Endcap Muons - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

Endcap Muons

Description:

physics.ucr.edu – PowerPoint PPT presentation

Number of Views:93
Avg rating:3.0/5.0
Slides: 37
Provided by: DanG97
Category:

less

Transcript and Presenter's Notes

Title: Endcap Muons


1
Endcap Muons
  • John Layter
  • US CMS Collaboration Meeting
  • May 19, 2001

2
Outline
  • Muon System Overview
  • CSC Production
  • FAST Sites
  • Electronics Progress
  • Integration and Installation
  • CPA, ETC
  • Plans for the next six months
  • Summary

3
CMS Endcap Muon System
  • 360 CSCs, not counting ME1/1 and ME4
  • 144 Large CSCs (3.4x1.5 m2)
  • 72 ME2/2 chambers
  • 72 ME3/2 chambers
  • Small CSCs (1.8x1.1 m2)
  • 72 ME1/2 chambers
  • 72 ME1/3 chambers
  • 20o CSCs (1.9x1.5 m2)
  • 36 ME2/1 chambers
  • 36 ME3/1 chambers
  • Frontend Electronics
  • 170K Cathode channels
  • 140K Anode channels
  • TriggerDAQ
  • (on-chamber part)
  • AlignmentServices

4
Endcap Muon System
5
EMU - Yearly BCWS
  • FY01 is the second largest year of EMU funding
  • Production of chambers at Fermilab at nominal
    rate
  • Purchasing of significant part of FE electronics
  • Finalization of integration and installation
    design

6
EMU Chamber Status
  • Fermilab Site (Panels for 410 CSCs Assembly of
    148 Large CSCs)
  • Panel production since 5/99 52 of chambers
    done on schedule
  • CSC assembly since 6/00 32/148 large CSCs done
    2 wks late
  • UF and UC Sites (Final Assembly and System
    Tests of Large CSCs)
  • First 5 CSCs arrived at UC and UF long term HV
    test will start
  • Begin mounting and testing electronics 9/01, 3
    mo. late
  • Delivery of on-chamber electronics is on critical
    path
  • PNPI Site (114 smaller CSCs)
  • Critical tooling commissioned 2 chambers
    assembled
  • PRRJune 7-8 start production in August
  • IHEP Site (148 smaller CSCs)
  • Critical tooling arrived, being commissioned,
    begin assembly
  • PRRJuly 30-31 start production in September

7
FNAL Factory Status - Chamber assembly at
MP9
  • 32 large CSCs assembled by May 2001
  • gt 20 complete
  • Production at nominal rate
  • On schedule

8
Chamber Assembly
Gluing Station (anode bars, gap bars are glued to
panels)
Winding Station (wires are wound directly on
panels)
Soldering Station (automated soldering of wires)
Wire Tension/Spacing Station (tension and spacing
of wires are checked)
Ionized Air Knife Station (dust is removed from
wires and panels)
Assembly Station (panels are stacked to make
chamber)
9
CSCs at UC FAST Site
10
CSCs at UC FAST Site
11
CSC Production at PNPI
Preproduction Prototype (P3) assembled at PNPI
12
CSC production at IHEP
  • Critical tooling received

Wire Tension measurement machine
13
Functions of Electronics
  • Acquire precise muon data for offline analysis
  • Cathode strips precise azimuthal position (in
    bending plane) in each layer by interpolation of
    induced strip charges.
  • Anode wires precise timing and coarse radial
    position.
  • Generate primitives for Level 1 trigger
  • Identify Local Charged Track (LCT) segments using
    cathode and anode signals.

14
Electronics System Layout
15
(No Transcript)
16
Radiation Tolerance Tests
  • Measure Single Event Upset (SEU) and Total
    Ionization Dosage (TID) effects with 63 MeV
    proton beam at UC Davis.
  • Measure effects due to Displacement damage of
    bipolar and biCMOS with 1MeV neutrons at OSU.
  • Results
  • Negligible degradation of analog performance due
    to TID (gt10kRad) or displacement (2x1012 cm-2
    neutrons).
  • No latch-ups observed up to p fluence of 2x1012
    cm-2.
  • SEUs in FPGAs observed and cross sections
    measured. All SEUs recoverable by reloading
    FPGAs. SEU rate at peak LHC luminosity
    manageable for CFEB, but higher for ALCT.

17
On-chamber Electronics I
  • Three out of four on-chamber boards designed and
    tested
  • Cathode Front End Board (CFEB)
  • Anode Front End Board (AFEB)
  • Low Voltage Distribution Board (LVDB)
  • Most of the components for these boards
    (excluding rad hard LV-regulators) procured in
    quantities sufficient to start production
  • Production costs at or below estimates

18
On-chamber Electronics II
  • LV-regulators (CERN design, standard for LHC
    experiments) are not available. Will define the
    schedule of production of CFEB and LVDB. On
    critical path
  • ALCT being redesigned using Xilinx FPGA (faster
    reloading) to deal with SEU problem.
    Preproduction boards to be delivered by September
    2001. On critical path

19
Status of On-chamber Boards
20
Off-chamber Electronics
  • Progress made on next round of prototype boards
    and on VME custom backplane.
  • Updated versions of the prototype boards will be
    delivered to the FAST sites during this summer.
  • These will be used for tests of mass-produced
    on-chamber electronics assembled with chambers.

21
Integration Installation
  • Infrastructure
  • Walkways
  • Piping, cooling, cabling
  • Chamber mounting
  • Installation
  • Fixture
  • Strategy
  • Schedule

22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
Mounting Detail
26
Chamber Mounts
27
Mounting Precision
28
Integration and installation design
  • EMU integration design advanced (mechanical, gas,
    cooling, power)
  • Installation procedures
  • being defined
  • Installation fixture
  • fully designed and built

29
CSC installation fixture
Counterweight movement keeps balance w/ or w/o
chamber Chamber can rotate at any angle

Counterweight
30
(No Transcript)
31
Chamber Production and Installation Schedule (V31)
  • CMS Schedule V31 Installation of all CSCs on the
    surface at SX5, beginning in 2002.
  • Very tight, advanced by 1 year compared to V30.
    Pressure on production and installation rate.

32
EMU Critical Path Analysis - I
  • FY01 Delivery of on-chamber electronics is on
    the critical path
  • ALCT Board redesign and start of production
  • Rad Hard Voltage regulators ? CFEB, LVDB
    production
  • FY02 CSC assembly at FAST sites and installation
    at CERN is on the critical path

33
EMU Critical Path Analysis - II
  • FY03 CSC Installation (station ME3) is on the
    critical path
  • short installation window (two shifts necessary)
  • FY04 CSC Installation (station ME1) is on the
    critical path
  • RPCs must be installed before CSCs
  • HE, EE, SE, ME1/1 cables should be installed
    before CSCs
  • Short installation windows (two shifts)
  • Available Slack analysis
  • 25-30 working days in 2002. Very tight in 2003
    2004.
  • Need two shifts for production at IHEP and
    ME1/2,3 installation

34
EMU Estimate to Complete
EMU Estimate to Complete 18.9 Actual Year M
Dominated by MS (mostly electronics)
35
Plans for the Next 6 Months
  • Continue CSC production at Fermilab.
  • Start production at PNPI and IHEP.
  • Continue FE electronics production.
  • Start electronics assembly and begin chamber
    tests at FAST sites.
  • Complete integration drawings for all chamber
    types.
  • Begin preparations for receiving and installing
    chambers at CERN.

36
Summary
  • Nominal rate of chamber production at FNAL
    achieved. Chamber production on schedule.
  • FE electronics production started first cost
    experience positive.
  • LV-regulators and trigger boards on the critical
    path defines beginning of assembly at FAST
    sites.
  • Endcap infrastructure designed installation
    fixture exists.
  • Adequate base program support is critical to
    maintain the schedule.
Write a Comment
User Comments (0)
About PowerShow.com