Title: Barry Barish
1Introduction
- Barry Barish
- PAC Valencia, Spain
- 13-May-10
2Technical Design Phase and Beyond
TDR
TDP Baseline Technical Design
RDR Baseline
TDP-1
TDP-2
Change Request
New baseline inputs
RDR ACD (alternate concepts)
RD Demonstrations
design studies
2009
2010
2011
2012
2013
3ILCSC Science Goals 2003, 2006
- Ecm adjustable from 200 500 GeV
- Luminosity ? ?Ldt 500 fb-1 in 4 years
- Ability to scan between 200 and 500 GeV
- Energy stability and precision below 0.1
- Electron polarization of at least 80
- The machine must be upgradeable to 1 TeV
The RDR Design meets these requirements,
including the recent update and clarifications of
the reconvened ILCSC Parameters group!
4RDR Design Parameters
Max. Center-of-mass energy 500 GeV
Peak Luminosity 2x1034 1/cm2s
Beam Current 9.0 mA
Repetition rate 5 Hz
Average accelerating gradient 31.5 MV/m
Beam pulse length 0.95 ms
Total Site Length 31 km
Total AC Power Consumption 230 MW
5RDR Design Value Costs
- Summary
- RDR Value Costs
- Total Value Cost (FY07)
- 4.80 B ILC Units Shared
-
- 1.82 B Units Site Specific
-
- 14.1 K person-years
- (explicit labor 24.0 M person-hrs
- _at_ 1,700 hrs/yr)
- 1 ILC Unit 1 (2007)
- The reference design was frozen as of 1-Dec-06
for the purpose of producing the RDR, including
costs. - It is important to recognize this is a snapshot
and the design will continue to evolve, due to
results of the RD, accelerator studies and value
engineering -
- The value costs have already been reviewed three
time -
- 3 day internal review in Dec
- ILCSC MAC review in Jan
- International Cost Review (May)
- S Value 6.62 B ILC Units
6Evolving Design ? Cost Reductions
July 2006
Some possible cost reductions (e.g. single
tunnel, half RF, value engineering) deferred to
the engineering phase
7RDR Complete
- Reference Design Report (4 volumes)
Physics at the ILC
Executive Summary
Detectors
Accelerator
82009 2012 Resource Outlook
- Flat year-to-year resource basis
- Focused on technical enabling R D
- Limited flexibility to manage needed ILC design
and engineering development - Well matched between ILC technical and
institutional priorities with some exceptions - Positron system beam demonstrations
- CF S criteria optimization and site development
9The ILC SCRF Cavity
- Achieve high gradient (35MV/m) develop multiple
- vendors make cost effective, etc
- Focus is on high gradient production yields
cryogenic - losses radiation system performance
10Global Plan for SCRF RD
Year 07 2008 2008 2009 2009 2010 2010 2011 2012
Phase TDP-1 TDP-1 TDP-1 TDP-1 TDP-1 TDP-1 TDP-2 TDP-2 TDP-2
Cavity Gradient in v. test to reach 35 MV/m ? Process Yield 50 ? Process Yield 50 ? Process Yield 50 ? Process Yield 50 ? Process Yield 50 ? Process Yield 50 ? Production Yield 90 ? Production Yield 90 ? Production Yield 90
Cavity-string to reach 31.5 MV/m, with one-cryomodule Global effort for string assembly and test (DESY, FNAL, INFN, KEK) Global effort for string assembly and test (DESY, FNAL, INFN, KEK) Global effort for string assembly and test (DESY, FNAL, INFN, KEK) Global effort for string assembly and test (DESY, FNAL, INFN, KEK) Global effort for string assembly and test (DESY, FNAL, INFN, KEK) Global effort for string assembly and test (DESY, FNAL, INFN, KEK)
System Test with beam acceleration FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012) FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012) FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012) FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012) FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012) FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012) FLASH (DESY) , NML (FNAL) STF2 (KEK, extend beyond 2012)
Preparation for Industrialization Production Technology RD Production Technology RD Production Technology RD Production Technology RD Production Technology RD
7 January 2010 SCRF AAP Review
10
Global Design Effort
11TTF/FLASH 9mA Experiment
Full beam-loading long pulse operation ? S2
- Stable 800 bunches, 3 nC at 1MHz (800 ms pulse)
for over 15 hours (uninterrupted) - Several hours 1600 bunches, 2.5 nC at 3MHz (530
ms pulse) - gt2200 bunches _at_ 3nC (3MHz) for short periods
XFEL ILC FLASHdesign 9mA studies
Bunch charge nC 1 3.2 1 3
bunches 3250 2625 7200 2400
Pulse length ms 650 970 800 800
Current mA 5 9 9 9
12Making Very Small Emittance (Beam Sizes at
Collision)
13R D Plan Resource Table
- Resource total 2009-2012
-
- Not directly included
- There are other Project-specific and general
infrastructure resources that overlap with ILC
TDP
14Updated ILC RD / Design Plan
- Major TDP Goals
- ILC design evolved for cost / performance
optimization - Complete crucial demonstration and
risk-mitigating RD - Updated VALUE estimate and schedule
- Project Implementation Plan
15Major RD Goals for TDP 1
- SCRF
- High Gradient RD - globally coordinated program
to demonstrate gradient by 2010 with 50yield -
- ATF-2 at KEK
- Demonstrate Fast Kicker performance and Final
Focus Design - Electron Cloud Mitigation (CesrTA)
- Electron Cloud tests at Cornell to establish
mitigation and verify one damping ring is
sufficient. - Accelerator Design and Integration (ADI)
- Studies of possible cost reduction designs and
strategies for consideration in a re-baseline in
2010
Global Design Effort
15
16Why change from RDR design?
- Timescale of ILC demands we continually update
the technologies and design to be prepared to
build the most forward looking machine at the
time of construction. - Our next big milestone the technical design
(TDR) at end of 2012 should be as much as
possible a construction project ready design
with crucial RD demonstrations complete and
design optimised for performance to cost to risk. - Cost containment vs RDR costs is a crucial
element. (Must identify costs savings that will
compensate cost growth)
17Cost Containment is essential for ILC
- Our problem is worse than comparable projects
- International Space Station was dominantly a US
project that was heavily supported by US
industry, so it could absorb large increase
without cancellation - LHC has a large well-funded host laboratory that
could absorb cost increase by stretching schedule
and paying for it from future years - ITER has more trouble and more jeopardy! A
significant ( 25-30 increase) is causing
enormous problems for the project. - We need governments to take ILC seriously. That
requires 1) science goals that are important
enough to convince making the investment 2) a
technical design and project that is considered
robust and worthwhile 3) and finally, costs that
are considered affordable and UNDER CONTROL.
18TDR vs RDR Costs
- Will a 15 cost savings make a difference for
project approval? - We are on record for a cost of 6.6 BILCU (2007
US) for the ILC. That cost has frightened
governments! - 15 savings corresponds to 1B, not a negligible
amount - We will have unavoidable areas of cost growth,
probably greater than the anticipated savings. -
- Significant net cost increase for the TDR over
RDR will be considered (by some) as a signal of
another out of control project.
19PAC Report Nov 09
- The PAC supports the Minimum Machine
activities to carefully review the RDR design,
although it is not enthusiastic about the use of
the term Minimum Machine. The Committee
believes that this activity should not compromise
the existing ILC physics goals, and reiterates
its belief that the 1 TeV upgrade option should
be maintained.
20AAP Review - Conclusion (1)
-
- The SB2009 exercise was carried out to save cost
and consolidate the design. The cost savings in
SB2009 amount to 12.6 and are composed of
several savings at the few per cent level. The
AAP recognizes that a cushion of savings at this
level will have to be identified to contain the
cost of the project which is likely to change
because of both a better understanding of the
cost composition, of progress in optimization and
of external influences such as the variations in
cost of raw material and external services until
the end of Technical Phase II.
21Recommendations of GDE EC (1)
- After review and subsequent discussion of the AAP
SB2009 Review Report, the GDE EC agreed and
confirmed - That containment of the capital cost (VALUE)
estimate at the RDR level is a primary TD Phase 2
goal. Our design activity is now aimed at making
the project more robust against possible
(expected) unit cost increases. - To move forward with studies aimed at the
possible adoption of the themes in SB2009
proposal, but not necessarily the exact details. -
- To establish a formal process to make these
changes to the baseline in an open and
transparent fashion, and where necessary after
due process and consultation with all
stakeholders.
22SB2009 Themes
Cost Savings 13
N Walker
23Proposed Design changes for TDR
RDR
SB2009
- Single Tunnel for main linac
- Move positron source to end of linac
- Reduce number of bunches factor of two (lower
power) - Reduce size of damping rings (3.2km)
- Integrate central region
- Single stage bunch compressor
24Achieving ILC Cost Containment
- We must continually balance science performance
with cost and risk to propose a convincing
construction project. - We must have continuing close GDE / detector /
physics studies and interaction to evaluate
science impact of proposed changes to ILC
baseline.
257.5 m Diameter Single Tunnel
- Egress passageway not needed
- 7 m Ø ok
25
267.5 m Diameter Single TunnelHigh-Level RF
Solution
- Critical technical challenge for one-tunnel
option is the high level RF distribution. - Two proposed solutions
- Distributed RF Source (DRFS)
- Small 750kW klystrons/modulators in tunnel
- One klystron per four cavities
- 1880 klystrons per linac
- Challenge is cost and reliability
- Klystron Cluster Scheme (KCS)
- RDR-like 10 MW Klystrons/modulators on surface
- Surface building shafts every 2 km
- Challenge is novel high-powered RF components
(needs RD)
26
27Technical Design Phase and Beyond
change control process
AAP PAC Physics
TDP Baseline Technical Design
TDR
RDR Baseline
SB2009 evolve
TDP-2
TDP-1
Beijing Workshop
CERN Workshop
Change Request
RDR ACD concepts
RD Demonstrations
ADI studies
2009
2010
2011
2012
2013
28Top Level Change Control Process
keywords open, transparent
28
29TLCC Process
- Albuquerque, PAC (Nov 09), DESY, AAP, Beijing,
PAC (May) - Builds on and extends work done during 2009 ADI
process - Generate plans/studies to be done in preparation
for the BAWs
29
30TLCC Process
- Open plenary meeting
- Two-days per theme
- Two themes per workshop
- Two four-day workshops
- Participation (mandatory)
- PM (chair)
- ADI team / TAG leaders
- Agenda organised by relevant TAG leaders
- Physics Detector Representatives
- External experts
- Achieve primary TLCC goals
- In an open discussion environment
- Prepare recommendation
30
31TLCC Process
Physics and detector input / representation
mandatory
When Where What
WAB 1 Sept. 7-8, 2010 KEK Accelerating Gradient Single Tunnel (HLRF)
WAB 2 Jan 17-21, 2011 SLAC Reduced RF power e source location
32TLCC Process
- Final formal step (recommended by AAP)
- Change Evaluation Panel
- Chaired by director
- Experts to evaluate impact on performance, cost,
schedule, risk - Decision by Director
- Accepts becomes baseline
- Rejects sent back for further work
32
33Technical Design Phase and Beyond
change control process
AAP PAC Physics
TDP Baseline Technical Design
TDR
RDR Baseline
SB2009 evolve
TDP-2
TDP-1
Beijing Workshop
CERN Workshop
Change Request
RDR ACD concepts
RD Demonstrations
ADI studies
2009
2010
2011
2012
2013
34Project Implementation Plan
ILCSC
35ILC RD Beyond 2012 ?
- The AAP points to uncertainties beyond 2012 in
their conclusions - Some aspects of the RD for the ILC will have to
continue beyond 2012. - The milestone 2012 is however timely placed. The
LHC will be providing operating experience of a
large facility and with some luck the first
physics discoveries will emerge. - The HEP community is thus well prepared for the
decision for the next facility. In a sense the
construction of the ILC seems the natural
evolution of that process, in which case the
efforts for the ILC have to be ramped up without
delay. - Nature may be less kind or science policy makers
not ready for a decision on the next big HEP
project. In this case the large community must be
engaged to facilitate the decision for the
construction of the next HEP project. - We need to prepare for uncertainties in the path
to the ILC after 2012, including what LHC tells
us.
36Timescales TDR to ILC(or beyond 2012)
- Steps to a Project Technical (2-3 years)
- RD for Risk Reduction and Technology Improvement
- Systems Tests (e.g. S2 completion ILC-like beam
tests) - Engineering Design
- Industrialization
- Project Implementation
- Government Agreements for International
Partnership - Siting and site-dependent design
- Governance
- Time to Construct
- 5-6 years construction
- 2 years commissioning
- Project Proposal / Decision keyed to LHC results
- ILC Could be doing physics by early to mid- 2020s
37Five Themes to Develop
N Walker
Remains special case