Title: Endcap Muons
1Endcap Muons
- John Layter
- US CMS Collaboration Meeting
- May 19, 2001
2Outline
- Muon System Overview
- CSC Production
- FAST Sites
- Electronics Progress
- Integration and Installation
- CPA, ETC
- Plans for the next six months
- Summary
3CMS Endcap Muon System
- 360 CSCs, not counting ME1/1 and ME4
- 144 Large CSCs (3.4x1.5 m2)
- 72 ME2/2 chambers
- 72 ME3/2 chambers
- Small CSCs (1.8x1.1 m2)
- 72 ME1/2 chambers
- 72 ME1/3 chambers
- 20o CSCs (1.9x1.5 m2)
- 36 ME2/1 chambers
- 36 ME3/1 chambers
- Frontend Electronics
- 170K Cathode channels
- 140K Anode channels
- TriggerDAQ
- (on-chamber part)
-
- AlignmentServices
4Endcap Muon System
5EMU - Yearly BCWS
- FY01 is the second largest year of EMU funding
- Production of chambers at Fermilab at nominal
rate - Purchasing of significant part of FE electronics
- Finalization of integration and installation
design
6EMU Chamber Status
- Fermilab Site (Panels for 410 CSCs Assembly of
148 Large CSCs) - Panel production since 5/99 52 of chambers
done on schedule - CSC assembly since 6/00 32/148 large CSCs done
2 wks late - UF and UC Sites (Final Assembly and System
Tests of Large CSCs) - First 5 CSCs arrived at UC and UF long term HV
test will start - Begin mounting and testing electronics 9/01, 3
mo. late - Delivery of on-chamber electronics is on critical
path - PNPI Site (114 smaller CSCs)
- Critical tooling commissioned 2 chambers
assembled - PRRJune 7-8 start production in August
- IHEP Site (148 smaller CSCs)
- Critical tooling arrived, being commissioned,
begin assembly - PRRJuly 30-31 start production in September
7FNAL Factory Status - Chamber assembly at
MP9
- 32 large CSCs assembled by May 2001
- gt 20 complete
- Production at nominal rate
- On schedule
8Chamber Assembly
Gluing Station (anode bars, gap bars are glued to
panels)
Winding Station (wires are wound directly on
panels)
Soldering Station (automated soldering of wires)
Wire Tension/Spacing Station (tension and spacing
of wires are checked)
Ionized Air Knife Station (dust is removed from
wires and panels)
Assembly Station (panels are stacked to make
chamber)
9CSCs at UC FAST Site
10CSCs at UC FAST Site
11CSC Production at PNPI
Preproduction Prototype (P3) assembled at PNPI
12CSC production at IHEP
- Critical tooling received
Wire Tension measurement machine
13Functions of Electronics
- Acquire precise muon data for offline analysis
- Cathode strips precise azimuthal position (in
bending plane) in each layer by interpolation of
induced strip charges. - Anode wires precise timing and coarse radial
position. - Generate primitives for Level 1 trigger
- Identify Local Charged Track (LCT) segments using
cathode and anode signals.
14Electronics System Layout
15(No Transcript)
16Radiation Tolerance Tests
- Measure Single Event Upset (SEU) and Total
Ionization Dosage (TID) effects with 63 MeV
proton beam at UC Davis. - Measure effects due to Displacement damage of
bipolar and biCMOS with 1MeV neutrons at OSU. - Results
- Negligible degradation of analog performance due
to TID (gt10kRad) or displacement (2x1012 cm-2
neutrons). - No latch-ups observed up to p fluence of 2x1012
cm-2. - SEUs in FPGAs observed and cross sections
measured. All SEUs recoverable by reloading
FPGAs. SEU rate at peak LHC luminosity
manageable for CFEB, but higher for ALCT.
17 On-chamber Electronics I
- Three out of four on-chamber boards designed and
tested - Cathode Front End Board (CFEB)
- Anode Front End Board (AFEB)
- Low Voltage Distribution Board (LVDB)
- Most of the components for these boards
(excluding rad hard LV-regulators) procured in
quantities sufficient to start production - Production costs at or below estimates
18 On-chamber Electronics II
- LV-regulators (CERN design, standard for LHC
experiments) are not available. Will define the
schedule of production of CFEB and LVDB. On
critical path - ALCT being redesigned using Xilinx FPGA (faster
reloading) to deal with SEU problem.
Preproduction boards to be delivered by September
2001. On critical path
19Status of On-chamber Boards
20 Off-chamber Electronics
- Progress made on next round of prototype boards
and on VME custom backplane. - Updated versions of the prototype boards will be
delivered to the FAST sites during this summer. - These will be used for tests of mass-produced
on-chamber electronics assembled with chambers.
21Integration Installation
- Infrastructure
- Walkways
- Piping, cooling, cabling
- Chamber mounting
- Installation
- Fixture
- Strategy
- Schedule
22(No Transcript)
23(No Transcript)
24(No Transcript)
25Mounting Detail
26Chamber Mounts
27Mounting Precision
28Integration and installation design
- EMU integration design advanced (mechanical, gas,
cooling, power) - Installation procedures
- being defined
- Installation fixture
- fully designed and built
29CSC installation fixture
Counterweight movement keeps balance w/ or w/o
chamber Chamber can rotate at any angle
Counterweight
30(No Transcript)
31Chamber Production and Installation Schedule (V31)
- CMS Schedule V31 Installation of all CSCs on the
surface at SX5, beginning in 2002. - Very tight, advanced by 1 year compared to V30.
Pressure on production and installation rate.
32EMU Critical Path Analysis - I
- FY01 Delivery of on-chamber electronics is on
the critical path - ALCT Board redesign and start of production
- Rad Hard Voltage regulators ? CFEB, LVDB
production - FY02 CSC assembly at FAST sites and installation
at CERN is on the critical path
33EMU Critical Path Analysis - II
- FY03 CSC Installation (station ME3) is on the
critical path - short installation window (two shifts necessary)
- FY04 CSC Installation (station ME1) is on the
critical path - RPCs must be installed before CSCs
- HE, EE, SE, ME1/1 cables should be installed
before CSCs - Short installation windows (two shifts)
- Available Slack analysis
- 25-30 working days in 2002. Very tight in 2003
2004. - Need two shifts for production at IHEP and
ME1/2,3 installation
34EMU Estimate to Complete
EMU Estimate to Complete 18.9 Actual Year M
Dominated by MS (mostly electronics)
35Plans for the Next 6 Months
- Continue CSC production at Fermilab.
- Start production at PNPI and IHEP.
- Continue FE electronics production.
- Start electronics assembly and begin chamber
tests at FAST sites. - Complete integration drawings for all chamber
types. - Begin preparations for receiving and installing
chambers at CERN.
36Summary
- Nominal rate of chamber production at FNAL
achieved. Chamber production on schedule. - FE electronics production started first cost
experience positive. - LV-regulators and trigger boards on the critical
path defines beginning of assembly at FAST
sites. - Endcap infrastructure designed installation
fixture exists. - Adequate base program support is critical to
maintain the schedule.