Large Wind Integration Impacts on Operations - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Large Wind Integration Impacts on Operations

Description:

Large Wind Integration Challenges for Operations / System Reliability By : Steve Enyeart, BPA With contributions from: Bart McManus, BPA Roy Ellis, BPA – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 27
Provided by: SteveE80
Category:

less

Transcript and Presenter's Notes

Title: Large Wind Integration Impacts on Operations


1
Large Wind Integration Challenges for Operations
/ System Reliability
By Steve Enyeart, BPA With contributions
from Bart McManus, BPA Roy Ellis, BPA Dmitry
Kosterev 2/12/08 Photo courtesy of PPM Energy
2
NW Wind Integration Action Plan Summary
  • NW added 900 MW of wind in 2007, gt2200 MW Total
    now
  • Total Wind in the NW Forecast 3500 - 3800 MW by
    end of 2009
  • Northwest Wind Integration Forum formed to
    Address
  • Transmission System Expansion and Funding
  • Wind Integration Costs and Cost Shifts from Load
    to Wind Generation
  • Operating Issues including Regulation and Balance
    of Hour
  • A Regional Wind Forecasting System
  • ACE Diversity Interchange and other Control Area
    sharing ideas to increase flexibility for Wind
    Integration
  • Severe Wind Ramps Impact on Reliability

3
Impact of State RPS Requirements
  • Montana, Washington, and Oregon have implemented
    Renewable Portfolio Stds
  • According to the estimates from the NW Power
    Council
  • Oregon 15 by 2015 - 650 aMW, 25 by 2025
  • Washington 7.5 by 2015 672 aMW, 15 by 2020
  • Wind is the primary Renewable Resource at this
    time
  • Assume 1400 aMW _at_ 30 equals 4700 MW peak
    capacity. This and export of 2000 MW would be
    7, 000 MW by 2015.
  • BPA has provided interconnection for 3500 MW at
    various locations and Rock Creek, John Day 500 kV
    interconnects (1200 MW each).
  • Other NW Utilities have connected over 800 MW
    with plans for more.

4
(No Transcript)
5
Wind Gen. within BPA Control Area (BAA)
  • BPA integrated 650 MW in 2007, total 1400 MW,
    may be 3000 MW by late 2009
  • Queue requests exceed 10,000 MW under study (due
    in part to BPA transmission location relative to
    wind resources)
  • Present 1400 MW, 15 of 9000 MW Peak BPA Load,
    higher than any BAA in US.
  • BPA Addressing
  • Intra-hour increases in total Balancing
    requirements
  • Impact of severe wind ramps on Balancing Capacity
  • Cost/Cost Shift of addl Balancing Capacity
  • Need for Voltage Support, Dynamic VAr
  • Balancing within 1 Minute Regulation (AGC
    response) Load Following for balance of hour
    schedule see next slide

6
Within Hour Balancing Definitions
  • Regulation minute-minute difference between
    generation and load (AGC).
  • Following is defined as the change in the general
    trend over a specific time interval 5, 10, 15 or
    even 60 minutes.
  • Within-Hour Balancing Load Following
    Regulation



Within Hour Balancing defined as the with-in hour
generation adjustments for variances of Load /
variable (wind) Generation New Requirement for
Wind Generation
7
(No Transcript)
8
Wind Balancing Analysis
  • As previous slide demonstrates, Wind Generation
    is quite variable, impacting BAA Balancing and
    total AGC Capacity Requirements.
  • The next slide shows the balancing required for a
    recent large wind ramp. Not nearly as extreme as
    the previous slide would have implied.
  • The 2nd slide shows the balancing required for
    simulated period for total wind of 2700 MW. Note
    the peak Balancing required.

9
Regulation versus Following (Wind Example)
10
2700 MW Simulated Balancing Capacity Requirements
2nd 3 week Period Simulation
11
Wind Balancing Analysis (Cont.)
  • The next slide shows the problems with scheduled
    vs actual (even with hourly adjustments) Note
    that scheduled trails actual and misses peaks and
    valleys.
  • This increases Within-Hour Balancing reserves
    requirements.
  • Better forecasts would reduce this problem.
  • The 2nd slide is Frequency Distribution Analysis
    for total Balancing Capacity requirements
    assuming 5000 MW.

12
Schedule Vs. Actual 12/27 12/29 2007
lt Actual
Note - Wind acts more like load - generation
seldom matches schedule, and - Good hourly
schedule will still increase Balancing Capacity
requirements.
13
Example Frequency Distribution of Wind
Generation Variation
14
Wind Within-Hour Balancing Analysis
  • The next slide BPA estimates the increase in
    Balancing Capacity required for up to 2880 MW.
  • Cumulative Frequency Distribution method used to
    calculate increase in Balancing Capacity,
    assuming 97.5 of Regulation and 95 Balance of
    Hour events are covered.
  • The Tail events from the previous slide
    indicate that some wind ramps could exceed
    Balancing Capacity. Options include
  • Increase Balancing Capacity More cost to all
    wind farms
  • Wind Ramp Controls to limit severe ramps
  • Other BA tools like shared ACE
  • Analysis includes using locations of proposed
    wind sites in BPA queue to provide simulation of
    locational diversity.

15
(No Transcript)
16
Wind Ramps
  • Wind Ramps are large unscheduled changes in the
    output of a wind farm or the aggregate of all
    wind farms in a Control Area.
  • As seen above Wind increases Balancing Capacity
    Requirements.
  • BPA now Concerned for Reliability Impacts (CPS2
    Violations).
  • Late fall 2007 BPA experienced increase in
    within-hour Balancing due to wind. CPS2
    Violations are also increasing.
  • Wind Ramp Controls now considered necessary and
    may be implemented in some form in the next year.

17
Improved AGC Response
  • Improving the AGC response to deviations of the
    load-generation balance due to wind generation is
    one option to reducing overall wind integration
    costs.
  • BPA Proposal Modify AGC Algorithm (Feed
    Forward AGC)
  • Present AGC Actual Load Scheduled Generation
    (includes Wind schedules)
  • New AGC Load Forecaster Scheduled Generation
    Forecasted Wind Generation
  • Goal is to anticipate AGC response, reduce
    overshoot, cycling of units (wear and tear) and
    minimize generation on stand-by.
  • Load Forecaster module to also be included in
    FF AGC.

18
Wind Forecast Module for FF AGC
  • Develop 5 minute within-hour wind generation
    forecasts enhanced with weather and regional
    monitoring of wind generation.
  • Uses Data (MW, wind speed, direction, unit
    status) from WTGs in Wind Farm, from all wind
    farms in BAA
  • Other goals
  • Provide output to adjust FCRPS generation
    schedules (mid-hour adjustment), reducing AGC
    units on stand-by or set aside for AGC.
  • Provide mechanism to automate Wind Ramp Limits
    control if Balancing reserves below minimum
    capability (next 10 30 minutes).
  • Pilot Project underway with 3-Tier to provide
    Forecasts
  • Target Mid 2009 to have Pilot FF AGC implemented

19
BPA Wind Integration Rate
  • Traditionally Loads have paid for regulation and
    load following as generation deviations were rare
    not so for wind.
  • BPA held Public workshops to develop a new Wind
    Integration Rate for within-hour balancing.
    (Public review still underway).
  • Rate to be applied to Wind Generation
  • Rate to be effective for a one-year period, FY
    2009
  • Rate will be based on installed capacity during
    rate period
  • Assumes 2240 MW up to 2880 MW in BPA Control Area
  • Estimates up to 23M needed for FY09 rate period

20
Wind Farm Dynamic Voltage Performance
  • Early WTG designs were mostly induction machines
    (used switched caps for PF correction)
  • Voltage control was limited to switched Caps on
    34.5kV bus
  • Integration of large amounts of wind generation
    requires dynamic reactive control capabilities
  • Need to match Synchronous Machines performance to
    maintain system performance and line loadings.
  • Next slide compares effect of 2700 MW of wind on
    grid without Dynamic VAr support to synchronous
    generation response

21
Dynamic Simulations - Malin 500-kV bus voltage
Baseline 2700 MW of Wind with No Voltage
Control replaced 2700 MW of hydro thermal
22
Wind Farm Voltage Controller Requirements
  • Voltage control of wind farms required to provide
    primary voltage support for system events.
    Options include
  • High side Voltage Control (may be overly
    sensitive)
  • Low side Voltage Control (may be too insensitive
    for system response)
  • Line Drop reactive compensated Voltage Control
    (Qdroop)
  • Line Drop adjustable up to15 (mid-line subgrid
    applications), for 7.5 typical applications
    allows for fine tuning of VC.
  • Next slide demonstrates Line Drop options

23
Voltage Control Types
POI Voltage
High Side Voltage Control
VC with 7.5 Reactive Droop
VC with 15 Reactive Droop Low Side Voltage
Control
Power Factor / VAR Control
POI Reactive Power
24
Wind Farm Dynamic Performance Summary
  • For Large Wind Generation BPA Requires -
    Controllable Dynamic VAr devices required (either
    WTG or DVAr devices)
  • Voltage control mode required (no PF control) to
    provide primary voltage support for system events
  • Type of voltage control depends on application,
    but Line Drop compensation preferred for
    flexibility of Application.
  • Smaller Wind farms or those in mid-line or remote
    areas will still need to be evaluated on
    case-by-case basis.

25
Summary Wind Integration for BPA
  • BPA continues to study a lot of wind
    interconnection requests (presently gt9000 MW in
    study queue)
  • Total 1400 MW now interconnected and operating,
    may be 3000 MW by late 2009. Operation
    Challenges to be Addressed
  • Regulation/Balance of Hour AGC/reserve
    requirements are increasing and are being
    addressed with new rate
  • FF AGC should reduce impact and cost of Wind in
    BAA
  • Wind ramp controls may be needed for Reliability
  • Dynamic VAr for Voltage control needed to
    maintain system capacity and reliability

26
Questions?
Write a Comment
User Comments (0)
About PowerShow.com