Title: Construction Site
1Building Green in Bowling Green
- Construction Site
- Stormwater Management
Barry Tonning Tetra
Tech
2State and local rules require
- Local and state permit coverage
- SWPPP available for review
- BMPs in the field that match the SWPPP
- Contractors weekly inspection forms available
for review
3Minimizing the active construction area
4(No Transcript)
5(No Transcript)
6(No Transcript)
7Consistency between whats in the SWPPP and BMPs
installed in the field
Site Drainage Plan
Site Building Plan
Site Grading Plan
Existing Site Conditions
Final Site Land-scaping Plan
Stormwater Pollution Prevention Plan
8SWPPP Applicability, Preparation, Contents, and
Process for Amending
- SWPPP applies to the site AND offsite
borrow/disposal areas - SWPPP is prepared BEFORE filing the NOI and
beginning work - SWPPP describes site, pollutants at site, plan
for controlling pollutant discharges,
construction procedure, responsible parties - SWPPP is amended by site personnel or project
engineer as construction proceeds on an as-needed
basis
9Basic SWPPP outline
- Site description map
- Description of receiving waters
- Description of construction project
- Identification of pollutants, sources, and any
non-stormwater discharges - Erosion sediment controls
- Controls for other pollutants
- Procedures for inspections, BMP maintenance, and
recordkeeping - Certification signatures
10Building, stabilizing, and preserving the
drainage system (ditches, traps, ponds)
11Drainage system controls
- Inlets for storm drains and channels
- Pond up the runoff to settle filter it
- Use rock berms, rock bags, or other items
- Storm drain channel outlets
- Protect areas receiving discharge flows from
erosion caused by flow velocities - Use rock or turf reinforcement mats seed heavily
- Ditches convey water without eroding
- Traps pond and settle out muddy runoff
12Good application of silt fence and rock bags for
inlet protection Lots of options available
13Other inlet protection approaches
14Outlet Protection
15Drainage ditch liner materials
- Steep or high flow channels (gt 20)
- Use concrete or riprap
- Moderately steep channels ( 10)
- Use riprap or turf mats seeding
- Slightly sloping channels (5)
- Use turf mats or blankets seeding
- Mostly flat channels (2)
- Use seeding with blankets
- Seed ditches immediately after construction
- Triple the seeding rate
16(No Transcript)
17Sediment traps basins
- Designed placed to pool runoff so sediment can
settle out - Installed before grading/fill work begins!
- Seeded immediately after construction
- Located in swales or low-lying areas where flows
are concentrated - Should not be placed near flowing streams
- Outlets should be made of rock or pipe
18Rock filter as sediment trap
19Good siting installation of sediment traps
20Protecting riser during construction! Wrap
with filter fabric Use rock inlet dam Pile
57s around pipe
21(No Transcript)
22Buffer zone requirements
- 25 ft undisturbed buffer between disturbed areas
and bankfull elevation of high quality waters /
impaired waters - 50 buffer required between sediment-impaired
waters with no TMDL and disturbed areas - Dredge/fill areas,
- stream crossings,
- or other deviations
- require adequately
- protective alternate
- practices, explained
- in SWPPP
23Buffer Zone
- Edge of Receiving Water is defined as bankfull
elevation of a water of the Commonwealth
24Slope stabilization
25Slope protection basics
- Seed and mulch immediately after grading
- Divert upland runoff with berms or channels
- Tread-track or terrace highly erodible soils
- Install sediment barriers at toe of slope and at
correct spacing on long slopes - Use blankets, mats, or mulch on steep slopes
- Control runoff from upland areas with drain pipes
or lined downdrain channels
26Mass grading tips
- Install all downgradient silt fences, traps,
basins before clearing grubbing - Use grubbed-out debris as sediment barriers /
berms downhill from your work - Use soil stockpiles as sediment berms / traps
that intercept concentrated/sheet flow - Seed and mulch/blanket/mat your ditches and
slopes as soon as you build them
27Blankets and mats(rolled erosion control
products)
- Excellent for slope and channel protection
- Use blankets for slopes flatter than 31 and
channels flatter than 201 - Use mats for slopes greater than 31 and channels
steeper than 201 - KY TC requires blankets in all channels slopes
gt 41
28Wishful thinking . . .
29Stabilization requirements
- Temporary stabilization required on portions of
the site where construction activities have
temporarily ceased shall be initiated within 14
days - Final stabilization also required within 14 days
after permanently ceasing work - Final stabilization required if work is suspended
for more than 180 days
30Homebuilder lot BMP compliance
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35Fiber roll installation
36Good housekeeping pollution prevention
37Good housekeeping
- Mud tracking on roadways
- Fuel, oil, paint, hazardous waste mgmt
- Concrete washout sites
- Trash debris management
- Sewage management
- Dust control (if needed)
38Waste management
- Provide convenient, well-maintained toilet
facilities
39(No Transcript)
40Establish proper building material handling and
storage areas
- Building materials with runoff potential should
be stored indoors or under cover
41Designate concrete washout areas Or wash out
material in formed-up areas ready for the next
pour
42(No Transcript)
43(No Transcript)
44Establish proper equipment/vehicle fueling and
maintenance practices
- Your on-site fueling and maintenance area should
have a spill kit - Conduct vehicle fueling and maintenance
activities in areas away from ditches - Conduct maintenance on vehicles and equipment
off-site if possible
45Develop a spill prevention and response plan
- Note the locations of chemical storage areas,
storm drains, ditches, and surface waters - Specify how to notify appropriate authorities
- Describe the procedures for spill cleanup
- Identify personnel responsible for implementing
the plan
46The Good, The Bad, and the Ugly
- The Good stabilized exit pads, initial silt
fence installation, initial inlet protection - The Bad temporary seeding/mulching, silt fence
maintenance, inlet maintenance, waste and
materials management - The Ugly ditch and channel protection, some
homebuilder lots
47Fair construction entrance poor silt fence
48Good fence, needs seed/mulch
49Good inlet protection
50Good stabilization on pipe job
51Well vegetated sediment basin, with poorly
vegetated inactive area in foreground
52Poor vegetation and no sign of active grading
53Unstabilized slope
54Lot with poor vegetation and poor silt fencing
55Lack of inlet maintenance and sediment management
56Poor stabilization drainage management
Left northwest corner discharge location,
showing sediment in discharge. Right stopped up
curb inlet (lower middle) with pooled water. No
grading occurring in this area.
57Eroding, unstabilized drainage swale
58Poor site stabilization, drainage system, and
sediment trap construction maintenance
59Overflowing concrete washout
60Vacant inactive site with poorly installed silt
fence and poor vegetation
61Poor soil stabilization, shaky silt fence,
ineffective inlet protection
62Torn and frayed
63Poor site management