Transcript and Presenter's Notes

Title: Cost


1
Cost Schedule
  • S. Steadman, MIT
  • PHOBOS Cost Schedule Review
  • Technical Advisory Committee
  • BNL
  • November 6, 1998

2
Outline
  • Financial status and WBS variance
  • Project cost estimates and schedule
  • Milestone performance
  • Institutional funding
  • Schedule for major procurements
  • Critical path items
  • Contingency
  • Completion of 2nd arm
  • Summary

3
Cost Status Overview
  • Management plan completed 4/96, approved 8/96
  • Last Cost Schedule review 6/97
  • Estimated Project Cost now 7.84M (1 increase
    from 6/97)
  • Cost to date 5.01M (64 of EPC)
  • RHIC funded PO commitments of 982K (13 of EPC)
  • Contingency of 276K for remaining cost of 1.31M
    (21)
  • Funding source Polish 1.43M 18 Taiwan
    .21M RHIC 6.15M 76 NSF .33 8.13M

4
Cost Status RHIC Funding
  • RHIC funds allocated through FY98 4.71M (77
    of available RHIC funding).
  • RHIC funds spent 3.58M (58)
  • PO commitments 0.98M (16)
  • Balance available 1.59M (26)

5
Funding Profile
  • RHIC Funding (K)
  • FY94 300
  • FY95 250
  • FY96 650
  • FY97 1,184
  • FY98 2,323
  • FY99 1,443
  • Total 6,150

6
Schedule Status Overview
  • Magnet delivered to BNL
  • Si spectrometer modules in full production
  • Si multiplicity/vertex detectors complete by 3/99
  • Time of flight on schedule ready 6/99
  • Trigger counters in production ready 4/99
  • Electronic readout has had some delays in FEC
    development, but prototype now under test. All
    other parts requiring major design are also in
    prototype stage.
  • Zero-suppression/DAQ will be ready on time
  • Mechanical structures almost complete

7
Milestone Performance
  • Milestone WBS 6/97 as of 10/98
  • Ordering magnet 7/97 11/97
  • Full chain software on simulated
    data 10/97 10/97
  • Prototype DAQ system 11/97 9/98
  • Testing of pipeline chips begins 5/98
  • Change to Begin testing front end
    controller 10/98
  • Complete fab. of spectrometer sensors 3/98 11/98
  • Pre-amp chips fab. and tested 5/98 9/98
  • Begin shipping detectors to BNL 1/99 1/99
  • Ready for beam 8/99 9/99

8
Project Progress
9
Project progress by subsystem
Values in K
However, note descoping to 1 arm!
10
Institutional funding
  • Contracts with all institutions in place
    Maryland last contract to be signed
  • Yale terminated with Steve Manly moving to
    Rochester

11
Major Procurements (gt100K)
  • VA readout chips (169K IDE AS) delivered 9/98
  • TOF phototubes/bases/shields (153K Hamamatsu)
    delivered 9/98
  • Magnet (228KDanfysik) delivered to BNL this
    week
  • Si sensor production (498KNCU) for arm 1
    complete 11/98
  • Beam pipe (307K Electrofusion) 3/98-4/99
  • Trigger and TOF electronics (189K LeCroy)
    9/98-1/99
  • Front-end controllers (145K) 1/99-3/99

12
Critical path items
  • Utilities must be ready for magnet hookup and
    mapping or serious delay in detector installation
    will result
  • Must begin production of FECs by 1/99 in order
    to have them all tested by 5/99 and ready for
    installation

13
Contingency
  • Value of 276K now at 21 of balance of cost for
    uncommitted expenses.
  • Estimates for outside vendors are firm, based on
    quotations.
  • Uncertainty in electronics cost essentially in
    estimate for time to assemble modules and to
    debug front-end controllers.
  • Some uncertainty in installation costs.

14
Completion of 2nd arm
  • Total cost for parts and assembly of arm 2 is
    414K, of which 100K is for custom parts which
    is in WBS.
  • Mechanical parts completed with Polish funds and
    Si sensors produced with Taiwan funds.
  • Completion of spectrometer arm 2 will depend on
    use of any remaining contingency and new funding.
    This includes commercially available parts and
    assembly VA readout chips (IDE AS)
    99K Vendor interaction and
    oversight 15K Assembly and
    test of detector modules (1.5 FTE-year) 165K
    Additional zero-suppression (Mercury) modules
    35K
    Total
    314K

15
Summary
  • All systems in prototype or production phase.
  • Total estimated project cost is within budget and
    completion by RHIC turnon is within schedule.
  • Completion of spectrometer arm 2 will depend on
    use of contingency and new funding.
  • Most major procurements complete.
  • Magnet must be installed and mapped on time or
    detector installation will be seriously delayed.
  • PHOBOS looking forward to physics running on day
    1.