Illinois Commerce Commission - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Illinois Commerce Commission

Description:

ILLINOIS COMMERCE COMMISSION Darin Burk Manager Pipeline Safety Distribution Integrity Management * Proposed Rule published in the Federal Register on June 25 ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 16
Provided by: Darin79
Learn more at: http://www.imga.org
Category:

less

Transcript and Presenter's Notes

Title: Illinois Commerce Commission


1
Illinois Commerce Commission
  • Darin Burk
  • Manager Pipeline Safety

2
Distribution Integrity Management
  • Proposed Rule published in the Federal Register
    on June 25, 2008
  • Numerous comments were received by the Pipeline
    and Hazardous Materials Safety Administration
    (PHMSA)
  • Final Rule expected in September of 2009

3
Why is PHMSA Proposing DIMP?
  • Additional prescriptive requirements would bee
    too burdensome on the pipeline industry.
  • More effective to allow operators to analyze
    their system, identify weaknesses that could
    result in high consequence incidents and address
    those weaknesses.

4
Program Implementation
  • Distribution system operators will have 18 months
    from the published date of the final rule to
    develop and implement a Distribution Integrity
    Management Program.
  • The DIMP will address 7 basic elements.

5
Element 1 Knowledge
  • Identify the characteristics of the system and
    the environmental factors necessary to assess
    applicable threats and risks to the system.
  • Understand the design and operation.
  • Identify the additional information needed
  • Determine how to obtain additional information
  • Have a process to refine plan
  • Record data for newly installed facilities

6
Element 2 Identify Threats
  • Threat Categories
  • Corrosion
  • Natural Forces
  • Excavation Damage
  • Other Outside Force
  • Material or Weld Failure
  • Equipment Malfunction
  • Inappropriate Operation
  • Other Concerns

7
Element 3 Evaluate and Prioritize Risk
  • Determine the relative probability of each threat
  • Determine likelihood of failure
  • Determine potential consequences
  • System may be subdivide the system into regions
    of similar characteristics and consistent risk

8
Element 4 Identify and Implement Measures to
Address Risks
  • Effective leak management program
  • Enhanced damage prevention
  • Assuring individual performance (Training
    Operator Qualification)
  • Quality assessment

9
Element 5 Measure Performance, Monitor Results
Evaluate Effectiveness
  • Number of hazardous leaks either eliminated or
    repaired
  • Number of excavation damages
  • Number of excavation tickets
  • Number of EFVs installed
  • Total number of leaks eliminated or repaired
  • Additional measures

10
Element 6 Periodic Evaluation
  • Continually re-evaluate threats and risks on the
    entire system
  • Evaluate the effectiveness of the program for
    assuring individual performance to reduce the
    risk of human error
  • Determine appropriate period for complete program
    re-evaluation based on complexity and changes in
    factors
  • Maximum of 5 year re-evaluation interval

11
Element 7 Reporting Results
  • Must report plastic pipe material failures
    including fittings, couplings, valves, and
    mechanical joints
  • Must be reported no later than 90 days after
    failure
  • Include location, pipe size, material type,
    nature of failure, pipe manufacturer, lot number,
    date of manufacture and other information found
    in markings on failed pipe

12
Excess Flow Valves
  • Required on all single family residences
  • New installations and replacements
  • Not require if
  • System operates below 10 psig
  • Operator has knowledge of contaminates
  • Could interfere with necessary operation and
    maintenance activities
  • If EFV meeting performance standards is not
    available to operator

13
Deviation from Required Inspections
  • Operators will be allowed to propose inspection
    intervals that are outside the current required
    time limits
  • The ICC will review the request and determine if
    the operator will be allowed to extend inspection
    intervals

14
Does This Rule Apply To Master Meter Operators?
  • Yes.
  • Master Meter operators will be required to meet 5
    elements
  • Infrastructure Knowledge
  • Identify Threats
  • Identify Implement Measures to Mitigate Risks
  • Measure Performance, Monitor Results, Evaluate
    Effectiveness
  • Periodic Evaluation and Improvement

15
Questions?
Write a Comment
User Comments (0)
About PowerShow.com