More on Scheduling - PowerPoint PPT Presentation

About This Presentation
Title:

More on Scheduling

Description:

More on Scheduling – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 19
Provided by: SteveDa65
Category:

less

Transcript and Presenter's Notes

Title: More on Scheduling


1
More on Scheduling
2
Recap of Last Class
  • Activity dependencies are shown through
    CPM/PERT Chart.
  • Critical path
  • Completion date
  • Slack time in non-critical path activities
  • Activity start and end dates and personnel
    responsibilities shown on Gantt Chart.

3
Managing Uncertainty
  • Q How confident can we be in our milestone dates
    and the delivery date?
  • A Using confidence and Statistics
  • for each task, determine pessimistic and
    optimistic times
  • if PT-OT is small for all tasks, then great!!!
  • compute average PT-OT, and std dev
  • if a task's PT-OT is outside the std dev, worry
    about that task

4
Managing Uncertainty
  • Q Where do we schedule uncertainty time?
  • A1 spread it out by bumping each milestone.
  • used by Critical Path
  • A2 lump it together as one activity at end.
  • used by Critical Chain

5
Common PERT Problems
  • Missing dependencies
  • Misinterpretation

6
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
K
M
N
3
4
5
2
1
7
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
K
M
N
3
4
5
2
1
But wait, we can shorten the project if we write
the manual right after testing is finished. (L
and M can be done in parallel.) So
8
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
3
K
2
1
M
N
4
5
But wait, the system needs to be installed
before we can use it to train people. So
9
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
3
K
2
1
5
M
N
4
But what is that activity between dates 3 and 4?
So
10
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
3
K
2
1
5
M
N
4
Dashed line is a dummy activity.
11
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
K
N
M
Note dummies not needed with "activity on node"
graphs.
12
Resource Leveling
  • Activity Shifting
  • to avoid using resources during a peak time.
  • use slack in start and end dates
  • Activity Splitting
  • to shorten duration
  • break activity into pieces when more resources
    are available
  • Optimize the System, not individual tasks
  • Leveling usually yields longer projects

13
Example
B 2wk
C 2wks
D 2wks
H 3wks
I 2wks
A 3wks
E 2wks
F 5wks
G 3wks
  • What is the completion time?
  • Since F is so long, what would be the completion
    time if we break it into two parallel parts of
    2wks and 3wks?

14
Theory of Constraints
  • The Goal by Goldratt in 1997
  • Traditional approach is to divide and divide into
    manageable parts, then optimize these parts.
  • TOC looks at the whole system.
  • Identify In order to manage a constraint, it is
    first necessary to identify it.
  • Exploit Focus on how to get more production
    within the existing capacity limitations.
  • Subordinate Prevent the materials needed next
    from waiting in a queue at a non-constraint
    resource.
  • Elevate If, after fully exploiting this process,
    it still cannot produce enough products to meet
    market demand, find other ways to increase
    capacity.
  • Go back to Step 1.

15
Scheduling Tools
  • Gantt Chart producers
  • MS Project
  • Web access
  • Supports multiple projects
  • Dependencies
  • Billing support
  • Resources leveling
  • Gantt charts, activity network,

16
MS Project
17
Open WorkBench
18
ATC Professional
Write a Comment
User Comments (0)
About PowerShow.com