Title: Integrity Management Workshop


1

Comprehensive Inspection Protocols for Risk
Analysis Preventive and Mitigative Measures
  • Integrity Management Workshop
  • July 23-24, 2002

2
Risk Analysis
  • Risk Analysis in Integrity Management Rule
    195.452
  • Element of Baseline Assessment Plan with respect
    to establishing assessment schedule c (1) iii
  • Integration of information on pipeline integrity
    and consequences of failure f(3), g
  • Evaluation of the need for additional preventive
    mitigative measures i(1,2)

3
Risk Analysis
  • Risk Analysis in Integrity Management Rule
    195.452
  • Evaluation of leak detection capability i(3)
  • Evaluation of additional EFRDs i(4)
  • Assessment interval determination j(2,3)

4
Risk Analysis
  • All that being the case, what types of areas
    will be looked at during the comprehensive
    inspections?
  • Process for Analyzing Risk (Risk Process)

5
Risk Analysis
  • All that being the case, what types of areas
    will be looked at during the comprehensive
    inspections?
  • Process for Analyzing Risk (Risk Process)
  • Application of Risk Process

6
Risk Analysis Process
  • What is the described risk process?

7
Risk Analysis Process
  • What is the described risk process?
  • Are all relevant risk factors included?
  • Required and others as appropriate (e.g.,
    operational contributions to failure risk)

8
Risk Analysis Process
  • What is the described risk process?
  • Are all relevant risk factors included?
  • Required and others as appropriate (e.g.,
    operational contributions to failure risk)
  • What are the technical assumptions and associated
    bases?

9
Risk Analysis Process (contd)
  • What measures of risk are produced by the
    process?

10
Risk Analysis Process (contd)
  • What measures of risk are produced by the
    process?
  • Are Information Analysis requirements met?
  • Risk analysis and paragraph (g) requirements

11
Risk Analysis Process (contd)
  • What measures of risk are produced by the
    process?
  • Are Information Analysis requirements met?
  • Risk analysis and paragraph (g) requirements
  • Periodic update/revision of process?

12
Risk Analysis Application
  • Are input data adequate and utilized
    appropriately?

13
Risk Analysis Application
  • Are input data adequate and utilized
    appropriately?
  • Is the pipeline appropriately segmented?

14
Risk Analysis Application (contd)
  • How are results integrated with integrity
    assessment results? With other pipeline
    integrity information? With other risk factors
    not in the process?

15
Risk Analysis Application (contd)
  • How are results integrated with integrity
    assessment results? With other pipeline
    integrity information? With other risk factors
    not in the process?
  • How are the results used in support of each of
    the associated integrity management elements?
    (e.g., segment ranking for assessment plan )

16
Preventive and Mitigative Measures
  • Required element of Integrity Management
  • Program f (6)
  • Requirements outlined in Section i
  • Identification of additional actions i(1)
  • Risk analysis i(2)
  • Leak detection evaluation i(3)
  • EFRD evaluation i(4)

17
Preventive and Mitigative Measures
  • As with risk analysis, look at two general areas
  • Process for evaluating Preventive and Mitigative
    Measures
  • Application of the evaluation process

18
Preventive and Mitigative Measures Process
  • What is the described process?

19
Preventive and Mitigative Measures Process
  • What is the described process?
  • Are the relevant risk analysis and risk factors
    included?

20
Preventive and Mitigative Measures Process
  • What is the described process?
  • Are the relevant risk analysis and risk factors
    included?
  • What are the technical assumptions and associated
    bases?

21
Preventive and Mitigative Measures Process
  • What are the additional action decision criteria?

22
Preventive and Mitigative Measures Process
  • What are the additional action decision criteria?
  • Are additional EFRDs evaluated as required?

23
Preventive and Mitigative Measures Process
  • What are the additional action decision criteria?
  • Are additional EFRDs evaluated as required?
  • Periodic update/revision of process required?
  • Review requirements?

24
Preventive and Mitigative Measures Application
  • Are input data adequate and utilized
    appropriately?

25
Preventive and Mitigative Measures Application
  • Are input data adequate and utilized
    appropriately?
  • Have risk factors in addition to the required
    factors been considered?

26
Preventive and Mitigative Measures Application
  • How are the results used in support of each of
    the associated integrity management elements?

27
Preventive and Mitigative Measures Application
  • How are the results used in support of each of
    the associated integrity management elements?
  • What additional actions have been considered?
    Timeliness of implementation?

28
Preventive and Mitigative Measures Application
  • How are the results used in support of each of
    the associated integrity management elements?
  • What additional actions have been considered?
    Timeliness of implementation?
  • Have any additional EFRDs been identified?

29
Risk Analysis / Preventive and Mitigative Measures
  • Inspection Expectations
  • Process will be examined

30
Risk Analysis / Preventive and Mitigative Measures
  • Inspection Expectations
  • Process will be examined
  • Application of process will be examined

31
Risk Analysis / Preventive and Mitigative Measures
  • Inspection Expectations
  • Process will be examined
  • Application of process will be examined
  • Documented evaluation of measures considered to
    prevent and mitigate will be important

32
Risk Analysis / Preventive and Mitigative Measures
  • Inspection Expectations
  • Process will be examined
  • Application of process will be examined
  • Documented evaluation of measures considered to
    prevent and mitigate will be important
  • Risk analysis is a key input