1Status of the LCLS Magnet PS Controls Needed for
First Injection Injector, Sector 21 and BC1 P
Bellomo / A de Lira / K Luchini / D MacNair /
Others
2Background
- Hardware Final Design Review March 30, 2006
- Magnet list in the Hardware FDR
- 89 new magnet control systems
- 6 Intermediate (10kW or 20 kW)
- 83 Small (480W or 1.5kW)
- 1 modified existing QE system in Sector 21
- Software Final Design Review in September
3New Magnet Control Systems in B24
4Sector 21 QE System Modification
5New Systems Hardware Status
- Magnets
- November installation
- DC cables
- Phase 1 installed, Phase 2 completed by
mid-December - Racks, power supplies, PS controllers, terminal
server, VME/PLC crates and modules for small PS - All in B24, except 200V, 50A SOL2 power supply
due September 15, 2006. 15 new MCOR12/6s replace
MCOR30s - PLC, 90 of VME modules here and installed,
remainder October - Move all to Sector 20 on September 15
- AC Power
- Panel-boards exist, CBs and conduit installation
Sep 25 Oct 16
6Modified S21 QE System Hardware Status
- Magnets, DC cables and racks
- 3 feet Bulk PS to new isolation and
reversing/shorting switch chassis - Power supplies and controllers
- QE21201/301 reversing/shorting switch chassis
fabricated and bench tested. - Bulk PS isolation switch chassis fabricated by
9/30 - Install first week of October
- CAMAC crates and modules exist
- AC Control Power
- Exists
7New Systems Design Documentation Status
- DC Cables
- EIs (Change some MCOR30s to MCOR12/6s), CAPTAR
list, power supply spreadsheet - Racks, power supplies, PS controllers VME/PLC
crates, modules and terminal server - Specifications, front views and manufacturers
drawings/manuals, EPICS/VME integration documents - PLC wiring diagram undergoing some changes
- CB hazard analysis completed requested labels
from CEF - Manuals, cable lists
- AC Power
- One lines, panel-board schedules
8Modified S21 QE System Design Documentation
Status
- DC cables
- On modified EI diagram
- Racks and accessories
- Existing one front view needs updating
- Power supplies and controllers
- Bulk PS Isolation chassis and QE201/301 magnet
reversing / shorting switch chassis wiring
diagrams - AC power
- Existing 120VAC control
9New and Modified QE Systems Software Status
- Software
- SLC 90 complete
- SLC Aware coding is complete and debugging 50
done - Displays
- SCP done
- EDM
- Test displays done
- Mockups 80 done
- Main displays 30 done
- Databases
- SLC All new units added to SLC database (MCOR30
to MCOR12) - EPICS
- Templates and databases 90 done
- Substitution databases are 40 done
- Polynomials are 25 done
10New Systems - B24 Testing Status
- Purpose Verify wiring, basic operation as
integrated systems - Controller-Power Supply-Local Mode (25 done)
- BX01, 02 and BXH1,2,3,4 successfully tested
- In process testing PLC, 3 MCOR bulk power
supplies, MCOR12/30s - Then test BXS, SOL1, SOL2, and BX11,12,13,14
- Network/Controller Integration (25 done)
- Network/EPICS integration with Intermediate PS
Controllers - VME integration with MCOR12 and MCOR30
controllers - Remote Mode Network/Power Supply Integration
- Completion September 15, 2006
11New Systems - Field Test Plan
- Three weeks needed in November-December timeframe
- Hi pot DC cables
- DC cable / magnet polarity checks B and V
- Run Intermediates in Local Mode to verify
transductor polarity - Run Intermediates and MCORs in Remote Mode
- Addressing is correct
- Voltage and current compliance
- All readbacks are functional
- Klixon, water flow, ground current interlocks
function and display correct status - Tune response of each system
12Modified S21 QE System Test Plan Last Slide
- Test Plan
- Initial tests 1 week, 2nd week October. Check
field wiring, isolating and reversing/shorting
switch functionality, - Use 3 small (lt 50V, less than 10J) power supplies
- Force EMHP controller bit to SLC/LCLS modes see
table - Integrated tests 1 week, Nov-Dec. Check
SLC/LCLS modes from SCP see table
Bit Bulk PS Q21201 Q21301
SLC I I I
LCLS 0 -I 0