Title: KC-135: Particle Damping
1KC-135 Particle Damping
- Bill Tandy
- Tim Allison
- Rob Ross
- John Hatlelid
2Introduction
- Team Overview
- Project Description
- Theory
- Design
- Budget
- Schedule
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
3The Team-Bill Tandy
- Internship Experiences Lead to the Concept
- Became the de Facto Leader
- Overall Responsibility for the Project
- Point Man for NASA
- Attends Department Meetings Events
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
4The Team-Tim Allison
- Hard Working and Diligent
- Responsible for Funding
- Arranged Hotel and Travel
- Theoretical Background
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
5The Team-Rob Ross
- Aptitude for Design and Construction
- Given Responsibility for Construction
- Cabinet Design and Construction
- Experiment Materials and Setup
- Volunteered to Write Weekly Memos
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
6The Team-John Hatlelid
- Dedicated and Thorough
- Determined Components of the Experiment
- Responsibility for Applying for Donations
- Worked with Rob on Construction
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
7KC-135 Program
- Annual opportunity for undergraduate student
research - KC-135 Aircraft flies parabolic trajectory to
create microgravity environment - Microgravity environment available for 20-30
seconds
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
8Goals for this Semester
- Understand the underlying concepts of vibrating
cantilever beams - Devise an experiment to test the impact of
particle damping - Gather data on the ground
- Gather data in flight
- Compare the two sets of data
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
9Project Background
- Ball Aerospace Needed Unique Solutions to
Damping Vibrations in Space Structures - Particle Damping was Investigated, but Discarded
Due to Lack of Data - NASAs Student Flight Program Provided the
Perfect Platform for Data Acquisition
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
10Experiment Basics
- Vibrating Cantilever Beam Filled with Particles
of Different Material Properties
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
11Particle Variations
- Twelve Pre-Filled Beams
- Three Materials of Different Density
- Each Material Will Have Two Sizes
- Each Size Will Fill the Beam 50 75
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
12Data Reduction
- Accelerometer will acquire acceleration at the
tip of beam - Peak acceleration amplitude will be plotted vs.
time - We will compare the duration amplitude of
transient, steady-state, and decay period
vibrations for each sample
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
13Theory Overview
- Viscoelastic Damping
- Frictional Damping
- Beam Response
- Problems
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
14Theory Viscoelastic Damping
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Particles collide with other particles and with
the cavity wall - Energy only conserved for perfectly elastic
collisions, where particles are undeformed - Particles may be represented with Maxwell model
- Dashpot in Maxwell model represents viscoelastic
damping within material
Source University of Texas
Bill Tandy Tim Allison Rob Ross John Hatlelid
15Theory Frictional Damping
- Friction forces act on particles as they scrape
against each other and cavity walls, converting
kinetic energy to thermal energy - Particle-Particle
- Particle-Cavity
- Particle-Cavity Equations are only useful in a
gravitational field
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Source Olson Drake, University of Dayton
Bill Tandy Tim Allison Rob Ross John Hatlelid
16Theory Beam Response
- System is a cantilever beam with sinusoidal base
excitation - Differential EOM is
- Solution is an infinite sum
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
y(t)Y0sin(?t)
u(x,t)
Algebraic Eigensolutions
Solutions to Modal ODEs
Bill Tandy Tim Allison Rob Ross John Hatlelid
17Theory - Problems
- Theoretical solution possible for hollow rod,
but with added particles the problem becomes
extremely complex - A theoretical prediction of the beams motion
will not be attempted - The effect of particles will be analyzed
experimentally on the KC-135
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
18Test Bay Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Some factors influencing the design
- Requirements
- Size
- Procedures
- Materials
Bill Tandy Tim Allison Rob Ross John Hatlelid
19Test Bay Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Some factors influencing the design
- Requirements
- Size
- Procedures
- Materials
Bill Tandy Tim Allison Rob Ross John Hatlelid
20Test Bay Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Some factors influencing the design
- Requirements
- Size
- Procedures
- Materials
Bill Tandy Tim Allison Rob Ross John Hatlelid
21Test Bay Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Some factors influencing the design
- Requirements
- Size
- Procedures
- Materials
Bill Tandy Tim Allison Rob Ross John Hatlelid
22Test Bay Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Some factors influencing the design
- Requirements
- Size
- Procedures
- Materials
Bill Tandy Tim Allison Rob Ross John Hatlelid
23Test Bay Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Some factors influencing the design
- Requirements
- Size
- Procedures
- Materials
Bill Tandy Tim Allison Rob Ross John Hatlelid
24Test Bay Design Requirements
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Structurally sound (withstand 9 Gs)
- Secure to Aircraft
- Test equipment security
- Test equipment containment
- Weight per spacer
- Non-hazardous
Bill Tandy Tim Allison Rob Ross John Hatlelid
25Test Bay Design Requirements
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Structurally sound (withstand 9 Gs)
- Secure to Aircraft
- Test equipment security
- Test equipment containment
- Weight per spacer
- Non-hazardous
Bill Tandy Tim Allison Rob Ross John Hatlelid
26Test Bay Design Requirements
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Structurally sound (withstand 9 Gs)
- Secure to Aircraft
- Test equipment security
- Test equipment containment
- Weight per spacer
- Non-hazardous
Bill Tandy Tim Allison Rob Ross John Hatlelid
27Test Bay Design Requirements
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Structurally sound (withstand 9 Gs)
- Secure to Aircraft
- Test equipment security
- Test equipment containment
- Weight per spacer
- Non-hazardous
Bill Tandy Tim Allison Rob Ross John Hatlelid
28Test Bay Design Requirements
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Structurally sound (withstand 9 Gs)
- Secure to Aircraft
- Test equipment security
- Test equipment containment
- Weight per spacer
- Non-hazardous
Bill Tandy Tim Allison Rob Ross John Hatlelid
29Test Bay Design Requirements
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Structurally sound (withstand 9 Gs)
- Secure to Aircraft
- Test equipment security
- Test equipment containment
- Weight per spacer
- Non-hazardous
Bill Tandy Tim Allison Rob Ross John Hatlelid
30Test Bay Design Requirements
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Structurally sound (withstand 9 Gs)
- Secure to Aircraft
- Test equipment security
- Test equipment containment
- Weight per spacer
- Non-hazardous
Bill Tandy Tim Allison Rob Ross John Hatlelid
31Test Bay Design Size
- Layout
- Spacing
- Weight
- Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
32Test Bay Design Size
- Layout
- Spacing
- Weight
- Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
33Test Bay Design Size
- Layout
- Spacing
- Weight
- Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
34Test Bay Design Size
- Layout
- Spacing
- Weight
- Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
35Test Bay Design Size
- Layout
- Spacing
- Weight
- Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
36Test Bay Design Size / Layout
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
37Test Bay Design Size / Layout
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
38Test Bay Design Size / Layout
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
39Test Bay Design Size / Spacing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Ample room for test operation
- Specimens laid end to end
- Function generator, Line conditioner, Surge
protector - Computer, Work space
Bill Tandy Tim Allison Rob Ross John Hatlelid
40Test Bay Design Size / Spacing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Ample room for test operation
- Specimens laid end to end
- Function generator, Line conditioner, Surge
protector - Computer, Work space
Bill Tandy Tim Allison Rob Ross John Hatlelid
41Test Bay Design Size / Spacing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Ample room for test operation
- Specimens laid end to end
- Function generator, Line conditioner, Surge
protector - Computer, Work space
Bill Tandy Tim Allison Rob Ross John Hatlelid
42Test Bay Design Size / Spacing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Ample room for test operation
- Specimens laid end to end
- Function generator, Line conditioner, Surge
protector - Computer, Work space
Bill Tandy Tim Allison Rob Ross John Hatlelid
43Test Bay Design Size / Spacing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Ample room for test operation
- Specimens laid end to end
- Function generator, Line conditioner, Surge
protector - Computer, Work space
Bill Tandy Tim Allison Rob Ross John Hatlelid
44Test Bay Design Size / Weight
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 200 lbs per spacer used
- 6 spacers required
- 300 lbs max weight
- Our weight approximately 280 lbs
Bill Tandy Tim Allison Rob Ross John Hatlelid
45Test Bay Design Size / Weight
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 200 lbs per spacer used
- 6 spacers required
- 300 lbs max weight
- Our weight approximately 280 lbs
Bill Tandy Tim Allison Rob Ross John Hatlelid
46Test Bay Design Size / Weight
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 200 lbs per spacer used
- 6 spacers required
- 300 lbs max weight
- Our weight approximately 280 lbs
Bill Tandy Tim Allison Rob Ross John Hatlelid
47Test Bay Design Size / Weight
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 200 lbs per spacer used
- 6 spacers required
- 300 lbs max weight
- Our weight approximately 280 lbs
Bill Tandy Tim Allison Rob Ross John Hatlelid
48Test Bay Design Size / Weight
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 200 lbs per spacer used
- 6 spacers required
- 300 lbs max weight
- Our weight approximately 280 lbs
Bill Tandy Tim Allison Rob Ross John Hatlelid
49Test Bay Design Size / Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 30 second zero G maneuver
- 40 seconds for test specimen swap and test setup
- Requires that test areas be uncluttered
Bill Tandy Tim Allison Rob Ross John Hatlelid
50Test Bay Design Size / Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 30 second zero G maneuver
- 40 seconds for test specimen swap and test setup
- Requires that test areas be uncluttered
Bill Tandy Tim Allison Rob Ross John Hatlelid
51Test Bay Design Size / Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 30 second zero G maneuver
- 40 seconds for test specimen swap and test setup
- Requires that test areas be uncluttered
Bill Tandy Tim Allison Rob Ross John Hatlelid
52Test Bay Design Size / Timing
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 30 second zero G maneuver
- 40 seconds for test specimen swap and test setup
- Requires that test areas be uncluttered
Bill Tandy Tim Allison Rob Ross John Hatlelid
53Test Bay Design Procedures
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Prior to parabola, move into position in front of
experimental assembly - Unlatch plexiglass door
- Remove safety pins from specimens
- Remove point mass from specimen
- Remove specimen from base mass
- Unlatch Upper Bay doors
- Select next specimen from storage bay
- Note new specimen selected
- Replace previous specimen in storage bay
- Close and latch upper bay doors
- Insert new specimen into base mass
- Attach point mass
- Insert safety pins
- Close and latch Plexiglas bay door
- Configure LabView for next parabola
Bill Tandy Tim Allison Rob Ross John Hatlelid
54Test Bay Design Procedures / Latch
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Prior to parabola, move into position in front of
experimental assembly - Unlatch plexiglass door
- Remove safety pins from specimens
- Remove point mass from specimen
- Remove specimen from base mass
- Unlatch Upper Bay doors
- Select next specimen from storage bay
- Note new specimen selected
- Replace previous specimen in storage bay
- Close and latch upper bay doors
- Insert new specimen into base mass
- Attach point mass
- Insert safety pins
- Close and latch Plexiglas bay door
- Configure LabView for next parabola
Bill Tandy Tim Allison Rob Ross John Hatlelid
55Test Bay Design Procedures / Latch
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Prior to parabola, move into position in front of
experimental assembly - Unlatch plexiglass door
- Remove safety pins from specimens
- Remove point mass from specimen
- Remove specimen from base mass
- Unlatch upper bay doors
- Select next specimen from storage bay
- Note new specimen selected
- Replace previous specimen in storage bay
- Close and latch upper bay doors
- Insert new specimen into base mass
- Attach point mass
- Insert safety pins
- Close and latch Plexiglas bay door
- Configure LabView for next parabola
Bill Tandy Tim Allison Rob Ross John Hatlelid
56Test Bay Design Procedures / Latch
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Prior to parabola, move into position in front of
experimental assembly - Unlatch plexiglass door
- Remove safety pins from specimens
- Remove point mass from specimen
- Remove specimen from base mass
- Unlatch Upper doors
- Select next specimen from storage bay
- Note new specimen selected
- Replace previous specimen in storage bay
- Close and latch upper bay doors
- Insert new specimen into base mass
- Attach point mass
- Insert safety pins
- Close and latch Plexiglas bay door
- Configure LabView for next parabola
Bill Tandy Tim Allison Rob Ross John Hatlelid
57Test Bay Design Procedures / Latch
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Prior to parabola, move into position in front of
experimental assembly - Unlatch plexiglass door
- Remove safety pins from specimens
- Remove point mass from specimen
- Remove specimen from base mass
- Unlatch Upper Bay doors
- Select next specimen from storage bay
- Note new specimen selected
- Replace previous specimen in storage bay
- Close and latch upper doors
- Insert new specimen into base mass
- Attach point mass
- Insert safety pins
- Close and latch Plexiglas bay door
- Configure LabView for next parabola
Bill Tandy Tim Allison Rob Ross John Hatlelid
58Test Bay Design Procedures / Latch
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Prior to parabola, move into position in front of
experimental assembly - Unlatch plexiglass door
- Remove safety pins from specimens
- Remove point mass from specimen
- Remove specimen from base mass
- Unlatch Upper Bay doors
- Select next specimen from storage bay
- Note new specimen selected
- Replace previous specimen in storage bay
- Close and latch upper bay doors
- Insert new specimen into base mass
- Attach point mass
- Insert safety pins
- Close and latch Plexiglas door
- Configure LabView for next parabola
Bill Tandy Tim Allison Rob Ross John Hatlelid
59Test Bay Design Materials
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Cost Availability to strength ratios
- Base - MDF
- Frame - Steel
- Walls and Shelves 7 ply
Bill Tandy Tim Allison Rob Ross John Hatlelid
60Test Bay Design Materials
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Cost Availability to strength ratios
- Base - MDF
- Frame - Steel
- Walls and Shelves 7 ply
Bill Tandy Tim Allison Rob Ross John Hatlelid
61Test Bay Design Materials
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Cost Availability to strength ratios
- Base - MDF
- Frame - Steel
- Walls and Shelves 7 ply
Bill Tandy Tim Allison Rob Ross John Hatlelid
62Test Bay Design Materials
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Cost Availability to strength ratios
- Base - MDF
- Frame - Steel
- Walls and Shelves 7 ply
Bill Tandy Tim Allison Rob Ross John Hatlelid
63Test Bay Design Materials
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Cost Availability to strength ratios
- Base - MDF
- Frame - Steel
- Walls and Shelves 7 ply
Bill Tandy Tim Allison Rob Ross John Hatlelid
64Test Bay Design Materials / Base
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 4 2X4 ft and half in. thick sheets of MDF
- 4 Casters Rated for 150 lbs each
Bill Tandy Tim Allison Rob Ross John Hatlelid
65Test Bay Design Materials / Base
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 4 2X4 ft and half in. thick sheets of MDF
- 4 Casters Rated for 150 lbs each
Bill Tandy Tim Allison Rob Ross John Hatlelid
66Test Bay Design Materials / Base
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- 4 2X4 ft and half in. thick sheets of MDF
- 4 Casters Rated for 150 lbs each
Bill Tandy Tim Allison Rob Ross John Hatlelid
67Test Bay Design Materials / Frame
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Steel angle iron
- Steel L-Clamps
- Steel truss members
Bill Tandy Tim Allison Rob Ross John Hatlelid
68Test Bay Design Materials / Frame
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Steel angle iron
- Steel L-Clamps
- Steel truss members
Bill Tandy Tim Allison Rob Ross John Hatlelid
69Test Bay Design Materials / Frame
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Steel angle iron
- Steel L-Clamps
- Steel truss members
Bill Tandy Tim Allison Rob Ross John Hatlelid
70Test Bay Design Materials / Frame
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Steel angle iron
- Steel L-Clamps
- Steel truss members
Bill Tandy Tim Allison Rob Ross John Hatlelid
71Test Bay Design Materials / Walls Shelves
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
72Test Bay Design Materials / Walls Shelves
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
73Hardware Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- A data acquisition system is needed to determine
the response in the beam - The system will use two accelerometers
- The data acquisition system must be lightweight
and capable of interfacing with a laptop
Bill Tandy Tim Allison Rob Ross John Hatlelid
74Hardware Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- A data acquisition system is needed to determine
the response in the beam - The system will use two accelerometers
- The data acquisition system must be lightweight
and capable of interfacing with a laptop
Bill Tandy Tim Allison Rob Ross John Hatlelid
75Hardware Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- A data acquisition system is needed to determine
the response in the beam - The system will use two accelerometers
- The data acquisition system must be lightweight
and capable of interfacing with a laptop
Bill Tandy Tim Allison Rob Ross John Hatlelid
76Hardware Design
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- A data acquisition system is needed to determine
the response in the beam - The system will use two accelerometers
- The data acquisition system must be lightweight
and capable of interfacing with a laptop
Bill Tandy Tim Allison Rob Ross John Hatlelid
77Hardware Selection
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- DAQ System
- We consulted Travis Fergusson at National
Instruments - Currently we are looking at using National
Instruments hardware for data acquisition
Bill Tandy Tim Allison Rob Ross John Hatlelid
78Hardware Selection
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- DAQ System
- We consulted Travis Fergusson at National
Instruments - Currently we are looking at using National
Instruments hardware for data acquisition
Bill Tandy Tim Allison Rob Ross John Hatlelid
79Hardware Selection
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- DAQ System
- We consulted Travis Fergusson at National
Instruments - Currently we are looking at using National
Instruments hardware for data acquisition
Bill Tandy Tim Allison Rob Ross John Hatlelid
80DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI - 6036 DAQ Card
- Lightweight
- Can be interfaced with a laptop
- Supports SCC line conditioner
- Has many inputs with high sampling rates
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
81DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI - 6036 DAQ Card
- Lightweight
- Can be interfaced with a laptop
- Supports SCC line conditioner
- Has many inputs with high sampling rates
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
82DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI - 6036 DAQ Card
- Lightweight
- Can be interfaced with a laptop
- Supports SCC line conditioner
- Has many inputs with high sampling rates
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
83DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI - 6036 DAQ Card
- Lightweight
- Can be interfaced with a laptop
- Supports SCC line conditioner
- Has many inputs with high sampling rates
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
84DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI - 6036 DAQ Card
- Lightweight
- Can be interfaced with a laptop
- Supports SCC line conditioner
- Has many inputs with high sampling rates
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
85DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI SC-2345
- Modular unit for SCC line conditioning
- SCC line conditioning is low cost and portable
- With low number of inputs, this is an ideal
system
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
86DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI SC-2345
- Modular unit for SCC line conditioning
- SCC line conditioning is low cost and portable
- With low number of inputs, this is an ideal
system
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
87DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI SC-2345
- Modular unit for SCC line conditioning
- SCC line conditioning is low cost and portable
- With low number of inputs, this is an ideal
system
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
88DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI SC-2345
- Modular unit for SCC line conditioning
- SCC line conditioning is low cost and portable
- With low number of inputs, this is an ideal
system
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
89DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI SCC-ACC01
- Accelerometer module
- Designed to take inputs from accelerometers and
send the signal to the DAQ card - Provides power for accelerometer
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
90DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI SCC-ACC01
- Accelerometer module
- Designed to take inputs from accelerometers and
send the signal to the DAQ card - Provides power for accelerometer
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
91DAQ System
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- NI SCC-ACC01
- Accelerometer module
- Designed to take inputs from accelerometers and
send the signal to the DAQ card - Provides power for accelerometer
Image courtesy of National Instruments
Bill Tandy Tim Allison Rob Ross John Hatlelid
92Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Interface with SCC DAQ system
- Compact size and weight
- High natural frequency
- Able to measure low frequencies
Bill Tandy Tim Allison Rob Ross John Hatlelid
93Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Interface with SCC DAQ system
- Compact size and weight
- High natural frequency
- Able to measure low frequencies
Bill Tandy Tim Allison Rob Ross John Hatlelid
94Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Interface with SCC DAQ system
- Compact size and weight
- High natural frequency
- Able to measure low frequencies
Bill Tandy Tim Allison Rob Ross John Hatlelid
95Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Interface with SCC DAQ system
- Compact size and weight
- High natural frequency
- Able to measure low frequencies
Bill Tandy Tim Allison Rob Ross John Hatlelid
96Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Honeywell PA Accelerometer
- 3-5000 Hz frequency range
- 50 g range
- Rugged
- Natural frequency of 30 kHz
Image courtesy of Honeywell
Bill Tandy Tim Allison Rob Ross John Hatlelid
97Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Honeywell PA Accelerometer
- 3-5000 Hz frequency range
- 50 g range
- Rugged
- Natural frequency of 30 kHz
Image courtesy of Honeywell
Bill Tandy Tim Allison Rob Ross John Hatlelid
98Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Honeywell PA Accelerometer
- 3-5000 Hz frequency range
- 50 g range
- Rugged
- Natural frequency of 30 kHz
Image courtesy of Honeywell
Bill Tandy Tim Allison Rob Ross John Hatlelid
99Accelerometers
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Honeywell PA Accelerometer
- 3-5000 Hz frequency range
- 50 g range
- Rugged
- Natural frequency of 30 kHz
Image courtesy of Honeywell
Bill Tandy Tim Allison Rob Ross John Hatlelid
100Shaker
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Exact shaker is still to be determined
- Needs to be lightweight
- Shaker must provide an input of around 100 Hz
Image courtesy of Labworks
Bill Tandy Tim Allison Rob Ross John Hatlelid
101Shaker
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Exact shaker is still to be determined
- Needs to be lightweight
- Shaker must provide an input of around 100 Hz
Image courtesy of Labworks
Bill Tandy Tim Allison Rob Ross John Hatlelid
102Shaker
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Exact shaker is still to be determined
- Needs to be lightweight
- Shaker must provide an input of around 100 Hz
Image courtesy of Labworks
Bill Tandy Tim Allison Rob Ross John Hatlelid
103Shaker Input Device
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Shaker input must come from a power supply and
function generator - Exact function generator and power supply cannot
be determined until a shaker has been determined - Possible shaker source is from Dr. Stearman
Bill Tandy Tim Allison Rob Ross John Hatlelid
104Shaker Input Device
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Shaker input must come from a power supply and
function generator - Exact function generator and power supply cannot
be determined until a shaker has been determined - Possible shaker source is from Dr. Stearman
Bill Tandy Tim Allison Rob Ross John Hatlelid
105Shaker Input Device
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
- Shaker input must come from a power supply and
function generator - Exact function generator and power supply cannot
be determined until a shaker has been determined - Possible shaker source is from Dr. Stearman
Bill Tandy Tim Allison Rob Ross John Hatlelid
106Project Expenses
Item Quantity Cost per Item Total Cost
Supplies and Materials - - -
Rods 24 15 360
Cabinet Materials 1 410 410
Damping Particles 1 100 100
Rod Mount 1 60 60
Misc. Construction 1 50 50
Cabinet Anchors 4 10 40
Wiring 1 25 25
End Mass 1 5 5
Travel, Lodging, and Medical - - -
Meals 150 7 1050
Hotel Fees 9 100 900
Travel 2 850 1700
Student Physicals 4 75 300
TOTAL COST 5000
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
107Project Expenses
Item Quantity Cost per Item Total Cost
Supplies and Materials - - -
Rods 24 15 360
Cabinet Materials 1 410 410
Damping Particles 1 100 100
Rod Mount 1 60 60
Misc. Construction 1 50 50
Cabinet Anchors 4 10 40
Wiring 1 25 25
End Mass 1 5 5
Travel, Lodging, and Medical - - -
Meals 150 7 1050
Hotel Fees 9 100 900
Travel 2 850 1700
Student Physicals 4 75 300
TOTAL COST 5000
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
108Project Expenses
Item Quantity Cost per Item Total Cost
Supplies and Materials - - -
Rods 24 15 360
Cabinet Materials 1 410 410
Damping Particles 1 100 100
Rod Mount 1 60 60
Misc. Construction 1 50 50
Cabinet Anchors 4 10 40
Wiring 1 25 25
End Mass 1 5 5
Travel, Lodging, and Medical - - -
Meals 150 7 1050
Hotel Fees 9 100 900
Travel 2 850 1700
Student Physicals 4 75 300
TOTAL COST 5000
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
109Funding and Other Aid
- NASA gave time space on the KC-135
- UT ASE Department gave 3000 and use of Laptop
and Digital Video Camera - Texas Space Grant Consortium gave 2000 for
specific costs - Honeywell donated accelerometers
- National Instruments donated LabView license,
possibly other hardware
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
110Current Financial Status
- Equipment so far has been less expensive than
anticipated - The surplus funds leave us extra options in case
of unexpected changes - The project will be completed within budget
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
111Schedule
Task Start Finish
Obtain Equipment Jan. 20 March 18
Build Test Bay Feb. 20 March 18
Testing March 19 March 20
Ground Experiments March 21 March 22
Evacuation Plans March 10 March 17
Flight Dates April 1 April 10
Data Reduction April 10 April 12
Final Presentation April 11 May 3
Final Paper April 11 End of Class
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid
112Summary
- Team Overview
- Project Description
- Theory
- Design
- Budget
- Schedule
The Team
Project Description
Theory
Design
Budget
Schedule
Summary
Bill Tandy Tim Allison Rob Ross John Hatlelid