Title: Measurement and Payment


1
Measurement and Payment
2
  • Construction Progress Payments
  • Contractor gives a bill for progress to RPR
  • Outlines what bill is for
  • Give details as needed (quantities)
  • RPR reviews
  • Approves (sends to owner) or disapproves (calls
    contractor)
  • Contractor gets paid

3
  • Approval of Payment Requests
  • RPR responsible for checking quantities and costs
  • Quantity take off
  • Inventory of equipment and materials on site but
    not used
  • Field measure work completed or claimed
  • Construction Cost Estimate of all completed work
  • Audit of Invoices and costs
  • Review of claims for extra work and completed
    change orders
  • Check of retention amount
  • Check method used for profit and overhead,
    material costs for estra work or change orders

4
  • Basis for Payment Amounts
  • Accuracy of field measurements determined by
    contract type
  • Lump sum contracts do not need accurate field
    measurements
  • Cost plus or Unit price contracts need very
    accurate field measurements
  • Pg 432

5
Schedule of Values v. Cost loaded CPM Schedule
  • Unit Price Contracts
  • Do not call for Cost Loaded CPM Schedule
  • Conflicts with line items on unit price sheet
  • Do not call for schedule of Values
  • A breakdown of all line items is submitted w/
    contractors bid and is binding throughout job

6
  • Lump Sum Contracts with Cost Loaded CPM
  • Do not ask for Schedule of Values cost loaded
    CPM is equal
  • Request Cost loaded CPM be submitted before first
    pay period ends
  • Lump Sum Contracts w/o Cost loaded CPM
  • Do not ask for a cost loaded CPM schedule
  • Do not ask for a bid breakdown
  • Request a schedule of values before starting work
    on project

7
Evaluation of Contractors Payment Requests
  • Contractor submits request for payment at a
    prearranged date each month for previous months
    work
  • Lump sum contract payment based on a fair
    estimate of work completed plus overhead and
    profit
  • Unit Price Contracts contractor gets paid based
    on quantity used RPR must have accurate field
    measurements
  • /- 25 is okay more or less allows for
    renegotiations by either party

8
  • Equipment And Materials delivered but not used
  • Contractor brings stuff on site early
  • May try to bill owner since stuff is on site
  • Contractor only paid when stuff is used
  • Includes materials used but not completed pipe
    not paid for until covered and tested
  • Unit price contracts are usually for installed in
    place materials on site is not in place
  • Can make exceptions for long lead items which
    arrive on site early

9
  • Force Account
  • Daywork or for any type of cost plus payment
  • In US associated with extra work and change
    orders
  • May be used to pay contractor when it is
    difficult to provide adequate measurements or
    estimate cost of certain items of work
  • Should be last choice when setting up items for
    payment

10
Force Account
  • Change order is a must
  • Force account payments not authorized for supers.
    Allowances for supers is in contractors OP.
    Foremen working full time on item would be
    covered by account
  • PM has authority to direct every aspect of force
    account work

11
  • PM and Contractor must agree on
  • Labor
  • Classification and approximate N of workers, wage
    rates, travel allowance, subsistence, are foremen
    included
  • Equipment
  • Types to be used including size, rating,
    capacity, which indicate that item can do work
    required, owned or leased, cost per hour for use
  • Materials
  • Cost and freight charges, purchased for project
    or from contractors stock

12
  • PM prepares lists of equipment and labor
    classifications actually used and corresponding
    rates
  • Equipment list includes complete nomenclature of
    the equipment to establish rental rate from a
    Rental Rate Book
  • Labor list includes labor classification and
    composite hourly rate (basic wage added costs
    listed in DOT standard specs)

13
  • Payments for Extra Work and Change Orders
  • Usually laid out in Contract
  • Common is cost plus with a reasonable allowance
    for OP
  • State agencies may allow 15, 20, 24,33 on labor
    and then 15 on equipment, 15 on materials 5 on
    primary subs (not subs subs)

14
  • RPR must evaluate all change orders and requests
    for payment of extra work
  • RPR should consult PM or owner to determine the
    exact terms of the agreement that cover extra
    work
  • RPR keeps daily record of extra work performed
    and materials used

15
  • Mobilization Costs
  • Initial expenditures contractor makes before any
    work towards progress payment
  • Permits, insurance, bonds
  • Equipment
  • Tools and supplies to do work
  • Field Office
  • Make it a fixed cost that is on every bid
  • Contractor cannot inflate

16
  • Make sure that all items allowed in the
    mobilization cost are listed
  • Can then either
  • Prorate mobilization based on complete
  • Or Lump sum when all complete
  • Other items to include
  • RPR Field Office Utilities Communications
  • Pg 448

17
Mobilization
  • Lump Sum Projects
  • Mobilization terms must be in a separate
    technical section
  • Lump sum for mobilization
  • Unit Price Projects
  • Part of Measurement and Payment section with a
    separate line item and an A/E determined cost

18
Partial Payment to Contractor
  • Waiver of Lien Procedure
  • After each progress payment GC, subs, suppliers
    all sign waivers of liens for that payment
  • Owner knows subs and suppliers are paid
  • Limits the amount of the lien to only what has
    not been paid

19
  • Total Cost Pricing of Change Orders
  • Compares total cost to do work with bid cost to
    do work, owner pays difference
  • Allowed when
  • Nature of claim makes it v. difficult to
    establish an accurate price
  • Contractors bid was realistic
  • Contractors costs were realistic
  • Contractors actual costs were realistic
  • Contractor was not responsible for any of the
    increased cost

20
  • Forward pricing of Change orders
  • GC and Owner establish a mutually agreed lump sum
    payment for work
  • Contractor cannot be forced to forward price work
  • Contractor needs to make sure price is right
    they are stuck with it

21
  • Retainage
  • 5 10 of contract price
  • Gives owner to satisfy lien claims if GC does
    not pay
  • Also is the profit
  • Can do either a lump sum or it can be computed
    based on each months progress payments

22
  • Retainage given to GC 35 days after completion of
    work if
  • all lien releases turned in
  • All employees paid
  • Approval of the performance insurance CO.
  • GC gets all but the amount representing the value
    of uncompleted or substandard work or materials.

23
  • Liquidated Damages during construction
  • Can have liquidated damages for missed milestones
  • Throws other contractors behind
  • Deduct from next progress payment

24
Interpreting the Contractors Bid
  • Bidding Errors
  • Mathematical errors (unit price x quantity)
  • Adding up bid items
  • Ask for values in words and numbers
  • Words rule
  • GC may or may not get released from bid

25
  • Unbalanced Bids
  • Contractor raises prices on some items and lowers
    prices on others w/o changing total project cost
  • Should be rejected if found

26
  • Why do unbalanced bids
  • To discourage certain types of construction and
    encourage others that the Contractor is good at
  • Contractor thinks A/E estimate is low can make
    unit price high and make extra profit
  • Increase unit prices on first items of work to be
    completed gt receive excessive early payments
    then default on the job
  • Leaves Surety with too little to do job

27
  • Can build up working capital eliminates squeeze
    due to 10 retention
  • Detecting an Unbalanced Bid
  • Usually an unbalanced bid indicates and A/E error
    in estimate
  • Use a spreadsheet to compare bids to find wide
    swings in bid prices
  • All contractors should be in the same price
    range if normal bid

28
  • Resolving an Unbalanced Bid
  • Easiest way is to reject all bids (owners
    perogative)
  • Take bids to A/E point out area where possible
    error exists in estimate
  • Get a new estimate
  • Rebid job

29
  • Measurement for Payment
  • Certain measurements do not represent true pay
    quantities
  • Pipeline paid for by amount shown on drawing
  • Drawing shows horizontal distance not length of
    pipeline on grade
  • Does not include pipe overlap (bell spigot
    joint)
  • Contractor must take this into account when
    bidding job
  • RPR must know how to measure bid item

30
  • Rock and Earth Quantities
  • Compacted earth takes up less area than earth in
    natural state (shrinkage)
  • shrinkage depends on material and compaction
    methods
  • Fine Sand 6, Sand and Gravel 8, Ordinary Clay
    10, Loam 12, Surface Soil 15
  • Rock takes up more space when removed (swell)
    from ground

31
  • RPR and contractor should agree on a method of
    measuring material and use it throughout project
  • Truckloads of loose material
  • Water content can change weight of load
  • 10 WC 500lbs extra / 10 ton load
  • Pay for materials in place as calculated from
    dimensions shown on the plans
  • Must be careful on a unit price bid to make sure
    contractor is not over excavating to use more
    material.

32
  • Paving Quantities
  • Small differences in depth can make a huge
    difference in price
  • 0.5 over a 12 lane 1 mile long 2200
  • Also need to make sure that asphalt is at
    temperature when spread

33
Measurement Guidelines for Unit Price Quantities
  • Pipelines depend on contract can be horizontal
    distance (drawings), measures along top of joined
    pipe
  • Do not measure along side of pipe
  • Curbs top edge facing the street
  • Channels use same location in channel for each
    measurement
  • Sewer Lines measure edge of manhole to edge of
    manhole manholes separate item

34
  • Fencing horizontal or along top rail of fence
  • Pavements area but watch for underruns on
    pavement thickness
  • Retaining walls each wall is measured as a
    prism, where walls meet do not double count

35
  • Final Payment to Contractor
  • After CO contractor can apply for final payment
  • Contractor must pay all bills or other
    indebtedness
  • Must submit receipts, releases, and waivers of
    liens
  • Consent of Surety must be obtained
  • Less retainage

36
  • When computing contractors last payment consider
    for deduction in addition to retainage
  • Any liquidated damages
  • Twice the value of all outstanding punch list
    items
  • The value of any lien claims already on file
  • Final payment should not be approved until after
    formal acceptance of the work by owner (Notice of
    Substantial completion)