Title: Large Wind Integration Impacts on Operations
1Large Wind Integration Challenges for Operations
/ System Reliability
By Steve Enyeart, BPA With contributions
from Bart McManus, BPA Roy Ellis, BPA Dmitry
Kosterev 2/12/08 Photo courtesy of PPM Energy
2NW Wind Integration Action Plan Summary
- NW added 900 MW of wind in 2007, gt2200 MW Total
now - Total Wind in the NW Forecast 3500 - 3800 MW by
end of 2009 - Northwest Wind Integration Forum formed to
Address - Transmission System Expansion and Funding
- Wind Integration Costs and Cost Shifts from Load
to Wind Generation - Operating Issues including Regulation and Balance
of Hour - A Regional Wind Forecasting System
- ACE Diversity Interchange and other Control Area
sharing ideas to increase flexibility for Wind
Integration - Severe Wind Ramps Impact on Reliability
3Impact of State RPS Requirements
- Montana, Washington, and Oregon have implemented
Renewable Portfolio Stds - According to the estimates from the NW Power
Council - Oregon 15 by 2015 - 650 aMW, 25 by 2025
- Washington 7.5 by 2015 672 aMW, 15 by 2020
- Wind is the primary Renewable Resource at this
time - Assume 1400 aMW _at_ 30 equals 4700 MW peak
capacity. This and export of 2000 MW would be
7, 000 MW by 2015. - BPA has provided interconnection for 3500 MW at
various locations and Rock Creek, John Day 500 kV
interconnects (1200 MW each). - Other NW Utilities have connected over 800 MW
with plans for more.
4(No Transcript)
5Wind Gen. within BPA Control Area (BAA)
- BPA integrated 650 MW in 2007, total 1400 MW,
may be 3000 MW by late 2009 - Queue requests exceed 10,000 MW under study (due
in part to BPA transmission location relative to
wind resources) - Present 1400 MW, 15 of 9000 MW Peak BPA Load,
higher than any BAA in US. - BPA Addressing
- Intra-hour increases in total Balancing
requirements - Impact of severe wind ramps on Balancing Capacity
- Cost/Cost Shift of addl Balancing Capacity
- Need for Voltage Support, Dynamic VAr
- Balancing within 1 Minute Regulation (AGC
response) Load Following for balance of hour
schedule see next slide
6Within Hour Balancing Definitions
- Regulation minute-minute difference between
generation and load (AGC). - Following is defined as the change in the general
trend over a specific time interval 5, 10, 15 or
even 60 minutes. - Within-Hour Balancing Load Following
Regulation
Within Hour Balancing defined as the with-in hour
generation adjustments for variances of Load /
variable (wind) Generation New Requirement for
Wind Generation
7(No Transcript)
8Wind Balancing Analysis
- As previous slide demonstrates, Wind Generation
is quite variable, impacting BAA Balancing and
total AGC Capacity Requirements. - The next slide shows the balancing required for a
recent large wind ramp. Not nearly as extreme as
the previous slide would have implied. - The 2nd slide shows the balancing required for
simulated period for total wind of 2700 MW. Note
the peak Balancing required.
9Regulation versus Following (Wind Example)
102700 MW Simulated Balancing Capacity Requirements
2nd 3 week Period Simulation
11Wind Balancing Analysis (Cont.)
- The next slide shows the problems with scheduled
vs actual (even with hourly adjustments) Note
that scheduled trails actual and misses peaks and
valleys. - This increases Within-Hour Balancing reserves
requirements. - Better forecasts would reduce this problem.
- The 2nd slide is Frequency Distribution Analysis
for total Balancing Capacity requirements
assuming 5000 MW.
12Schedule Vs. Actual 12/27 12/29 2007
lt Actual
Note - Wind acts more like load - generation
seldom matches schedule, and - Good hourly
schedule will still increase Balancing Capacity
requirements.
13Example Frequency Distribution of Wind
Generation Variation
14Wind Within-Hour Balancing Analysis
- The next slide BPA estimates the increase in
Balancing Capacity required for up to 2880 MW. - Cumulative Frequency Distribution method used to
calculate increase in Balancing Capacity,
assuming 97.5 of Regulation and 95 Balance of
Hour events are covered. - The Tail events from the previous slide
indicate that some wind ramps could exceed
Balancing Capacity. Options include - Increase Balancing Capacity More cost to all
wind farms - Wind Ramp Controls to limit severe ramps
- Other BA tools like shared ACE
- Analysis includes using locations of proposed
wind sites in BPA queue to provide simulation of
locational diversity.
15(No Transcript)
16Wind Ramps
- Wind Ramps are large unscheduled changes in the
output of a wind farm or the aggregate of all
wind farms in a Control Area. - As seen above Wind increases Balancing Capacity
Requirements. - BPA now Concerned for Reliability Impacts (CPS2
Violations). - Late fall 2007 BPA experienced increase in
within-hour Balancing due to wind. CPS2
Violations are also increasing. - Wind Ramp Controls now considered necessary and
may be implemented in some form in the next year.
17Improved AGC Response
- Improving the AGC response to deviations of the
load-generation balance due to wind generation is
one option to reducing overall wind integration
costs. - BPA Proposal Modify AGC Algorithm (Feed
Forward AGC) - Present AGC Actual Load Scheduled Generation
(includes Wind schedules) - New AGC Load Forecaster Scheduled Generation
Forecasted Wind Generation - Goal is to anticipate AGC response, reduce
overshoot, cycling of units (wear and tear) and
minimize generation on stand-by. - Load Forecaster module to also be included in
FF AGC.
18Wind Forecast Module for FF AGC
- Develop 5 minute within-hour wind generation
forecasts enhanced with weather and regional
monitoring of wind generation. - Uses Data (MW, wind speed, direction, unit
status) from WTGs in Wind Farm, from all wind
farms in BAA - Other goals
- Provide output to adjust FCRPS generation
schedules (mid-hour adjustment), reducing AGC
units on stand-by or set aside for AGC. - Provide mechanism to automate Wind Ramp Limits
control if Balancing reserves below minimum
capability (next 10 30 minutes). - Pilot Project underway with 3-Tier to provide
Forecasts - Target Mid 2009 to have Pilot FF AGC implemented
19BPA Wind Integration Rate
- Traditionally Loads have paid for regulation and
load following as generation deviations were rare
not so for wind. - BPA held Public workshops to develop a new Wind
Integration Rate for within-hour balancing.
(Public review still underway). - Rate to be applied to Wind Generation
- Rate to be effective for a one-year period, FY
2009 - Rate will be based on installed capacity during
rate period - Assumes 2240 MW up to 2880 MW in BPA Control Area
- Estimates up to 23M needed for FY09 rate period
20Wind Farm Dynamic Voltage Performance
- Early WTG designs were mostly induction machines
(used switched caps for PF correction) - Voltage control was limited to switched Caps on
34.5kV bus - Integration of large amounts of wind generation
requires dynamic reactive control capabilities - Need to match Synchronous Machines performance to
maintain system performance and line loadings. - Next slide compares effect of 2700 MW of wind on
grid without Dynamic VAr support to synchronous
generation response
21Dynamic Simulations - Malin 500-kV bus voltage
Baseline 2700 MW of Wind with No Voltage
Control replaced 2700 MW of hydro thermal
22Wind Farm Voltage Controller Requirements
- Voltage control of wind farms required to provide
primary voltage support for system events.
Options include - High side Voltage Control (may be overly
sensitive) - Low side Voltage Control (may be too insensitive
for system response) - Line Drop reactive compensated Voltage Control
(Qdroop) - Line Drop adjustable up to15 (mid-line subgrid
applications), for 7.5 typical applications
allows for fine tuning of VC. - Next slide demonstrates Line Drop options
23Voltage Control Types
POI Voltage
High Side Voltage Control
VC with 7.5 Reactive Droop
VC with 15 Reactive Droop Low Side Voltage
Control
Power Factor / VAR Control
POI Reactive Power
24Wind Farm Dynamic Performance Summary
- For Large Wind Generation BPA Requires -
Controllable Dynamic VAr devices required (either
WTG or DVAr devices) - Voltage control mode required (no PF control) to
provide primary voltage support for system events - Type of voltage control depends on application,
but Line Drop compensation preferred for
flexibility of Application. - Smaller Wind farms or those in mid-line or remote
areas will still need to be evaluated on
case-by-case basis.
25Summary Wind Integration for BPA
- BPA continues to study a lot of wind
interconnection requests (presently gt9000 MW in
study queue) - Total 1400 MW now interconnected and operating,
may be 3000 MW by late 2009. Operation
Challenges to be Addressed - Regulation/Balance of Hour AGC/reserve
requirements are increasing and are being
addressed with new rate - FF AGC should reduce impact and cost of Wind in
BAA - Wind ramp controls may be needed for Reliability
- Dynamic VAr for Voltage control needed to
maintain system capacity and reliability
26Questions?