Title: d.
1 Innovative Project Delivery Processes
d.
delivers
FAISAL HAMEED RONALDO T. NICHOLSON. P.E.
district department of transportation
2Overview
- Use of Programmatic Agreements
- Public Agency Coordination
- Agency Review and Decision Making
- Context Sensitive Alternatives Development
- Scope of Preliminary Design
- Enhanced Technical Assistance
- Design- Build
- Design-Build to Budget
- Other Innovative Delivery Methods
3 Planning Project Development
FAISAL HAMEED Division Chief Project Development,
Environment Sustainability Division Faisal.hamee
d_at_dc.gov
d.
delivers
district department of transportation
4Use of Programmatic Agreements
- NEPA / Cat Ex
- Section 106
- Others
5Public Agency Coordination
- FHWA
- NPS
- USACE
- NMF
- USCG
- EPA
- DDOE
- DCSHPO
- DMPED
- DCOP
- NCPC
- CFA
- DOD
- WASA
6Agency Review and Decision Making
- In time decision making
- Decision workshops
- Leadership buy-in
7Context Sensitive Alternative Development
Engineering Design
Transportation elements ( Capacity, lane width,
etc)
Cost
8(No Transcript)
9(No Transcript)
10Scope of Preliminary Design
Preliminary Design 23 CFR 636.103 Preliminary
design defines the general project location and
design concepts. It includes, but is not limited
to, preliminary engineering and other activities
and analyses, such as environmental assessments,
topographic surveys, metes and bounds surveys,
geotechnical investigations, hydrologic analysis,
hydraulic analysis, utility engineering, traffic
studies, financial plans, revenue estimates,
hazardous materials assessments, general
estimates of the types and quantities of
materials, and other work needed to establish
parameters for the final design. Prior to
completion of the NEPA review process, any such
preliminary engineering and other activities and
analyses must not materially affect the objective
consideration of alternatives in the NEPA review
process Linking Planning NEPA Enhanced
Technical Assistance
11 Design Construction
RONALDO T. NICHOLSON, P.E. Deputy Director/Chief
Engineer Ronaldo.nicholson_at_dc.gov
d.
delivers
district department of transportation
12Design-Build
- Administered by Eastern Federal Lands of FHWA.
Completed in 2002 general SOW was to provide
comprehensive design construction services
throughout Wards 3 4, to include design
construction of 108 local streets, totaling
approximately 17 miles of urban roadway. - Selection process 2-step shortlisted 3 DB
contractors, based on RFQ submittal. Selected DB
contractor based on best value which included
technical, managerial qualifications, past
performance and cost - Construction cost 35 million
- Contractor Fort Myer Construction Company
/Parsons Transportation Group (Joint Venture) - Result was substantial time and cost savings
Rehabilitation of 108 Streets in Wards 3 4
13Southern Avenue Bridge over Suitland Parkway
- Year completed 2006
- General Scope of Work Complete replacement of
existing bridge - Selection process Two-step DB (Technical/Cost
proposal) - Construction Cost - 9.5 Million
- Project Outcome Innovative construction phasing
sequence/MOT/Cost/Time - Contractor Shirley Contracting/Wilbur Smith
Associates
149th Street Bridge, N.E.
- Year completed 2011
- General scope of work Complete replacement of
existing bridge - Selection process A two-phase DB (selection
based on railroad experience, best value,
tech/cost) - Construction cost - 55 Million
- Project Outcome Very successful DB project
project delivered on time, within budget, good
railroad coordination maintained existing bridge
for traffic during reconstruction - Contractor Cherry Hill/JMT
15Design-Build to Budget
16Design-Build to Budget11th Street Project
- EIS Proposed Cost
- 459 million
- Funds available
- 300 million
- Bridges deteriorating
17Procurement Process
- Identify Project or Program
- Set Project or Program Goals
- Prioritize Goals
- Identify Risk
- Allocate/Mitigate Risk
- Complete Pre-Procurement Planning
- Implement Procurement Process
- Manage the Program Post Award
18Design-Build to Budget11th Street Project Goals
- Budget - Deliver the corridor improvements with
the total construction budget of 260 million. - Mobility - Maximize the potential to support
multiple modes of transportation on the local
bridge. - Schedule - Meet or beat the construction
completion date of December 31, 2013. - Maintenance of Traffic - Maximize accessibility
and mobility during construction. - Public Information - Provide timely and accurate
information regarding project progress and
activities to the public.
19Key 11th Street Bridge Project Aspects
- Improve mobility by removing freeway traffic from
local connections - Provide shared pedestrian/bicycle path and future
streetcars - Provide alternative evacuation route from
Nations capitol - Environmental investments
20Lessons Learned from Design-Build
- Continual flexibility
- Executive level support
- Quick response times
- ATC/RFI reviews are managed
- Can approve with conditions
- Must empower decision makers
- Must have a complete handle on finances and
schedule
21Current Innovative Delivery Methods
- Turnkey Maintenance Contracts
- CM/GC (Hybrid)
- P3 Efforts
22Awards
- FHWA Environmental Excellence Award 2009 for
Streamlining - ACEC 2009 Design Build national award
23 Innovative Project Delivery Processes QUESTIONS?
RONALDO T. NICHOLSON, P.E. Deputy Director/Chief
Engineer Ronaldo.nicholson_at_dc.gov FAISAL
HAMEED Division Chief Project Development,
Environment Sustainability Division Faisal.hamee
d_at_dc.gov
d.
delivers
district department of transportation