Title: CIRED 2011RT 5b
1CIRED 2011RT 5b
- TSO-DSO co-ordination of planning for wind
connections
Tony Hearne Manager, Renewable Planning ESB
Networks
2Topics
- Utility Landscape in Ireland
- Wind situation in Ireland
- Group processing
- Gate 3
- Conclusions
3Topics
- Utility Landscape in Ireland
- Wind situation in Ireland
- Group processing
- Gate 3
- Conclusions
4Main Players in Ireland
- Regulator
- Transmission System Operator
- Transmission System Planner
- Distribution System Operator
- Distribution System Planner
- Transmission and Distribution Asset owner
- CER
- EirGrid
- EirGrid
- ESB Networks
- ESB Networks
- ESB
5System Operator Structures
ESB Group Generation- Customer supply Consultancy
- Eirgrid PLC
- TSO
- Plan Tx network
- Contol access to Tx network
- Operate Tx network
- SEMO
- Operate wholsale energy market
- ESB Networks Ltd
- TAO
- DAO
- DSO
6Transmission
Distribution
MV 20 kV 10 kV
LV 400 230 V
220kV 400kV
400kV
220kV
110kV
110kV
38kV
20kV 10kV
- Transmission
- 6,300 km of Overhead Network
- 140km of Underground Cables
- 165 HV Stations
- Distribution
- 160,000 km of Lines/Cables
- 630 HV Substations
- 230,000 MV Transformers/Units
- 2m meters
1B RAB Value
5B RAB Value
7Topics
- Utility Landscape in Ireland
- Wind situation in Ireland
- Group processing
- Gate 3
- Conclusions
8(No Transcript)
9 Wind Connections MW
System Demand 2020
3990
1460 MW
c1250
10(No Transcript)
11History to date
- Up to 2003 applications for connection of wind to
both System Operators were processed sequentially - Since 2004, following a moratorium on wind
connections, such is the volume of applications
in the queue, that a Group Processing Approach
GPA was the only practical way forward. - They are now processed in batches known as Gates
Gate Size MW Year Take up of offers
1 370 2005 100
2 1385 2007 100
3 3900 2011 Offers issue nearing completion
12Connected Blue
In Progress Red
Being Quoted Green
13Topics
- Utility Landscape in Ireland
- Wind situation in Ireland
- Group processing
- Gate 3
- Conclusions
14Example of Sequential Approach
MV
38kV
38kV/MV Stn
38kV
38kV
110/38kV Stn
38kV/MV Stn
110kV
15Example of Sequential Approach
MV
?
38kV
38kV/MV Stn
38kV
38kV
110/38kV Stn
38kV/MV Stn
110kV
16Example of Group Approach
110kV
38kV
38kV
38kV/MV Stn
110/38kV Stn
38kV/MV Stn
110kV
17- Sequential processing
- Large applicants tend to apply to TSO, smaller
ones to DSO - The connection method is determined solely on the
basis of their connection - Applicants pay for their dedicated works
- Interracting offers can cause withdrawal of
offers already in train
- Group Processing
- Applications are processed by the SO most suited
to their Group connection irrespective of which
SO they originally applied to. - The connection method is determined by the Least
Cost technically Acceptable LCTA method for the
defined sub-group - Applicants pay in full for their dedicated
shallow works and a per MW share of shared
shallow works - No Interaction issues within Gates
18General operation of a Gate
- Regulator with input from both System Operators
and wind industry determine criteria for
eligibility for inclusion of Gate - TSO and DSO jointly apply criteria to the Queue
of application - Queue comprises both DSO and TSO applicants
- Result Make up of Gate is determined
19Gate 1 vs Gate 2
- Gate 1 370MW purely date order
- Gate 2
- Date order plus element of System optimisation
- First 500MW in Queue driver
- Applications that share a LCTA shallow connection
with driver - Extensions to existing installations
- Outliers with interactions lt10MW at 110kV node
- Resulting size circa 1385MW
20Topics
- Utility Landscape in Ireland
- Wind situation in Ireland
- Group processing
- Gate 3
- Conclusions
21Implementation of Gate 3
- The implementation of Gate 3 required very close
collaboration between CER, TSO and DSO. - The following slides will endeavour to explain
the steps, mechanisms and features involved
Network MW Number of Connections
Distribution 1941 127
Transmission 2050 28
22Size of Gate 3
22
231 Eligibility criterion
- Full consultation held with industry and
stakeholders - Result Date order of applications the clear
preference from the wind industry - CER Direction issued to System Operators
including MW size of the Gate - Implementation commences
- Unified queue formed by combining separate SO
queues - Cut-off criterion applied
In
Out
24What next?
- Now we know who is in and out!
- To begin their studies, TSO need to know how much
generation will present at their transmission
nodes - In order to inform this, DSO would normally carry
out full studies on the smaller applicants to
determine which transmission node - To shorten timeframe as much as possible it was
necessary to frontload the node assignments
252 Node Assignments
Application Capacity Node Rule
Less than 5 MW Nearest 38 kV
5 MW 10 MW Nearest 38 kV or 110 kV
10 MW 40 MW Nearest 110 kV
40 MW 177 MW New 110 kV
Greater than 177 MW New 220 kV or 400 kV
- Banded rule-set devised based upon distance to
nearest distribution primary sub-station - Clauses put in place to define nearest
- Result Transmission sub-groups formed
Tx Node 1
Tx Node 2
26Gate 3 General TSO-DSO Process
TSO
Issue Tx offers
DSO and TSO
Tx SC and other studies
Establish Tx Firm Access Quantities
Node Assignment
Report to TSO
Connection Agreement
DSO
Determine Distribution connection methods
Issue DSO offers
27Transmission Firm access quantities
- Transmission System Operator calculates
additional capacity available at each node for
each future year. - Available capacity allocated based on application
date-order - Each Gate 3 application will have a Scheduled
Firm Access Quantity for each year from 2010 to
2025, taking account of grid reinforcements and
other new generation - Thus, transmission reinforcement based on
approved development strategy leads the wind
generation connections.
28Grid development strategy to 2025
- Takes account of
- demand growth
- renewable generation to meet targets
- conventional generation development
- future DC interconnections with UK or Europe.
- Will require
- 1,150 km new transmission
- 2,300 km upgrades
http//www.eirgridprojects.com/
29Project Planning
- Country divided in to Areas for transmission
study purposes - Detailed offer issuance Project Plan agreed
between TSO, DSO and CER. - Project Plan published
30Communications
- Gate 3 Liaison Group meeting
- chaired by Regulator
- Attended by both SO s and representatives of all
industry stakeholders - SOs report on progress per workplan
- Other issues discussed as they emerge
- Customer connection meetings
- Held once distribution connection methods signed
off - TSO-DSO bi-lateral meetings
- Held bi-monthly or weekly
31Questions ?
32Conclusions
- The circumstances in Ireland lend themselves to
the TSO-DSO-Regulator approach outlined above - Facilitates large quantities of Renewable Energy
being processed in a structured manner - Transmission and Distribution systems developed
in co-ordinated fashion - Certainty of offer issuance to those in the Gate
- Rationalises the allocation of scarce capacity