Kapitel 4 / 1 - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

Kapitel 4 / 1

Description:

Flow shop production Object-oriented Assignment is derived from the item s work plans. Uniform material flow: Linear assignment (in most cases) Useful if (and only ... – PowerPoint PPT presentation

Number of Views:81
Avg rating:3.0/5.0
Slides: 38
Provided by: sattler
Category:

less

Transcript and Presenter's Notes

Title: Kapitel 4 / 1


1
Flow shop production
  • Object-oriented
  • Assignment is derived from the items work plans.
  • Uniform material flow
  • Linear assignment (in most cases)
  • Useful if (and only if) only one kind of product
    or a limited amount of different kinds of
    products is manufactured (i.e. low variety high
    volume)

2
Flow shop production
  • According to time-dependencies we distinguish
    between
  • Flow shop production without fixed time
    restriction for each workstation
    (Reihenfertigung)
  • Flow shop prodcution with fixed time restriction
    for each workstation (Assemly line balancing,
    Fließbandabgleich)

3
Flow shop production
  • No fixed time restriction for the workload of
    each workstation
  • Intermediate inventories are needed
  • Material flow should be similiar for all prodcuts
  • Some workstations may be skipped, but going back
    to a previous department is not possible
  • Processing times may differ between products

4
Flow shop production
  • Fixed time restricition (for each workstation)
  • Balancing problems
  • Cycle time (Taktzeit) upper bound for the
    workload of each workstation.
  • Idle time if the workload of a station is
    smaller than the cycle time.
  • Production lines, assembly lines
  • automated system (simultaneous shifting)

5
Assembly line balancing
  • Production rate Reciprocal of cycle time
  • The line proceeds continuously.
  • Workers proceed within their station parallel
    with their workpiece until it reaches the end of
    the station afterwards they return to the begin
    of the station.
  • Further possibilites
  • Line stops during processing time
  • Intermittent transport workpieces are
    transported between the stations.

6
Assembly line balancing
  • Fließbandabstimmung, Fließbandaustaktung,
    Leistungsabstimmung, Bandabgleich
  • The mulit-level production process is
    decomomposed into n operations/tasks for each
    product.
  • Processing time tj for each operation j
  • Restrictions due to production sequence of
    precedences may occur and are displayed using a
    precedence graph
  • Directed graph witout cyles G (V, E, t)
  • No parallel arcs or loops
  • Relation i lt j is true for all (i, j)

7
Example
Operation j Predecessor tj
1 - 6
2 - 9
3 1 4
4 1 5
5 2 4
6 3 2
7 3, 4 3
8 6 7
9 7 3
10 5, 9 1
11 8,1 10
12 11 1
Precedence graph
8
Flow shop production
  • Machines (workstations) are assigned in a row,
    each station containing 1 or more
    operations/tasks.
  • Each operation is assigned to exactly 1 station
  • I before j (i, j) ? E
  • i and j in same station or
  • i in an earlier station than j
  • Assignment of operations to staions
  • Time- or cost oriented objective function
  • Precedence conditions
  • Optimize cycle time
  • Simultaneous determination of number of stations
    and cycle time

9
Single product problems
  • Simple assembly line balancing problem
  • Basic model with alternative objectives

10
Single product problems
  • Assumptions
  • 1 homogenuous product is produced by performing n
    operations
  • given processing times ti for operations j
    1,...,n
  • Precedence graph
  • Same cycle time for all stations
  • fixed starting rate (Anstoßrate)
  • all stations are equally equipped (workers and
    utilities)
  • no parallel stations
  • closed stations
  • workpieces are attached to the line

11
Alternative1
  • Minimization of number of stations m (cycle time
    is given)
  • Cycle time c
  • lower bound for number of stations
  • upper bound for number of stations

12
Alternative 1
  • t(Sk) workload of station k Sk, k 1, ..., m
  • Integer property
  • Sum of inequalities
  • and integer property of m

? tmax t(Sk) gt c i.e. t(Sk) ? c 1 - tmax
? k 1,...,m-1
?
? upper bound
13
Alternative 2
  • Minimization of cycle time
  • (i.e. maximization of prodcution rate)
  • lower bound for cycle time c
  • tmax max tj ? j 1, ... , n processing
    time of longest operation ? c ? tmax
  • Maximum production amount qmax in time horizon T
    is given
  • ?
  • Given number of stations m ?

14
Alternative 2
  • lower bound for cycle time
  • upper bound for cycle time

15
Alternative 3
  • Maximization of efficiency (Bandwirkungsgrad)
  • Determination of
  • Cycle time c
  • Number of stations m
  • ? Efficiency (BG)
  • BG 1 ? 100 efficiency (no idle time)

16
Alternative 3
  • Lower bound for cycle time see Alternative 2
  • Upper bound for cycle time cmax is given
  • Lower bound for number of stations
  • Upper bound for number of stations

17
ExampIe
  • T 7,5 hours
  • Minimum production amount qmin 600 units
  • seconds/unit

18
ExampIe
Arbeitsgang j Vorgänger tj
1 - 6
2 - 9
3 1 4
4 1 5
5 2 4
6 3 2
7 3, 4 3
8 6 7
9 7 3
10 5, 9 1
11 8,1 10
12 11 1
Summe   55
?tj 55 ? No maximum production amount ?
Minimum cycle timecmin tmax 10 seconds/unit
19
ExampIe
Combinations of m and c leading to feasible
solutions.
20
ExampIe
  • maximum BG 1(is reached only with invalid
    values m 1 and c 55)
  • Optimal BG 0,982(feasible values for m and c
    10 ? c ?45 und m ? 2)? m 2 stations? c 28
    seconds/unit

21
Example
  • Possible cycle times c for varying number of
    stations m

Stationen m theoretisch min Taktzeit minimale realisierbare Taktzeit c Bandwirkungsgrad 55/c?m
1 55 nicht möglich da c ? 45 -
2 28 28 0,982
3 19 19 0.965
4 14 15 0,917
5 11 12 0.917
6 10 10 0,917
Increasing cycle time ? Reduction of BG
(increasing idle time) until 1 station can be
omitted. BG has a local maximum for each number
of stations m with the minimum cycle time c where
a feasible solution for m exists.
22
Further objectives
  • Maximization of BG is equivalent to
  • Minimization of total processing time
    (Durchlaufzeit) D m ? c
  • Minimization of sum of idle times
  • Minimization of ratio of idle time LA
    1 BG
  • Minimization of total waiting time

23
LP formulation
  • We distinguish between
  • LP-Formulation for given cycle time
  • LP-Formulation for given number of stations
  • Mathematical formulation for maximization of
    efficiency

24
LP formulation for given cycle time
  • Binary variables
  • number of station, where operation j
    is assigned to
  • Assumption Graph G has only 1 sink, which is
    node n

? j 1, ..., n ? k 1, ..., mmax
25
LP formulation for given cycle time
  • Objective function
  • Constraints
  • ? j 1, ... , n ... j on exactly 1 station
  • k 1, ... , mmax ... Cycle time
  • ... Precedence cond.
  • ?
  • ... Binary variables

? j and k
26
Notes
  • Possible extensions
  • Assignment restrictions (for utilities or
    positions)
  • elimination of variables or fix them to 0
  • Restrictions according to operations
  • Operations h and j with (h, j) ? ? are not
    allowed to be assigned to the same station.

27
LP formulation for given number of stations
  • Replace mmax by the given number of stations m
  • c becomes an additional variable

28
LP formulation for given number of stations
  • Objective function Minimize Z(x, c) c
    cycle time
  • Constraints
  • ? j 1, ... , n ... j on exactly 1 station
  • ? k 1, ... , m ... cycle time
  • ... precedence cond.
  • ?
  • ? j und k ... binary variables

c ? 0 integer
29
LP formulation for maximization of BG
  • If neither cycle time c nor number of stations m
    is given ? take the formulation for given cycle
    time.
  • Objective function (nonlinear)
  • Additional constraintsc ? cmax
  • c ? cmin

30
LP formulation for maximization of BG
  • Derive a LP again ? Weight cycle time and number
    of stations with factors w1 and w2
  • Objective function (linear)
  • Minimize Z(x,c) w1?(?k?xnk) w2?c
  • ? Large Lp-models!
  • ? Many binary variables!

31
Heuristic methods in case of given cycle time
  • Many heuristic methods(mostly priorityrule
    methods)
  • Shortened exact methods
  • Enumerative methods

32
Priorityrule methods
  • Determine a priortity value PVj for each
    operations j
  • Prioritiy list
  • A non-assigned operation j can be assigned to
    station k if
  • all his precedessors are already assigned to a
    station 1,..k and
  • the remaining idle time in station k is equal or
    larger than the processing time of operation j.

33
Priorityrule methods
  • Requirements
  • Cycle time c
  • Operations j1,...,n with processing times tj ? c
  • Precedence graph, defined by a sets of
    precedessors.
  • Variables
  • k number of current station
  • idle time of current station
  • Lp set of already assigned operations
  • Ls sorted list of n operations in respect to
    priority value

34
Priorityrule methods
  • Operation j ? Lp can be assigned, if tj ?
    and h ? Lp is true for all h ? V(j)
  • Start with station 1 and fill one station after
    the other
  • From the list of operations ready to be assigned
    to the current station the highest prioritized is
    taken
  • Open a new station if the current station is
    filled to the maximum

35
Priorityrule methods
  • Start determine list Ls by applying a prioritiy
    rule k 0 LP lt ... No operations
    assigned so far
  • Iteration
  • repeat
  • k k1 c
  • while there is an operation in list Ls that
    can be assigned to station k do
  • begin
  • select and delete the first operation j (that
    can be assigned to) from list Ls
  • Lp lt Lp,j - tj
  • end
  • until Ls lt
  • Result Lp contains a valid sorted list of
    operations with m k stations.

Single-pass- vs. multi-pass-heuristics
(procedure is performed once or several times)
36
Priorityrule methods
  • Rule 1 Random choice of operations
  • Rule 2 Choose operations due to monotonuously
    decreasing (or increasing) processing time PVj
    tj
  • Rule 3 Choose operations due to monotonuously
    decreasing (or increasing) number of direct
    followers PVj ??(j)?
  • Rule 4 Choose operations due to monotonuously
    increasing depths of operations in GPVj
    number of arcs in the longest way from a source
    of the graph to j

37
Priorityrule methods
  • Rule 5 Choose operations due to monotonuously
    decreasing positional weight (Positionswert)
  • Rule 6 Choose operations due to monotonuously
    increasing upper bound for the minimum number of
    stations needed for j and all its
    predecessors
  • Rule 7 Choose operations due to monotonuously
    increasing upper bound for the latest possible
    station of j
Write a Comment
User Comments (0)
About PowerShow.com