beyond
  • Motivate financial markets
  • Ability to feed load pockets?

9
LICENSING REQUIREMENTS
  • Environmental Impact Assessment (e.g. MEPA)
  • Potential triggers
  • Energy facility gt 25 MW (ENF, EIR if required by
    Secretary)
  • Major Source of Air Emissions (ENF, EIR if
    required by Secretary)
  • Solid waste processing, combustion, etc. gt 150
    TPD (ENF EIR)
  • Land Alterationgt 25 acres
  • Rare species, hist/arch, ACEC things to watch
    out for
  • Other agencies cannot issue permits until MEPA is
    complete
  • May take 6-12 months depending on Sectarys
    requirements and availability of information.
  • Solid Waste Site Assignment/Permitting
  • Not required if
  • No processing
  • Valid air permit
  • BUD

10
LICENSING REQUIREMENTS
  • Air Permitting
  • Major CPA Nonattainment Review (MassDEP)
  • PSD Review (EPA in MA and NY)
  • BACT, LAER, Emissions Offsets
  • Up to 190 day application review period
  • Air Toxics Impacts
  • Boiler MACT
  • Local Land Use Zoning
  • Stacks (height, visual impacts, visible plumes)
  • Odors?
  • Traffic (30-40 trucks per day _at_ 20 MW
    employees, other)
  • Water Supply Discharge
  • 500-800K GPD Consumption (wet cooling)

11
OTHER ENVIRONMENTAL CONCERNS
  • Is it Incineration?
  • Moratorium
  • New Source Performance Standards (Sub CCCC -
    CISWI)
  • Is it Solid Waste?
  • Mass probably no, other states probably yes
  • Is it Hazardous Waste?
  • Qualified Renewable or Legislated Illegal?
  • Is the wood clean (enough)?

12
DEVELOPMENT CONCERNS
  • Securing Land
  • Time for Permitting
  • Purchase Power Agreements
  • Long Term REC Agreements
  • Supply and price uncertainty
  • Regulatory uncertainty
  • Securing the fuel supply
  • Financing! (40-80 MM)

13
OPERATIONAL CONCERNS
  • Maintaining Fuel Quality
  • Boiler fouling
  • Emissions
  • Ash Quality
  • Dispatch Order
  • Frequency of startup and shutdown
  • Wood pile management

14
EXISTING FACILITIES
  • BioEnergy, Hopkinton, NH
  • 12.5 MW plant
  • Granted permit for CD in 1984
  • Significant local opposition, but demonstrated
    compliance
  • No Advisory Ruling or SOQ
  • Boralex, Stratton Energy Energy, ME
  • 45 MW plant
  • Re-tooling Advisory Ruling June, 2004
  • 25 CD
  • Greenville Steam Company, ME
  • Re-tooling (BFB) with Advisory Ruling SOQ

15
PROPOSED FACILITIES
  • GenPower Hinsdale, NH Uxbridge, MA
  • Two different Advisory Rulings
  • Emissions not specified
  • Projects announced with some opposition
  • Russel Biomass, Massachusetts
  • 50 MW BFB
  • Clean wood waste e.g. construction demolition
    wood waste
  • Emissions not specified
  • EcoPower, Massachusetts
  • 20 MW plant
  • Advisory Ruling including emissions