The West Main Street Bridge Rehabilitation - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

The West Main Street Bridge Rehabilitation

Description:

... adjacent to structural steel Damaged structural elements due to impact Operator house to be upgraded using a suitable cladding ... Architectural repairs to the ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 12
Provided by: Lian152
Category:

less

Transcript and Presenter's Notes

Title: The West Main Street Bridge Rehabilitation


1
The West Main Street Bridge Rehabilitation
2
Outline
  • History of The West Main Street Bridge
  • Overview of The Project
  • Why is Rehabilitation Needed?
  • Rehabilitation Program

3
History of The West Main Street Bridge
  • Steel truss bridge crossing over The Old Welland
    Canal Previously a lift bridge, but is now in a
    fixed state.
  • Built between 1929-1930.
  • Presently the bridge carries two lanes of
    westbound traffic with an average annual daily
    traffic of 10,700 vehicles.

4
History of The West Main Street Bridge
  • Last rehabilitation of the bridge occurred in
    2005
  • Concrete repairs to the bridge deck, abutments
    and piers.
  • New concrete sidewalks, approach slabs, steel
    abutment bearings, pier and abutment expansion
    joints.
  • Removal of steel splash guards.
  • Below deck structural repairs.
  • Re-coating of structural steel 1.8 m above the
    roadway.

5
Overview of The Current Project
  • A full bridge inspection was carried out in the
    fall of 2013 according to current Ontario
    Structure Inspection Manual (OSIM) guidelines.
  • The report provided rehabilitation
    recommendations to extend the useful life of the
    bridge, and to
  • Re-assed previous inspection reports to refine
    rehabilitation costs.

6
Why is Rehabilitation Needed?
7
  • BRIDGE CONDITION
  • Common areas of deterioration include peeling of
    coating, light to moderate corrosion and areas
    section loss
  • Areas that not have been re-coated are
    susceptible to deterioration caused by rain, snow
    and salt

8
  • BRIDGE CONDITION
  • Typical areas of section loss where the original
    splash guard was removed
  • 100 section loss at some locations

9
  • BRIDGE CONDITION
  • Some areas underneath bridge need re-coating
    since the last project
  • Areas of corrosion and section loss are common
  • Concrete delamination on bridge concrete piers

10
  • BRIDGE CONDITION
  • 200 mm gap on sidewalk adjacent to structural
    steel
  • Damaged structural elements due to impact
  • Operator house to be upgraded using a suitable
    cladding system

11
Rehabilitation Program
  • A 3-coat paint system is recommended.
  • Steel repairs are recommended including
  • Plate repairs
  • Steel angle replacements
  • Gusset plate replacements
  • Lacing and batten plate replacements
  • Architectural repairs to the operator house are
    recommended
Write a Comment
User Comments (0)
About PowerShow.com