Title: FY 09 Mission/Program Support Sub-Goal Program Plan William F. Broglie November 16, 2006
1FY 09 Mission/Program Support Sub-GoalProgram
PlanWilliam F. BroglieNovember 16, 2006
Workforce Management
Administrative Services
Acquisition Grants
Financial Services
IT Services
Facilities
2Overview
- FY 09 Program Plan Vision for 2013
- Cost effective, value-added service
provider-of-choice for workforce management,
acquisition and grants, facilities, financial, IT
and administrative services. - Long range plans identifying future requirements
for - Facilities
- Information Technology
- Workforce Management
NEP/NEC Guidance Requested Require IT
Long-Range Plan to be Developed for FY 10-14 PPBES
NEP/NEC Recommendation
3Overview
- FY09 FY13 Program Plan Objectives
- Programs and services comply with legal,
regulatory and departmental mandates and enable
NOAA and its partners to efficiently accomplish
NOAA mission objectives. - Process improvements enhance quality,
cost-effectiveness and timeliness of services and
reflect best management practices - Acquisition and Grants timely awards, aligned
with NOAAs mission effective oversight and
administration to maximize outcomes. - Financial and Administrative Services and
systems compliance with legal/regulatory
requirements enable informed management
decision-making. - Facilities safe, sustainable, and modern with
increased opportunities for collaboration and
integration within NOAA and with NOAAs partners. - IT Secure, sound, and robust infrastructure and
processes to advance NOAA mission leverages
NOAA-wide economies of scale enhances workforce
collaboration and sharing of data and knowledge. - Workforce Management value-added systems and
processes promoting both a highly-skilled
workforce and Merit System principles in support
of NOAA mission goals.
4Overview
- FY09-FY13 Program Plan Achievements
- Acquisition and Grants Integrated and sustained
BPR improvements - Administrative Services Compliance with
requirements HSPD-12, deemed exports,
competitive sourcing, personal property. - Facilities Completion/occupancy of major
facility projects (Pacific Region Center and La
Jolla) facility condition index improved through
targeted restoration investments long-range
planning process. - Financial Services End-to-End Resource
Management System implemented Budget BPR
recommendations fully implemented/integrated. - Information Technology Security/Certification
Accreditation services integrated across NOAA
NOAA Enterprise MIS implemented. - Workforce Management WFM BPR recommendations
partially implemented systems promote employee
competency aligned with NOAA business
requirements e-OPF implemented.
5Overview
- FY09-FY13 Program Plan Shortfalls/Excesses
- NO EXCESSES!
- Program-Specific Shortfalls
- Administrative Services Unfunded/under-funded
mandates with rising expectations/ requirements
deemed exports, HSPD-12, personal property, and
security/guard services. - Facilities Inadequate recapitalization funding
stream to support sustained execution of facility
long term plan. - Financial Services Unfunded requirements for
Working Capital Fund full contribution and CBS
system enhancements. - Information Technology Unfunded requirements
for redundancy in critical infrastructure (e.g.,
single points of failure, network
infrastructure, public web services, and
electronic mail services). Need for
fully-compliant CA and IT Security program.
Inadequate resources to develop and execute
long-range IT recapitalization/modernization plan
and transformation of NOAAs web. - Workforce Management Sustained funding stream
for systems and programs (e.g., integrated human
resources management system, learning management
system and competency models).
6Funding
- NOTES
- Fiscal and programming guidance concerning
facility projects Pacific Region Center, La
Jolla, Fairbanks BIGELOW homeporting
improvements. - Fiscal and programming guidance concerning
transfer of funding from Leadership Sub-Goal to
the Program Support Sub-Goal (Information
Technology Services Program).
7Details
- Strategy to Meet Sub-Goal Objectives and
Fiscal/Programming Guidance - Funds allocated in accordance with fiscal and
programming guidance and in consideration of
Annual Guidance Memo and Strategic Plan. - Identified significant, extensive Gaps with no
excess capacity and no capabilities that could be
eliminated in out-years. - Utilized the Program Operating Plans (POPs) to
evaluate to what extent priorities could be
accomplished within the Current Program and
Revised Program funding detailed in Serial 3. - Above Core requirements identified and
prioritized. - Reallocate resources and funding from Line
Offices and Mission Goals to support major
projects PRC and La Jolla. - Maintain required programs and services to meet
or exceed legal, regulatory and departmental
mandates. - Implement BPR recommendations, and create a
climate of continuous process assessments that
supports end-to-end business process improvements.
8Details Desired End State (FY 09 and FY 13)and
Ability to Meet
Acquisition/Grants FY 09 FY 13
Sustainment of Grants on Line and Grants BPR G G
Fully implemented Acquisitions BPR Y Y
Integrated planning processes for acquisitions and grants AGO and NOAA customers Y Y
Rational work environment for AGO employees R Y
Administrative Services
Implement competitive sourcing feasibility study plan G G
Comply with deemed exports requirements G Y
Comply with HSPD-12 requirements Y Y
Comply with personal property program requirements Y Y
9Details Desired End State (FY 09 and FY 13)and
Ability to Meet
Facilities FY 09 FY 13
Integrated long-range facility modernization planning G G
Sustained funding strategy to support long-term facility modernization requirements R R
Pacific Region Center, La Jolla, BIGELOW homeporting completed G G
Complete Pribilofs cleanup ongoing monitoring G G
Initiate redevelopment of Beaufort, WRC, Montlake, Norfolk, Miami R R
Financial Services FY 09 FY 13
Maintain clean audit opinion, no material findings G G
Implementation of E2E resource mgmt system G Y
CBS enhancements supported R R
10 Details Desired End State (FY 09 and FY 13)and
Ability to Meet
Information Technology FY 09 FY 13
Integrated Enterprise-level IT Security, including CA Y Y
Phased implementation/development of MIS G G
Sound, secure (and redundant) network/infrastructure R R
Long-range IT capital planning process R R
Implemented OneNOAA Web presence R R
Workforce Management
Robust workforce planning (including competency development) capabilities Y Y
Implementation of BPR recommendations (hiring training development) Y Y
Fully implemented HSPD-12 and e-OPF Y Y
11Details
- How Program Capabilities Were Prioritized
- Priorities identified in NOAA 2006-2011 Strategic
Plan, April 2005 - Recognized AGM and Fiscal/Program Guidance
Priorities - Emphasized need to sustain/maintain current
capacities (assumes inflation increases to
sustain capacities will be budgeted separately). - Utilized POPs to evaluate capabilities and
capacities across Mission Support at current and
100 level. - Items eliminated in FY08 DOC Passback
re-evaluated. - Evolving program requirements (Deemed Exports,
HSPD-12, competitive sourcing feasibility
studies) addressed. - Integrated Priority Lists items evaluated for (a)
applicability to Program Support and (b) priority
against current program.
12Details
- How Program Capabilities Were Integrated Across
Programs - Program capabilities analyzed for duplication,
low priority services and/or availability of more
cost effective methods of providing services. - Integration across Program Support programs for
select initiatives HSPD-12, personal
property/Laptops/PII - Facility requirements integrated with other
program directions (fleet modernization, etc.)
and balanced against other competing program
priorities to ensure integration.
13Compliance with Guidance
ISSUE Compliance
Provide recommendation for annual funding level for real property recapitalization. Include analysis and rationale for proposed level. Based on recommended funding level, develop recommendation for projects with start dates, to be funded ?
In coordination with Weather and Water and the National Weather Service, fund Weather Forecast Office (WFO) lease costs. Provide a plan for the WFO Facilities Management Staff. ?
Working with the Satellite sub-goal, provide plan for permanent solution to facility requirements for Fairbanks Command and Data Acquisition Station (CDAS). ?
Fund homeporting requirement for the Bigelow. ?
Provide details on impact of not implementing and cost to eliminate single points of failure for network infrastructure (ITS) ?
Mission Support goal to provide recommendation on the Commerce Business System (CBS) funding shortfall. ?
Various technical adjustments (inter-program realignments) ?
14Compliance with Guidance
ISSUE Compliance
Working with all goals and subgoals who fund personnel who will occupy the PRC and La Jolla, transfer funding consistent with the proportion of the requirement generated by the goal from that goal to Mission support for the revised requirements. (Climate Goal is Above Core Satellite not discussed) ?
Fund IT Security Centralized Certification Accreditation (CA) (Listed in Above Core) ?
Complete implementation of e-OPF as mandated by OPM. (Listed in Above Core) ?
Implement Homeland Security Presidential Directive-12. (Listed in Above Core) ?
Develop competency models to develop/validate competencies in NOAA mission-critical occupations. (Listed in Above Core) ?
15Compliance with Guidance Facility
Recapitalization Level
- Background Previous recommendation for
sustained funding strategy for facility
recapitalization/modernization was supported by
NEP/NEC and reflected in Program Guidance. - Serial 3 Guidance requires recommendation of (1)
annual funding level, with rationale and
analysis and (2) specific projects to be funded
under this level (projects listed in backup). - Recommendation of Methodology
-
- Adjusted Facility Recapitalization Rate (FRR)
methodology Annual funding requirements
calculated as aggregate Current Replacement Value
(CRV) of NOAA owned facility portfolio divided by
facility life. - Research indicates 50 years average facility life
as an accepted target---used by DoD and NASA. - NOAA aggregate CRV (for owned facilities) is
approximately 1.77B based on 2005 portfolio
valuation. - FRR (CRV) / 50 (years average facility life)
35M for 2005. - FRR must be adjusted annually based on
re-valuation of aggregate CRV of NOAA-owned
facility portfolio. - Design and Engineering (DE) requirements also
must be included to yield adjusted FRR.
16Compliance with Guidance Facility
Recapitalization Level
- Total Facility Recapitalization Rate for program
years
Phased implementation recommended FY 09 10.
See next slide
- Recapitalization methodology assumes that there
is adequate funding available to address the
sustainment and restoration requirements.
Inadequate sustainment and restoration reduces
facility life, accelerating need for
recapitalization.
NEP/NEC Guidance Requested Accept Adjusted
Facility Recapitalization Rate (FRR) as
methodology for calculating recapitalization
requirements.
NEP/NEC Recommendation
17Compliance with Guidance Facility
Recapitalization Projects
- Phased Implementation of Recapitalization
Funding FY 09-10 - Projects previously identified in NOAA Facility
Modernization Plan--Long-Range Facility Plan FY
2008-2017
NEP/NEC Guidance Requested Approve phased
funding strategy and recommended projects to be
funded under strategy.
NEP/NEC Recommendation
18Compliance with Guidance Single Points of
Failure
- Elimination of Single Points of Failure
- The elimination of single points of failure will
improve NOAAs Silver Spring Metro Center (SSMC)
network infrastructure, public web services
(PWS), and electronic mail services. - Not implementing will negatively impact NOAAs
ability to accomplish its corporate priorities.
Reduction of key services will impact NOAAs
ability to deliver data products resulting in the
inability for programs to meet their goals. - Lack of or reduced Internet service will impact
NOAAs ability to deliver its data products to
all customers and the general public. This
includes, but is not limited to, Life and
Property data made available to the public via
the Internet. For example, Hurricane Xs
tracking data would not be available to the
public. - The reduction in tier 3 support will impact the
Line Office local area networks (LANs) and
increase the IT security risk to all NOAA
systems, including networks.
19Major Program Adjustments
- Major Program Adjustments (Compliance with
Fiscal/Program Guidance)
20Major Program AdjustmentsFunding for PRC
LaJolla Projects
- Program Guidance
- transfer funding consistent with the proportion
of the requirement generated by the goal from
that goal to Mission support for the revised
requirements - Benefit/Risk PRC Consolidates programs and
replaces inadequate facilities large
requirement impacts Mission Goal capability. - La Jolla Provides safe facility,
sustains programs and strategic program
relationships large requirement impacts Mission
Goal capability. - Transfers from Mission Goals and satellite
sub-goal based on planned occupancy (people) of
facilities by Goal/Program
21Major Program AdjustmentsFunding for PRC
LaJolla Projects (contd)
- Transfers to Program Support for PRC and La Jolla
projects
PROPOSED ADJUSTMENTS
(M) FY 09 FY 10 FY 11 FY 12 FY 13
Pacific Regional Center (PRC) (6.0) 61.3 68.9
La Jolla SW Fisheries Science Ctr (31.0) 50.0
TOTAL (37.0) 111.3 68.9
NEP/NEC Guidance Requested Accept proposed
adjustments to fund PRC and La Jolla projects as
approved by NEP/NEC.
NEP/NEC Recommendation
22Major Program AdjustmentsFairbanks CDAS
- Fairbanks Command and Data Acquisition Station
- Background DoC Passback eliminated funding,
based on no long-term primary use for facility
beyond 2013. Alternative solution approved by
NEP/NEC Temporary, modular buildings with
shorter life span. - Benefit/Risk Alternative most likely to get DoC
support, but is only a temporary solution. - Out-year costs (current estimate 20M-25M)
beyond 2013 to shut down and dispose facility. - Fund development of detailed implementation plan
and refined cost estimates in FY07 through NESDIS
PAC funding. - PROPOSED ADJUSTMENT
(M) FY 09 FY 10 FY 11 FY 12 FY 13
Fairbanks CDAS (10.0) 15.0
NEP/NEC Guidance Requested Accept proposed
adjustment to fund Fairbanks temporary solution.
NEP/NEC Recommendation
23Major Program AdjustmentsBIGELOW Homeporting
- BIGELOW Homeporting
- Background BIGELOW commissioned in FY2006
larger vessellonger, wider, and with a deeper
draftthan ship replaced. Deeper draft requires
dredging of the existing Woods Hole berthing area
and channel. Existing pier and bulkhead need to
be replaced to safely support ship operations. - Benefit/Risk Leverages existing facilities and
collaboration opportunities will require
out-year, periodic dredging (1.5M every 10
yrs.). - PROPOSED ADJUSTMENT
(M) FY 09 FY 10 FY 11 FY 12 FY 13
BIGELOW Homeporting 6.3 8.2
NEP/NEC Guidance Requested Accept proposed
adjustment to fund BIGELOW homeport improvements
(dredging and pier replacement).
NEP/NEC Recommendation
24Above Core
- Rationale for Prioritization of Above Core
Requirements - Responsiveness to fiscal and program guidance
- Impact on accomplishment of program mission
sustainment of capabilities vs. enhancement - Current clarity of requirements
- Methodology for Prioritization
- Segregated ORF vs. PAC
- ORF 4 Tiers (1) Required to Comply with
Fiscal/Program Guidance (2) - (4) based on
mission impact and clarity of requirements - PAC 2 Tiers based on mission impact and
requirements clarity - Impact and Risk of Not Funding Above Core
Requirements Addressed in Individual Quad
Charts in Backup Information - Potential Unfunded Requirements (Not Currently
Fully Defined) - HSPD-12 (IT and Facility impacts)
- IT Recapitalization
25Above Core RequirementsPrioritized ListORF
- TIER ONE Compliance with Fiscal and Programming
Guidance
NEP/NEC Guidance Requested Fund Tier One Above
Core items required for Compliance with
Fiscal/Programming Guidance.
NEP/NEC Recommendation
26Above Core RequirementsPrioritized ListORF
- TIER TWO Sustain Current Program Capabilities
NEP/NEC Guidance Requested Fund Tier Two Above
Core items required to sustain current program
capabilities.
NEP/NEC Recommendation
27Above Core RequirementsPrioritized ListORF
- TIER THREE Improve Current Program Capabilities
28Above Core RequirementsPrioritized ListORF
NOTE Requirements identified in this tier do
not necessarily mean the requirement itself is
lower priority, but may indicate additional
analysis is required, or other alternatives to
support capability exist.
29Above Core RequirementsPrioritized ListPAC
- TIER TWO
NEP/NEC Guidance Requested Fund Tier One (PAC)
Above Core level to support Facility
Recapitalization requirements.
NEP/NEC Recommendation
30Backup Information
31Above Core Quads Tier OneORF
Investments Required to Comply with Fiscal and
Programming Guidance
32Compliance with Guidance -- ABOVE CORE
Electronic Official Personnel Files (e-OPF)
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Workforce Management
- CAPABILITY HR Programs
- REQUIREMENT OPM (e-Gov Initiative)
- DESCRIPTION OF ADJUSTMENT
- Funding for annual licensing fees
- PERFORMANCE MEASURES
- Compliance with OPM milestones
BENEFITS AND RISKS
- If Adjustment made, employees have immediate
access to personal data from any web browser
NOAA has superior retrieval capability for COOP
time for transfer of records reduced from weeks
or months to near real time potential to free up
FTE for higher priority HR activities. - If Adjustment not made, e-OPF has no consistent
funding source which could result in OPFs being
inaccessible to HR staff and other NOAA
employees. Funding would then be needed to print
and reestablish paper OPFs to meet legal
requirements and conduct HR operations. - Risk LOs may not fund 100 back-file
conversions prior to FY 2009 this would require
Programs to make up the difference to meet OPM
timeline of 50 by FY 08, 20 in FY 09-10, and
10 in out years
ACTIVITIES, SCHEDULE MILESTONES
- Annual licensing fee (272K) requires consistent
funding source - FY 06 Infrastructure established for e-OPF from
01/01/06 forward - FY 06 funds contributed by LO/SOs are sufficient
to scan 44 of existing folders during FY 07-08 - US, COs, PPI, OAR, NMAO fully funded
- NMFS is 73 funded (56K needed to fully fund)
- NOS (79K), NWS (317K) (or appropriate Programs)
must provide funding to meet OPM requirements
between FY 07 and FY 11
33Compliance with Guidance -- ABOVE
CORECentralized Certification Accreditation
(CA) Services
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Information Technology Services
- CAPABILITY IT Security
- REQUIREMENT Centralized Certification
Accreditation (CA) Services - DESCRIPTION OF ADJUSTMENT Implement centralized
CA team to ensure consistency in the review of
CA packages, complete certification, and provide
controls testing for each system prior to
submission to Commerce - PERFORMANCE MEASURES IT Security Incidents
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- If program adjustment is made
- Compliance with Federal Information Security
Management Act (FISMA) and Commerce IT Security
Policy - Maintain 100 of NOAA IT systems that have a
current CA - If program adjustment is not made
- Out of compliance with July 12, 2006 OMB memo
M-06-19 from Karen Evans (Ofc of E-Gov IT) that
requires agencies to meet existing security
requirements (e.g., correct security weaknesses
in stead-state investments) before new funds are
spent on system development, modernization, or
enhancement - Restrict public access to hazardous weather
warnings and hurricane tracking information
during peak demand periods when capability of
enterprise security systems is exceeded - Retain IT Security material weakness (DOC OIG)
- Delay implementation of IT Security Architecture
by 2 to 3 years
- Standardize CA process throughout NOAA
Oct 2007 - Capability of providing a suite of CA services
Oct 2007 - Automate CA process Oct 2008
- Provide CA dashboard capability
Mar 2009
34Compliance with Guidance -- ABOVE CORE Develop
Competency Models
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Workforce Management
- CAPABILITY Strategic Management of Human Capital
- REQUIREMENT 5 U.S.C. 1103(c) Human Capital
Initiative of PMA E.O. 13352 (Cooperative
Conservation) - DESCRIPTION OF ADJUSTMENT
- Fund development of competency models for 25 of
NOAAs highest priority and/or most populous job
series and work roles to support workforce
planning - PERFORMANCE MEASURES
- Number of valid competency models developed
ACTIVITIES, SCHEDULE MILESTONES
- FY 07- 08 WFMO works with contractor and LO/COs
to develop/validate NOAA foundational competency
model, DOC-assigned competency models, and other
high-priority models using existing interagency
agreement with OPM complete skills gap
assessments for priority models - FY 09 WFMO works with contractor and LO/COs to
validate competency model for Cooperative
Conservation Competencies and develop/validate an
additional 5 competency models complete skills
gap assessments for priority models - FY 10-13 WFMO works with contractor and LO/COs
to develop/validate an additional 5 competency
models each year complete skills gap assessments
for priority models - Ease of using models for skills gap assessments
and workforce planning dependent on nature of
automated competency management system available
BENEFITS AND RISKS
- If Adjustment made, NOAA will be able to add 26
validated competency models to those developed in
FY 07 FY 08 increasing our ability to determine
skills gaps and develop workforce plans to fill
those gaps - Filling skills gaps helps meet the AGM guidance
for A more flexible, diverse and mobile
workforce with minimal skill gaps - Validated competency models can serve as a basis
for valid QuickHire and interview questions,
training needs assessments, succession planning,
and other HR processes. - If Adjustment not made, NOAA not having valid
data to use for workforce planning (closing
skills gaps), recruitment, training, other HR
processes - Barriers to implementation include the time
resources required of NOAA managers employees
to develop and validate models
35Compliance with Guidance -- ABOVE CORE HSPD-12
(Workforce Management)
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Workforce Management
- CAPABILITY Human Resources Programs
- REQUIREMENT Homeland Security Presidential
Directive (HSPD)-12 - DESCRIPTION OF ADJUSTMENT
- 5 FTE and funding to support the human resource
requirements created by HSPD-12 - PERFORMANCE MEASURES
- Timely security clearances
- Error rates
- Hiring cycle time
ACTIVITIES, SCHEDULE MILESTONES
- FY09, Q2 Fill 5 ZS-IV personnel security
positions - Positions will
- Initiate and monitor process for all levels of
security clearance requests for new employees - Review and adjudicate pre-employment suitability
investigation results with LO hiring officials
(new with HSPD-12 post-employment suitability
has been an on-going responsibility) - Serve as PIV sponsor for all new hire actions
- Ensure that the appropriate on-line training is
completed - Complete appropriate activities related to
badging and re-badging - Other NOAA players include the IT Services,
Administrative Services, and Facilities Programs
BENEFITS AND RISKS
- If adjustment made, MS-WMP able to process 100
of new security requirements timely while
carrying out on-going workload - If adjustment not made, security-related work
likely to be delayed while current staff works to
keep up with volume and still carry out other HR
activities quality and accuracy of all work
suffers other HR activities (e.g., hiring)
already being delayed to focus on security - New employees may not be able to enter on duty in
a timely fashion until all required security
clearances are completed. High potential to lose
candidates to other positions or agencies if
process too slow - In mid-1990s, MS-WMP gave up 6 FTE to DOC for
security-related work. Work has returned with
HSPD-12, but not the FTEs - No direct dependencies on other programs
36Compliance with Guidance -- ABOVE CORE HSPD-12
(Administrative Services)
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Administrative Services
- CAPABILITY Logistics
- REQUIREMENT HSPD-12 Credentialing
- DESCRIPTION OF ADJUSTMENT Implementation of a
new standardized credentialing process to comply
with OMB-05-24 - PERFORMANCE MEASURES
- Number/percentage of employees and equipment
processed annually to remain compliant
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- The program is designed to enhance security,
reduce identity fraud, and protect personal
privacy - Personnel security at risk, identity fraud not
deterred - Risks/barriers to implementation interfaces to
legacy systems
- DOC has selected the GSA Managed Service Office
to implement the Program NOAA retains specific
abjudication responsibilities - Smartcards, background checks, card readers,
servers, installation and maintenance, training - Card implementation begins in October 2006 full
implementation by October 2008 - FY09-FY13 primarily for ongoing maintenance,
annual employee rebadging, logical access for
computers, and equipment replacement and upgrades
37Above Core QuadsTier OnePAC
- Investments
- Required to Fund Facility Recapitalization
Requirements - (using Facility Recapitalization Rate)
38ABOVE CORE (PAC T-1) Facility Recapitalization
Requirements
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Facilities
- CAPABILITY Construction
- REQUIREMENT Facility Recapitalization
- DESCRIPTION OF ADJUSTMENT Implementation of a
sustained funding strategy to address NOAA
facility recapitalization requirements - PERFORMANCE MEASURES
- Improved portfolio facility condition index
- Elimination of substantial backlog of repair
projects (50-60M)
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- Enables NOAA to replace owned facilities that
have reached the end of their useful life. - Provides modern, state-of-the-art, and safe
working conditions - Risks
- Funding level is substantial and will face severe
budget challenge. - Unclear where possible offsets would come, and at
what expense.
- Phased implementation of funding level in FY
09-10. - Initial years funding supports (1) delineation
of program of requirements and analysis of
alternatives, and (2) design. - Specific schedules and milestones for each
project still need to be developed. High level
implementation schedule reflected on next slide.
39ABOVE CORE (PAC T-1) Facility Recapitalization
Requirements
- Projects Recommended Under Recapitalization
Funding Projects previously identified in NOAA
Facility Modernization Plan--Long-Range Facility
Plan FY 2008-2017
Background
40Above Core Quads Tier TwoORF
Investments Required to Sustain Current
Services/Capabilities
41Sustain Current Capabilities--Above Core Guard
Service Contract
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Administrative Services
- CAPABILITY Logistics
- REQUIREMENT NOAA-wide Guard Services Contracts
- DESCRIPTION OF ADJUSTMENT
- Funding to pay for three Guard Service contracts
covering NCR, Boulder and Seattle - PERFORMANCE MEASURES
- Proper physical security for NOAA facilities and
staff - Timely payment of contracts
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- Actual funding was previously provided through
the Working Capital Fund, and was first requested
in FY07. FY06 funding came via a reprogramming
and a DOC subsidy. FY07 funding will be short
by over 2.0M. - Services to NOAA Programs will be reduced or
Direct Billed, causing unacceptable loss of
capability - Required payments produce a shortfall for other
critical Program Support requirements
- Contracts require funding in first quarter each
year - Guard Service is Must Pay for NOAA
42Sustain Current Capabilities--Above Core
Working Capital Fund (Financial)
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Financial Services
- CAPABILITY NOAA Centralized Payments
- REQUIREMENT Centralized Payments/WCF
- DESCRIPTION OF ADJUSTMENT
- Funding mechanism to process NOAA centralized
payments - PERFORMANCE MEASURES
- Accurate on-time end of year close out
- Timely allocation of appropriation
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- Actual funding for assessments have not kept pace
with the bill - Services to NOAA Programs will be reduced or
Direct Billed, causing loss of capability - Required payments produces a shortfall for other
Common Services requirements as well
- DOC requires funding in first quarter each year
- WCF is Must Pay for NOAA
43Sustain Current Capabilities--Above Core
Learning Management System
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Workforce Management
- CAPABILITY Strategic Management of Human
Capital - REQUIREMENT 5 CFR BPR implementation
- DESCRIPTION OF ADJUSTMENT
- Fund the NOAA portion of the DOC Learning
Management System including a competency
management functionality - PERFORMANCE MEASURES
- Compliance with OPM reporting requirements
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- If Adjustment made, NOAA will be able to fully
support the new Training and Development business
process to meet new OPM training data reporting
requirements, provide cost-effective training to
employees, and support the competency assessment
and skills gap analysis required for workforce
planning. - If Adjustment not made, NOAA will not be assured
of a having a business process and system to meet
OPM data reporting requirements or to efficiently
support workforce planning via competency
management functionality funding would be
dependent on direct bill. - No dependencies on other programs
- FY 2007 Q1-Q2 DOC competition for LMS develop
requirements for competency management module - FY 2007 Q3-Q4 Implement new LMS
- FY 2008 Implement competency management module
- FY 09-13 Maintain LMS licenses
44Program Support Above Core Commerce Business
SystemOracle Licenses
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Financial Services
- CAPABILITY Accounting Services and Funds
Management - REQUIREMENT Commerce Business System
- DESCRIPTION OF ADJUSTMENT
- Oracle license renewal
- PERFORMANCE MEASURES
- Improved funds control
- Accurate and timely financial information
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- Supports new DOC Web Enabled CBS Application to
NOAA - Enables term purchases of Oracle Internet
Application Server Licenses - System at risk with obsolete software
- Above Core request serves as place holder until
accurate costing is received from OCIO
- FY 2009 - 2013
- Two year term purchase of Oracle internet
application server licenses to support NOAA users
of CBS and Grants On Line
45Sustain Current Capabilities--Above Core End to
End Resource Management System
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Financial Services
- CAPABILITY PPBES Management Information System
- REQUIREMENT End to End Resource Management
System - DESCRIPTION OF ADJUSTMENT
- Maintenance and sustainment costs
- PERFORMANCE MEASURES
- Accurate and timely financial information for
program managers
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- Provides improved budget development and
production including budget justification and
all necessary exhibits - Enables interface with Commerce Business System
and consolidates Reporting System - Eliminates separate system inefficiency and
costly labor-intensive processes - Leverages integrated investment by connecting to
mission support system support architecture for
NOAAs planning, programming, budgeting and
execution processes - Fewer unlinked systems support all phases of
PPBES
- FY 2009-FY 2013
- System Maintenance
- Implementation of operational system
- Improves the availability and quality of data
available for PPBES
46Sustain Current Capabilities--Above Core
Elimination of Single Points of Failure (SSMC
Network Infrastructure Public Web Services)
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Information Technology Services
- CAPABILITY Enterprise Network Operations
- REQUIREMENT Elimination of Single Points of
Failure in Silver Spring Metro Center (SSMC)
Network Infrastructure and Public Web Services
(PWS) - DESCRIPTION OF ADJUSTMENT Implement
fully-redundant SSMC network backbone with
built-in failover, and mirrored web clusters at 7
U.S. locations - PERFORMANCE MEASURES Network and Application
Services Availability
BENEFITS AND RISKS
- If program adjustment is not made
- NOAA data products (provided via SSMC and/or
other locations) will become unavailable during a
power failure or when construction/utility
equipment (e.g., backhoe) severs the SSMC
internet connection. For example, Hurricane Xs
tracking data would not be available to the
public during the time of need. - Customers and the general public will become
displeased with the data unavailability, which in
turn becomes front-page, above-the-fold news in
the Washington Post for weeks. Can NOAA afford
the bad press and management of the resulting
triage? - Lack of or reduced Internet service will impact
NOAAs ability to deliver its data products to
all customers and the general public. This
includes, but is not limited to, Life and
Property data made available to the public via
the Internet. Reduction of key services will
impact NOAAs ability to deliver data products
resulting in the inability for programs to meet
their GPRA or corporate performance targets. - IT security risks will increase on all NOAA
systems, including networks. - Dependency Public Web Services within the
Weather Water Goal (via the Web Consolidation
Initiative in NWS)
ACTIVITIES, SCHEDULE MILESTONES
- Complete implementation of a 10 Gigabit Ethernet
SSMC backbone 10 Gigabit Ethernet Wash DC
metropolitan area network (MAN) 2011 - Complete hardening of the SSMC backbone in order
to produce a 99.99 uptime network 2013
47Supplemental Information
Information Relevant to Fiscal/Programming
Guidance
48Compliance with Guidance -- ABOVE CORE HSPD-12
Proposed Five-Year Budget
HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget HSPD-12 Proposed Five-Year Budget
ITEM Unit Cost FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 Comments
Smartcard w/ PKI Credential - 17,600 (card replacement) Direct Bill? 110 0 0 1,936,000 0 0 Assumes initial issuance of all cards in FY2008 full replacement in FY2011 on 3-year refresh cycle
Smartcard w/ PKI Credential - 17,600 (card maintenance fee) Direct Bill? 51 897,600 897,600 897,600 897,600 897,600 NOAA Employee count (Feds, Commissioned Contractors) changed to 17,600 based on 10/17/06 MOC figures
Reissued cards Direct Bill? (10 of 17,600 per year 1,760) 110 193,600 193,600 0 193,600 193,600 10 employee turnover / lost cards
System Certification and Accreditation (ea) Required once every 3 years 250,000 250,000 0 0 250,000 0 CA on 3 year cycle. FY09 Initial CA 300,000. FY2010-2011 no CA costs. FY2012 Re-CA 200,000 (i.e., 67 of initial CA). FY2013 no CA costs.
49Compliance with Guidance -- ABOVE CORE HSPD-12
Proposed Five-Year Budget
HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued) HSPD-12 Proposed Five-Year Budget (Continued)
ITEM Unit Cost FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 Comments
Additional FTEs Administrative Services 144,000 432,000 432,000 432,000 432,000 432,000 3 additional FTEs needed for HSPD-12 support - NCR, Seattle and KC.
Additional FTEs - WFM 75,000 375,000 375,000 375,000 375,000 375,000 5 additional WFM FTEs will be required
TOTAL ESTIMATED COSTS Â 2,148,200 1,898,200 3,640,600 2,148,200 1,898,200 Â
Cost per NOAA/ Contractor Employee  122 108 207 122 108
50Compliance with GuidanceFacility
Recapitalization Level
Also measure and use facility utilization, OM
costs, and mission dependency.
51Compliance with GuidanceFacility
Recapitalization Level
- Other budget development methods researched.
Most are more applicable for estimating
sustainment and restoration requirements rather
than recapitalization. - National Research Council (NRC) Recommended
Percentage (2-4 of CRV) - Facility Condition Index (FCI) (can lead to a
recapitalization estimate) - Deferred Maintenance/Repair Backlog
- Validated Repair Needs
- Facility Sustainment Model (FSM)
- Life Cycle Component Management (can lead to a
recapitalization estimate) - Other methods primarily used for project
prioritization
52Compliance with GuidanceElimination of Single
Points of Failure
- Action Item Eliminate Single Points of Failure
Provide details on the impact of not
implementing and cost to eliminate single points
of failure - Scope The elimination of single points of
failure will improve NOAAs Silver Spring Metro
Center (SSMC) network infrastructure, public web
services (PWS), and electronic mail services. - Impact of Not Implementing
- It will negatively impact NOAAs ability to
accomplish its corporate priorities. Reduction of
key services will impact NOAAs ability to
deliver data products resulting in the inability
for programs to meet their goals. - The IT Services Program will be forced to
- Reduce the plans for email system redundancy and
provide replication of email only for priority
users - Reduce the hardening of the SSMC backbone
- Abandon the optimal solution of providing a
common infrastructure, redundancy, and diversity
- Extend the project timelines and scale back the
functional requirements for current projects - Extend system lifecycle refresh periods, thereby,
limiting our ability to implement the 10 Gigabit
Ethernet SSMC backbone and MAN networks or new
requirements - Reduce the implementation of PWS hardware and
staff supporting the NOAA Continuity of
Operations (COOP) Plan requirements - Abandon the implementation of mirrored clusters
(i.e., consolidated set of servers and storage
devices) at 7 locations throughout the U.S. - Lack of or reduced Internet service will impact
NOAAs ability to deliver its data products to
all customers and the general public. This
includes, but is not limited to, Life and
Property data made available to the public via
the Internet. For example, Hurricane Xs
tracking data would not be available to the
public. - The reduction in tier 3 support will impact the
Line Office local area networks (LANs) and
increase the IT security risk to all NOAA
systems, including networks. - Cost
Activity Project Managers or Subject Matter Experts Year 1 Year 2 Year 3 Year 4 Year 5 Each Outyear
Elimination of Single Points of Failure in NOAAs Silver Spring Metro Center (SSMC) Network Infrastructure John Kyler, Bob Brunner 0.8M 0.8M 1.0M 1.0M 1.0M 1.0M
Elimination of Single Points of Failure in Public Web Services John Unekis, John Kyler, Chi Kang 1.2M 1.4M 0.9M 0.9M 0.9M 0.9M
Elimination of Single Points of Failure in Electronic Mail Services (including migration to Commerce-wide common email system) John Unekis, Don Holtzer 13.0M 4.8M 4.8M 4.8M 4.8M 4.8M
53Compliance with GuidanceTransfer of LO CIO
Operating Funds
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Information Technology Services
- CAPABILITIES IT Security, Enterprise Network
Operations, Enterprise Architecture, IT Support
for Administrative Systems, IT Administration and
Regulation - REQUIREMENT Transfer of Line Office (LO) CIO
Operating Budgets from LO Headquarters Program to
IT Services Program - DESCRIPTION OF ADJUSTMENT Transfer of funding
will allow the IT Services Program to improve
performance through the IT Administration and
Regulation, IT Security, Enterprise Network
Operations, Enterprise Architecture, and IT
Support for Administrative Systems capabilities. - PERFORMANCE MEASURES IT Security Incidents
Network and Application Services Availability,
Capability Maturity Model Score
ACTIVITIES, SCHEDULE MILESTONES
BENEFITS AND RISKS
- Provide CA dashboard capability 2009
- NEMIS data storage acquisition, product
inventories, analysis, Suite 2 dashboard
instruments 2009 - Complete phase 2 of the consolidated electronic
mail system, including complete redundancy and
replication of data for all users 2010 - Complete hardening of the SSMC backbone and
NOAAnet in order to produce a 99.99 uptime
network 2013
- If program adjustment is made Provide
centralized administration and management of IT
Services across NOAA
54Compliance with GuidanceTransfer of Funding
from OCIO to PS/ITS
Information Technology Services Program (MS-ITS) CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds CURRENT PROGRAM - FUNDING (K)including Transfer of LO CIO Operating Funds Amount from LO CIO
Capability FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 Amount from LO CIO
MS-ITS-ADI IT Administration and Regulation 1650 1650 1650 4052 4052 4052 4052 4052 2402
MS-ITS-SEI IT Security 1000 3050 3050 7637 7637 7637 7637 7637 2587
MS-ITS-NET Enterprise Network Operations 5123 5123 5123 9760 9760 9760 9760 9760 4637
MS-ITS-ARC Enterprise Architecture 216 216 216 2263 2263 2263 2263 2263 1047
MS-ITS-SPT IT Support for Administrative Systems 15961 16132 16132 20515 20515 19661 19661 19661 4201
TOTAL FUNDING 23950 26171 26171 44227 44227 43373 43373 43373 14874
55Compliance with GuidanceRecommendation on CBS
Funding Shortfall
CBS Requirements ( in millions) FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 Comments
Server Consolidation 2.4 2.4 2.5 2.5 0.0 - Supports NOAA contribution to Census - Cost of software license maintenance - Telecommunication cost to Census
New Accounting System .9 .9 5.9 27.0 34.0 - Supports study for new system - Conversion of Data Training - Implementation of new system
Enhancements to System 3.5 2.0 2.0 1.3 1.3 -HS-PD12 (modifying CBS, Data warehouse, Travel Manager, etc to accept authorization from this card) - NOAA Integration and Data Storage - Full implementation of Commitment Accounting - Migration to DOC web portal
Total CBS Shortfall 6.8 5.3 10.4 30.8 35.3
56Compliance with GuidanceRecommendation on CBS
Funding Shortfall
- Recommendations for Funding CBS Shortfall
CBS Requirement Alternatives for Funding Shortfall
Server Consolidation Reduce services to NOAA customers Reduce funding to the Information Technology Center (ITC)
New Accounting System CBS Base Funding Increase -Transitional cost associated with moving to new DOC consolidated accounting system exceed the current CBS base funding Eliminate current services to NOAA customers - Stop funding for all maintenance and administrative efforts, help desk support, system testing and training efforts on the current system
Enhancements to System Eliminate support for HS-PD12 within CBS suite of applications - Suspend modification to accommodate security verification Reduce services to NOAA customer - Decrease access to timely financial data
57Compliance with GuidanceUpdate Capabilities
ProfileFinancial Services
Current Capabilities Profile
ITEM FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 TOTALS
MS-FIN Accounting Services and Funds Management 23,347 23,347 23,347 23,347 23,347 23,347
MS-FIN Develop and Defend Budget 1,638 1,638 1,638 1,638 1,638 1,638
MS-FIN NMA Resource Management 9,831 9,831 9,796 9,796 9,796 9,796
MS-FIN PPBES Management Information System 4,380 4,380 4,380 4,380 4,380 4,380
MS-FIN NOAA Centralized Payments 34,425 34,425 34,425 34,425 34,425 34,425
Total Current Program 73,621 73,621 73,586 73,586 73,586 73,586
Updated Current Capabilities Profile
ITEM FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 TOTALS
MS-FIN Accounting Services and Funds Management 26,411 26,411 26,411 26,411 26,411 26,411
MS-FIN Develop and Defend Budget 1,743 1,743 1,743 1,743 1,743 1,743
MS-FIN NMA Resource Management 9,040 9,040 9,040 9,005 9,005 9,005
MS-FIN PPBES Management Information System 2,002 2,002 2,002 2,002 2,002 2,002
MS-FIN NOAA Centralized Payments 34,425 34,425 34,425 34,425 34,425 34,425
Total Current Program 73,621 73,621 73,586 73,586 73,586 73,586
58Above Core QuadsTier 3 4 (ORF) Tier 2 (PAC)
59Program Support Above Core (T-3) Business
Process Reengineering
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Administrative Services
- CAPABILITY Office of the NOAA Chief
Administrative Officer - REQUIREMENT Business Process Reengineering (BPR)
- DESCRIPTION OF ADJUSTMENT Designate continuing
direct funding for the Business Process
Reengineering effort. BPR depends on personnel
detailed from the Line and Staff Offices, and
direct billing of the LO/SO programs for staffing
and funding. This adjustment would provide direct
funding for contract support. - PERFORMANCE MEASURES
- As Is evaluations completed
- To Be evaluations completed
- Recommendations implemented
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- Would provide the ability to
- Complete the reengineering effort on any
remaining financial and administrative service
areas - Conduct continuous improvement for financial and
administrative processes already reengineered. - BPR activities risk delay during Government
Continuing Resolution due to reliance on
contractor funding in 1st quarter
- FY09 Financial Services Phase 3
Information Technology Phase 4 - FY10 Financial Services Phase 4
- FY11-FY13 No projects scheduled
- The assumption is that the Safety and Facilities
Programs have already completed internal BPR
activities.
60Program Support Above Core (T-3) Commerce
Business System (CBS)Server Consolidation
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Financial Services
- CAPABILITY Accounting Services and Funds
Management - REQUIREMENT Commerce Business System
- DESCRIPTION OF ADJUSTMENT
- Server Consolidation Project
- PERFORMANCE MEASURES
- Improved funds control
- Accurate and timely financial information
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- FY 2008
- Commerce Business System moves from IT Services
to Census Data Center - FY 2009
- Consolidation of CBS technology architecture
- Supports NOAA contribution to Census facility
- Ensure software license maintenance for software
installed at Census
- Ensures software license maintenance for software
installed at Census location - Consolidates CBS technology architecture
- Without enhancements to the current CBS system,
NOAA managers will not have access to timely
financial data necessary to make informed
programmatic decisions - Supports the NOAA contribution to Census facility
and includes telecommunications cost for
developers and administrators
61Program Support Above Core (T-3) Commerce
Business System Funds Control Enhancements
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Financial Services
- CAPABILITY Accounting Services and Funds
Management - REQUIREMENT Commerce Business System
- DESCRIPTION OF ADJUSTMENT
- Enhancement to Commerce Business System
- PERFORMANCE MEASURES
- Improved funds control
- Accurate and timely financial information
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- To improve management of funding, NOAA needs to
implement commitment accounting - Implementation of E-Travel will enable NOAA to
meet the PMA requirement, which will simplify
Federal travel management - Without enhancements to the current CBS system,
NOAA managers will not have access to timely
financial data necessary to make informed
programmatic decisions
- FY 2009 FY 2013
- Implementation of commitment accounting
- Staffing will be increased to meet accelerating
reporting requirements - Migration to DOC Business web portal
- Implementation of Reimbursable module to monitor
and control Reimbursable funding - Development of an automated accounting module
62Program Support Above Core (T-3) Technology
Refresh Desktop Management
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Information Technology Services
- CAPABILITIES IT Security, Enterprise Network
Operations, Enterprise Architecture, IT Support
for Administrative Systems, IT Administration and
Regulation - REQUIREMENT Technology Refresh Desktop
Management - DESCRIPTION OF ADJUSTMENT Technology Refresh
Desktop Management for NOAA Computer Incident
Response Team, Information Technology Center,
Network Operations Center, Web Operations Center,
Messaging Operations Center, OS LAN / Systems
Support, and OCIO - PERFORMANCE MEASURES IT Security Incidents,
Network and Application Services Availability,
Capability Maturity Model Score
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- If program adjustment is made Meet recommended
system lifecycle refresh requirements - If program adjustment is not made
- Extend system lifecycle refresh period from 3
years to 5 years - Extend timelines and scale back functional
requirements for current projects
- Technology Refresh Oct 2008 Sep 2013
- Desktop Management Oct 2008 Sep 2013
63Program Support Above Core (T-3) Human
Resources Information System
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Workforce Management
- CAPABILITY HR Programs
- REQUIREMENT BPR recommendation e-Gov
Initiative - DESCRIPTION OF ADJUSTMENT
- HRIS is an enhancement to the current NFC payroll
system that supports automated processing of HR
actions (e.g., SF-52-s) - PERFORMANCE MEASURES
- of actions resulting in processing errors
- Hiring cycle time
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- If Adjustment made, HR actions can be initiated
in LO/COs, automatically routed for approval and
action, and automatically fed into the NFC
system. This will reduce hiring cycle time, lost
paperwork, processing errors due to rekeying and
use of drop-down menus. - If Adjustment not made, BPR recommendations will
not be maximized and current situation will
continue. - No dependencies on other programs
- FY 07-08 Work with DOC and NFC on systems
requirements and develop implementation plan - FY 09 Implement HRIS
- FY 10-13 Maintain system license
64Program Support Above Core (T-3) Mandated
Administrative Services
PROGRAM ADJUSTMENT FUNDING
- GOAL Program Support
- PROGRAM Administrative Services
- CAPABILITY CAO, AICIM, LOG
- REQUIREMENT Mandated Administrative Services
- DESCRIPTION OF ADJUSTMENT A number of unfunded
mandates have been imposed on MS-ADS that have
strained existing resources to the point where
other critical services are being degraded.
Dedicated funding and FTE for these activities
are required - PERFORMANCE MEASURES
- Deemed Export requirements are met.
- Personal Property program and audit requirements
are met. - FOIA requirements are met.
- Audit Liaison requirements are met.
BENEFITS AND RISKS
ACTIVITIES, SCHEDULE MILESTONES
- Failure to provide additional FTE and funding
will result in continued degradation of existing
services, many of which are critical. - Dedicated FTE and resources will ensure NOAAs
ability to meet legal and regulatory mandates,
both timely and effectively, and achieve clean
audits.