Future Protons for 8 GeV Program - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Future Protons for 8 GeV Program

Description:

Future Protons for 8 GeV Program Eric Prebys FNAL Accelerator Physics Center – PowerPoint PPT presentation

Number of Views:73
Avg rating:3.0/5.0
Slides: 25
Provided by: mcginnis
Learn more at: https://home.fnal.gov
Category:

less

Transcript and Presenter's Notes

Title: Future Protons for 8 GeV Program


1
Future Protons for 8 GeV Program
  • Eric Prebys FNAL Accelerator Physics Center

2
Disclaimer
  • I no longer have any official involvement with
    the Proton Source or Accelerator Division.
  • This talk represents strictly my own (correct)
    opinions.

3
Background
  • With the installation of the new Booster
    correctors, the Proton Plan is effectively over
  • Max beam to NuMIpBar
  • 1-2e20 protons/year to 8 GeV line (BNB)
  • The system will now supply enough protons for
    NoVA with nothing left over for an 8 GeV program
  • Running the Booster at a full 15 Hz would provide
    4e20 protons/year to an 8 GeV program
  • We kinda-sorta know what we need to do that,
    but there is as yet no official plan or time line
    to do it.

4
Proton Plan Charge
  • Develop a plan for a reasonable set of
    improvements and operational initiatives to
    maximize proton delivery to NuMI and the Booster
    Neutrino Beam (BNB)
  • Estimate the budget and timeline for these
    improvements.
  • Estimate proton delivery to both beam lines if
    the Plan proceeds on schedule.

Very important
5
The Fermilab Accelerator Complex
MinBooNE
NUMI
Proton Plan System
Proton Plan Customer
6
Preac(cellerator) and Linac
New linac (HEL)- Accelerate H- ions from 116
MeV to 400 MeV
Preac - Static Cockroft-Walton generator
accelerates H- ions from 0 to 750 KeV.
Old linac(LEL)- accelerate H- ions from 750 keV
to 116 MeV
7
Booster
  • Accelerates the 400 MeV beam from the Linac to 8
    GeV
  • Operates in a 15 Hz offset resonant circuit
  • Sets fundamental clock of accelerator complex
  • From the Booster, beam can be directed to
  • The Main Injector
  • MiniBooNE (switch occurs in the MI-8 transfer
    line)
  • A dump.
  • More or less original equipment

8
Main Injector
  • The Main Injector can accept 8 GeV protons OR
    antiprotons from
  • Booster
  • The anti-proton accumulator
  • The Recycler (which shares the same tunnel and
    stores antiprotons)
  • It can accelerate protons to 120 GeV (in a
    minimum of 1.4 s) and deliver them to
  • The antiproton production target.
  • The fixed target area.
  • The NUMI beamline.
  • It can accelerate protons OR antiprotons to 150
    GeV and inject them into the Tevatron.

9
Limits to Proton Intensity
  • Total proton rate from Proton Source
    (LinacBooster)
  • Booster batch size
  • 4-5E12 protons/batch, depending on beam quality
    required.
  • Booster repetition rate
  • 15 Hz instantaneous
  • Currently 9Hz, limited by RF system.
  • Beam loss
  • Damage and/or activation of Booster components
  • Above ground radiation
  • Total protons accelerated in Main Injector
  • Maximum main injector load
  • Six slots for booster batches (3E13)
  • Up to 11 with slip stacking (4.5-5.5E13)
  • Beam stability (RF issues)
  • Beam loss concerns
  • Cycle time
  • 1.4s loading time (1/15s per booster batch)

Historically our biggest worry
Critical path for NuMI/MINOS
10
Some Handy Rules of Thumb
  • 1 Booster Hz _at_ 5E12 protons
  • 2E16 protons/hour
  • 1E20 protons/year
  • 6KW at 8 GeV
  • 100 kW at 120 GeV
  • Considerations
  • lt5E12 for slip stacked batches or low losses
  • Realistic up times and intensity ramp - ups

11
Review Main Injector Loading
  • The Main Injector has six usable slots, into
    which Booster batches may be placed.
  • More batches may be loaded, using slip
    stacking, in which an initial batch in the Main
    Injector is accelerated such that a subsequent
    batch will be at a slightly different energy.
  • The two will then drift together and can be
    captured as a single batch (with at least twice
    the longitudinal emittance).
  • This will be done in the Recycler in the NOvA/ANU
    era

12
NuMI Operating Modes
  • Present NuMI operation (29)
  • Five batches loaded into the Main Injector,
    leaving one empty slot.
  • Six more batches loaded and slipped with the
    first to make two for antiproton production and 9
    for NuMI.
  • NOvA Operation (2011 ?)
  • Slip stacking will be done in Recycler to
    eliminate loading time

13
NOnA time line improvements
300 kW
700 kW
14
Summary Significant Elements of Plan
  • Linac
  • Stockpile two year supply of spare 200 MHz power
    amplifier tubes (7835s), in the event of an
    interruption in supply
  • Characterize and improve Low Energy Linac Low
    Level RF
  • Booster
  • Replace and reconfigure injection bump (ORBUMP)
    system.
  • Relocate 8 GeV dump from Booster tunnel to MI-8
    transfer line
  • Make Booster robust to 9 Hz, and understand
    requirements to go to 15 Hz
  • Design, build, and install new corrector system
  • Last element of Proton Plan
  • Main Injector
  • Replace seven quadrupoles with increased aperture
    versions, to reduce injection and extraction
    losses.
  • Operationally develop multi-batch and multi-batch
    slip stacked operation
  • Design and install collimation system, both in
    the MI-8 line and in the MI ring
  • Modify injection kicker to allow multi-batch slip
    stacked operation
  • Characterize and improve to RF system, to support
    high intensity operation.

Proton Plan now complete (at least as far as
hardware is concerned)
15
Proton Delivery
Average Booster Activation
MiniBooNE
NuMI
Factor of 15 increase in protons
16
Total Booster Output
2e17 protons/hour
17
Booster Corrector System
  • Biggest single project in plan
  • Replace all 48 (original) Booster corrector
    packages.
  • Unique new design
  • Six independent multipoles
  • Stronger H and V dipoles
  • 1cm beam motion throughout cycle
  • Stronger quad
  • Arbitrary tune working point throughout cycle
  • Skew quad
  • Coupling, same strength as before.
  • Sextupole and skew sextupole at every period.
  • Less emittance blowup
  • More control of harmonic resonances.
  • Integrated BPM
  • Saves space

16
18
Construction
19
Installation
  • Installed 12/48 in 2007
  • The remaineder were installed in the recent
    shutdown.
  • Currently being commissioned

20
Performance since shutdown
Loss based limit
Batch size
Normalized energy loss
  • Currently, loss limits rate to 1e17
  • Must double this to run at 15 Hz
  • Probably not as hard as it sounds

21
Loss Limits
  • The total rate is limited by losses at particular
    points.
  • As we learn to use the new corrector system, we
    hope to lower these losses.
  • Once weve done everything we can, we can
    consider increasing the limits at these points.
  • That leaves us with the problem of getting to 15
    Hz

22
Booster Repetition Rate
  • The magnetic lattice elements in the Booster
    operate in a 15 Hz resonant circuit.
  • Pulsed magnetic elements and RF system only
    operate when beam is present (plus conditioning
    pre-pulses)
  • When MiniBooNE first started, the average
    repetition rate was limited to 1.5 Hz by the
    extraction septum.
  • Over the last few years all magnetic elements
    have been upgraded to enable 15 Hz operation
  • New extraction septum and power supply
  • New injection bump (ORBUMP) magnets and power
    supply
  • New corrector system.
  • The average rate (including pre-pulses) is
    currently limited to about 9Hz
  • This brings us to the same limit as the loss
    limits, which is why there is no strong pressure
    to reduce them further.
  • Will need to go beyond this to support NOvA8 GeV

23
Getting to 15 Hz
  • All magnetic elements can now run at 15 Hz
  • Remaining limits come from RF system
  • Half of the RF bias supplies
  • These power the tuning curves
  • Half of them (8/19) need new transformers to run
    at 15 Hz
  • RF tuning cones
  • Tuning cones overheat at high rep. rate
  • Cooling channels exist, but are not used and some
    need repair.
  • Anode supply transformers
  • Probably need refurbishment
  • General reliability
  • New solid state RF system?
  • Cost scale (WAG)
  • Cost scale 1-2M for bias supplies, tuning cones
    and anode refurbishment
  • Solid state RF (if needed) 8M
  • If the anode supplies need to be replaced 3M

24
The plan
  • The basic plan is not to have a plan
  • No experiment wants to bear the cost of these
    upgrades
  • Hope to justify them as maintenance to improve
    general reliability
  • Nevertheless, we really have to start thinking
    about these things, since several programs are
    relying on them
  • MicroBooNE
  • g-2
  • Mu2e
  • ??
  • Now that the Booster corrector project is done,
    its probably time to start to think more
    seriously about the rep. rate upgrades.
Write a Comment
User Comments (0)
About PowerShow.com