Title: Towards Outcome-Based Incentives for Grid-Connected Windpower
1Towards Outcome-Based Incentives for
Grid-Connected Windpower Energy Conclave
2006 Implementing the Integrated Energy
Policy IRADe, New Delhi, 27th July 2006
Ajay Mathur President Senergy Global Pvt Ltd India
2Overview
- IEP stresses need to move away from capital
subsidies towards performance incentives, such as
Tradeable Tax Rebate Certificates - Wind projects have need for high cashflow in
early years because debt-service coverage ratio
is low this need is met by cashflow from the
currently available accelerated depreciation
benefit - A TTRC of Rs. 1 per kWh, subject to a maximum of
Rs. 17 lakhs per MW per year, for the first four
years of a project, can provide the same benefit
as accelerated depreciation
3Subsidy should be linked to outcomes
- IEP, Chapter VII Policy for Renewable and
Non-Conventional Energy - Price subsidy should be linked to outcomes. Thus,
for example, giving a capital subsidy on wind
power plant provides encouragement to set-up a
power plant but does not provide additional
incentive to generate power - capital subsidy, however, can be linked to the
amount of power actually generated, if it is
given in the form of Tradable Tax Rebate
Certificates (TTRC)
4Depreciation benefit helps the repayment capacity
of wind power projects
- Assumptions
- Rs 5 crore/MW
- PLF-20
- Buy-back rate Rs 3.10/kWh (5 escalation)
With 80 Accelerated Depreciation Average DSCR
1.70
Without Depreciation Average DSCR 1.39
5The shift to TTRC The much required correction
- The current accelerated depreciation, for
installation of wind energy projects, to be
supplemented by a system of tax credit
certificates of equivalent value, earned through
the generation of electricity from these
projects.
6What are TTRCs ?
- Rearrangement of existing cash-flow of tax
forgone/tax collected by Government of India,
from wind energy projects, in order to link with
energy generation by using the same discount
factor - REVENUE NEUTRAL VIS-À-VIS BASE CASE
- TCCs are tax credit certificates to be given on a
unit generation of electricity (much like in US)
with a possibility of a transfer to a third party - Ensure performance
- Create a framework for non-recourse project
financing - Push a way for large sized wind projects (50 MW
and above) - Culminate into an environment to attract FDI in
wind energy projects - Lower the cost of generation, and in turn the
tariff
7Advantages of TTRCs
- Direct
- Participation of serious energy sector players
- Encourage higher performance improving the
economics - Break investment barrier which is currently
linked with tax appetite - Indirect
- Energy diversity/security environment benefits
- Higher tax revenues with expanded markets
- Being generation linked, would put extensive
thrust on RD and improved OM - Push project financing, thereby reduction in
Capex
8The design of Revenue neutrality
- Current model of accelerated depreciation
- Tax deferral against a normal depreciation (for
PM) accounted using time value of money
(discount rate of 12) - Wind energy projects subsequently generate profit
and thereby pay tax on operations - TTRC is designed for the same revenue neutrality
(atleast in designing) so that it is not a burden
on the exchequer
9Yearly tax loss/gain to exchequer
TCC payments
Depreciation Tax shelter
10The way ahead
- Not changing the set-up hence TTRCs offered
alongwith accelerated depreciation - Project proponent can choose the following option
at the start of the project - Availing 80 depreciation benefit, OR
- Availing TTRC (per unit of generation, subject to
a certain cap per MW per year) for a period of
years
11TTRC Benefit
- A possible TTRC design so as to maintain
revenue neutrality for the government compared to
the current accelerated depreciation regime
could be - Rs.1 per kWh generated for the first four years,
subject to a cap of Rs. 17 lakh per MW per year - Other combinations of value, duration and cap are
also possible -
12Plausible implementation framework
13(No Transcript)
14(No Transcript)
15Trade-offs
- The final design of the TTRC system will involve
tradeoffs - Valuation, duration and cap
- No annual cap
- Annual cap with fixed duration
- Fixed duration
- Transfer
- Taxable or non-taxable
- Tax neutral !!
- Only fixed duration