Title: Electron Beam Systems ETC and Methodology
1Electron Beam SystemsETC and Methodology
David Schultz E-Beams Systems Manager
- Electron Beam Systems
- Definition of terms
- Schedule Overview
- Start-Up Test Plan
- E-Beams Costs
- Risk Analysis
2E-Beams Systems layout
Sector 21
Sector 20
Laser lab
BC1
LX
L1
Injector
Injector Commissioning complete
3The electron gun in the Injector
Laser beam transport
Electron gun
4E-Beams Systems layout
6 MeV
250 MeV
4.30 GeV
13.6 GeV
135 MeV
Linac-X L 0.6 m
Linac-0 L 6 m
rf gun
Linac-1 L ?9 m
Linac-2 L ?330 m
Linac-3 L ?550 m
Commissioned
Now Installing
...existing linac
undulator L 130 m
X
BC2 L ?22 m
BC1 L ?6 m
LTU L 275 m
L2/BC2/L3
Injector/BC1
SLAC linac tunnel
research yard
5E-Beams Systems layout
Beam Transport Hall Transport the electron beam
to the Undulator
Undulator Hall Underground tunnel housing the
undulator.
Controls Beamline and diagnostics control for
e-beams systems.
SLAC Linac LCLS uses the last 1/3 of the
existing Linac.
Electron Beam Dump Underground facility for the
beam dump.
Near and Far Halls Areas for x-ray experiments
6E-Beams Systems WBS structure
- Injector WBS 1.02, 2.02
- Jose Chan, Control Account Manager
- Laser/Gun/L0/Spectrometer
- Installed and commissioned
- Create electrons, accelerate, analyze beam quality
- Laser Heater
- Accelerator RD activity
7E-Beams Systems WBS structure
- Linac WBS 1.03, 2.03
- Jose Chan, CAM
- L1/Lx/BC1 Installed and commissioned
- Accelerate the beam,
- initial beam bunch compression
- L2/BC2/L3
- Full beam acceleration,
- second compression of bunch
- LTU
- Transport electron beam from Linac to Undulator
- Electron dump
- Safely dispose of the electron beam
8E-Beams Systems WBS structure
- Undulator WBS 1.04, 2.04
- Generate x-rays as the high power electron beam
passes through. - Undulator Systems at ANL, Geoff Pile, CAM
- Fabricate components and supports for the
Undulator system - Undulator Integration at SLAC, Rodd Pope, CAM
- Tune, fiducialize, assemble, and install the
Undulator system
9E-Beams Systems WBS structure
- Accelerator Controls WBS 1.02.02, 2.02.02,
- 1.03.02, 2.03.02, 1.04.02,
2.04.02 - Hamid Shoaee, CAM
- Controlling hardware, cable plant and software
for Injector, Linac and Undulator Systems - Commissioning WBS 2.01.01, 2.02.17,
- 2.03.07, 2.04.06
- David Schultz, CAM
- LOE manpower for LCLS personnel and maintenance
groups during the electron beam commissioning
process.
10System Design Management
- System engineering resource loaded schedule is
controlled through P3. - Design process
- Interface Control Documents specify which group
has responsibility for each system. - Physics Requirements Documents are written by the
LCLS Physics group specifying subsystem needs. - Engineering group holds Design Reviews, and
writes Engineering Specification Documents to
detail how the PRD is to be satisfied. - Physicists and Engineers sign-off on component
assembly and testing prior to installation.
11E-Beams Systems Level 3 Milestones
L3 milestones sufficient and properly distributed
to monitor performance.
12E-Beams Systems Level 3 Milestones
13LCLS Installation and Commissioning Time-Line
X-ray tunnel/FEH Install
LTU/Und/Dump Install
FEH X-rays milestone
Flux milestone
CF Early Occupancy
CD-4 (7/30/10)
FEE/NEH Install
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
2007
2008
2009
2010
PPS
PPS
LTU/Und Commissioning
Tunnel/FEH Commissioning
Linac/BC2 Commissioning
Linac/BC2 Install
FEE/NEH Commissioning
14Start Up Test Planning
- LCLS Safety Assessment Document is due 7/2008
- LCLS Accelerator Readiness Review is needed
10/2008 - Systems installed, checked out, signed off by
responsible parties. - Safety officers signoffs on approvals and
installations. - Safety specific systems (Personnel Protection)
certified. - Maintenance groups have procedures and training
in place. - Procedures in place for Operations, and Operators
trained. - Beam Authorization Sheet prepared.
- Detailed commissioning schedule and performance
goals are produced by the LCLS Physics group. - Approval to begin commissioning given by the
Directors office
15E-Beams Systems Cost Estimation
- As installation is approaching, systems are well
defined. - Installation costs
- Based on experience in 2006 Injector
installation. - Hardware install estimate done top-down and
bottom-up. - Based on experience on undulator prototype at
ANL. - Cable plant install estimated using R.S. Means.
- Fabrication/procurement
- Costs based on quotes and experience with
prototypes at SLAC and ANL. - Engineering and Commissioning
- Timetable for completion well understood.
16Risk Assessment
- Design maturity and cost/schedule exposure are
used in the contingency analysis for all DCE
activities. - Major risks are identified as Risk Registry
entries, and assessed and maintained by the
System Manager. - The Senior Management team reviews the Registry
monthly. - Summary of E-Beams Systems entries
- Linac (2)
- Risk Linac diagnostics may need to be enhanced
to have sufficient sensitivity for FEL
commissioning. - Mitigation The upcoming BC2 commissioning will
determine if an upgrade is warranted.
17Risk registry
- Summary of entries (cont.)
- Undulator (3)
- The assembly of the Undulator Girders is a
pacing item for Undulator commissioning. - Several components from ANL are close to being
the limiting factor - Risk Any rework or modification of parts at SLAC
will delay girder assembly. - Mitigation We have multiple weekly video
meetings with ANL and quarterly Undulator
collaboration meetings to ensure coordination. - Integration engineers at ANL and at SLAC have
been established to coordinate the receipt and
assembly.
18Summary
- Electron Beams Systems are approaching final
installation. - Systems are well defined,
- Based on Project documentation.
- Resource loaded schedule in P3.
- Costs have a solid basis.
- The start up test plan is based on the successful
turn-on of the LCLS Injector. - Identified risks are being controlled.