Title: Project Management in Marketing Session 6
1Project Management in MarketingSession 6
- Project Tools, Techniques and Termination
2Agenda
- General Process of project Planning
- Determining the Work breakdown structure
- Estimating task duration
- Tools and Techniques
- Project Termination
3Reasons for failure
- Typical mistakes
- Taking a task view
- Optimism
- Tracking
- Not confronting early
- Shackled by a plan
- Lack of..
- appropriate expertise and approach from Project
Leader need to provide development - support from project sponsor need to
communicate resources needed and reasons - ability/necessary expertise of team members
need to select carefully - buy-in from end-users need to involve them in
the project - project initiation
4Project budget
- Amount of resource required
- Where required (i.e. doing what)
- When required (calendarised, dd/mm/yy)
- Who needs to sign-off (authority levels)
- How will it be delivered
5Determining Requirements A Resources Checklist
- The people to be involved in the project , the
level of their commitment and the required level
of skills . - The facilities for the project planning , and
depending on the project its implementation . - The equipment required such as computers ,
cameras , or other audio visual equipment . - The money a budget needed to complete the task
. There will often be an iterative process to
determine budgets , taking account of the costs ,
timescales etc . - The materials what tangibles , consumable or
other items will be required in the process.
6Sequencing Work
- Scheduling refers to linking the various
activities of a project - It examines the sequencing of tasks , both
independent and interrelated. - By Organising into Suschedules and charts,
detailing what will happen , when , by whom ,
interfaces and the milestones for the tasks . - Once the work is listed out the following should
be identified. - Predecessor tasks those required for another
task to be completed - Successor Tasks those that cannot start until
another task has been completed . - The schedule is a key tool in managing progress.
7Tools
- Project budget
- GANTT chart
- Network analysis
- Project Evaluation Review Technique
- Resource planning
8GANTT Chart assessment basic
http//youtu.be/rm_iWKoOd0U 4m
- Listing of all the activities to be carried out
with the overlay of - Duration of each element
- Estimated and actual task
- Static and variable
- Critical Path
- Linked items (sequential or parallel)
9Gantt Charts
Sample Gantt Chart for a production project .
Source http//www.rickwells.co.uk/images/gantt.gi
f
10Network Analysis tools
- Network Analysis tools Show the dependencies in
work activities. - Common Analysis tools
- CPM Critical Path Methodology
- PERT Programme Evaluation and review
techniques. - These tools concentrate on managing the total
time for the project. Gantt charts concentrate on
controlling time for each aspect of the project - The term critical path is used in place of the
sequence of activities that takes the longest
total time required to complete the project. - PERT used to determine how much time a project
needs before it is completed, on the basis of
activities being completed within a best worst
and most likely estimate.
11Critical Path Analysis or Network Analysis
- Changes each and every time a significant
alteration is made to the plan - Estimating task time for completion
- Sequential or tandem or parallel tasks
- Longest time allowable/shortest time
- Drawing these into a network diagram
12Critical Path on Gantt Chart
13Project Management Software
- Microsoft Project
- Micro Planner X-Pert
- Access (depending upon the project)
- Excel
- Word document tables (using formula)
14Contingency plans - essential
- Be realistic about
- the time that elements of the project will take
- how much can be done
- other pressures on your time
- What happens if the plan has to change?
- More chance of keeping to time plan the earlier
these changes are made - Discuss problems
15Project reports anddocumentation extra marks
- Project charter document - overview
- Project management plan
- Progress report
- Post-completion audit
16Core Project management Methodologies.
- There are two common process methodologies.
- Scalable Methodology
- Agile methodology
- Process
- PRINCE stands for Projects in Controlled
Environments. - It was developed by the Central Computer and
Telecommunications Agency (CCTA) as a standard
for IT project management by the UK Government. - While it was developed for IT projects, PRINCE is
also used for non-IT projects, in both the public
and private sectors. PRINCE2 is the latest
version of this methodology.
17Scalable Methodology
Source Official CIM course book PMIM, 2009
18Agile Methodologies
- Agile methodologies are ,
- Adaptive rather than predictive agile
approaches welcome changes , rather than have
fixed plans . - Focused on people rather than process Process
methods focus the processes set , and anyone
could implement the plans . Agile approaches
recognize that people have skills that can add to
the project as it progresses. -
- Adaptive Project Framework
- ADF is a customer focused methodology , which is
based on being - Client focused and client driven
- Frequent and early results reporting
- Focused on questioning and introspection
- Change is good when it is moving to a better
solution .
19Project Monitoring - assessment
- Project monitoring is the collecting, recording
and reporting information concerning any and all
aspects of project performance that the project
manager or others in the organisation need to
know Meredith and Mantell (2000)
- The project monitoring system comprises of
identifying - the key information requirements
- the key factors to be monitored
- the boundaries
20Project Control
- Project control is the act of reducing the
difference between plan and reality through
Meredith and Mantell (2000)
- Project team meetings
- Issues lists
- Regular reviews
- Team member accountability
- Milestones
- Scheduling
- Stakeholder meetings
21Project Management - Summary
- Initiation
- Limits constraints and priorities defined
- Planning
- Team members selected
- Scope of project defined
- Potential risks identified and planned for
- Resources required determined
- Control
- Deliverables created
- Progress monitored communicated
- Issues resolved and changes managed
- Close out
- Customer satisfaction measured
- Lessons learned analysed
22(No Transcript)
23Project Monitoring
- Progress report
- Project status update
- Extending knowledge
- Independent reviews or project audits
- Project meetings
- Monitoring measures
- Progress checks
- Variance analysis
- Earned value analysis and monitoring
24Agenda
- General Process of project Planning
- Determining the Work breakdown structure
- Buying Physical or electronic Products
- Estimating task duration
- Tools and Techniques
- Project Termination
25Agenda
- General Process of project Planning
- Determining the Work breakdown structure
- Buying Physical or electronic Products
- Estimating task duration
- Tools and Techniques
- Project Termination .
26Buying Physical or electronic Products
Source Official CIM course book PMIM, 2009
27Agenda
- General Process of project Planning
- Determining the Work breakdown structure
- Buying Physical or electronic Products
- Estimating task duration
- Tools and Techniques
- Project Termination
- The Project report
28Agenda
- General Process of project Planning
- Determining the Work breakdown structure
- Buying Physical or electronic Products
- Estimating task duration
- Tools and Techniques
- Project Termination .
- The Project report.
29Learning Outcomes
- 6.1 Critically assess the importance of and
techniques for establishing the marketing
projects scope, definition and goals relative to
the organisational marketing plan - 6.2 Utilise a range of tools and techniques to
support project planning, scheduling, resourcing
and controlling of activities within the project
to enable effective and efficient implementation - 6.3 Utilise a variety of methods, measurements
and control techniques to enable effective
monitoring and measuring of progress throughout
the project to ensure that it is completed to
specification, on time and within budget - 6.4 Critically Assess the main techniques for
evaluating effectiveness, success or failure of a
marketing project on its completion
30Agenda
- General Process of project Planning
- Determining the Work breakdown structure
- Buying Physical or electronic Products
- Estimating task duration
- Determining Requirements A Resources Checklist
- Tools and Techniques
- Project Termination
- The Project report
31Agenda
- General Process of project Planning
- Determining the Work breakdown structure
- Buying Physical or electronic Products
- Estimating task duration
- Determining Requirements A Resources Checklist
- Tools and Techniques
- Project Termination
- The Project report
32Agenda
- Core Project management methodologies
- Project monitoring and Control
- Project monitoring
- Project Monitoring System
33General Process of Project Planning
- Determining the work breakdown structure
- Estimating timing and task duration
- Determining resource requirements
- Allocating responsibilities
- Sequencing work
- Developing the project schedule or network
- Preparing the integrated planning document .
34Determining the Work breakdown structure - WBS
WBS Implementing a customer relationship
Management System Source Adapted from Maylor.
35Representing the Schedule
..............
Task Network
..............
..............
..............
..............
Milestones
Resource Histogram
Gantt Chart
36Example Gantt Chart
37Estimates
- Not written in stone
- Not even necessarily accurate
- Accompanying confidence level
- Need to be monitored throughout
- Need to be changed each time the specification is
changed or discoveries made
38Agenda
- Core Project management methodologies
- Project monitoring and Control
- Project monitoring
- Project Monitoring System
39Project Termination
- Ideally a project is terminated once it is
completed . - Alternatively it could when the project has
problems or it fail to achieve its outcomes. - Activities at termination rarely affect the
project activities . - Although it will affect
- the success of the future projects.
- The attitudes of the project team .
- This is the final stage in project management .
- This will be followed by the project review
process which will use evaluation tools to
address the dimensions of success and failure. - The two models of project decision making
- Models based on the extent to which the project
has achieved or failed to achieve its desired
outcomes. - Models that compare the rpoject against generally
accepted standards for success and failure for a
project.
40Project Termination Concerns
- Terminating a project needs delicate handling and
finesse. Successfully closing out a terminated
project should be viewed as a greater achievement
than closing out a successful one. - The team should be made aware of the rationale
behind the termination well before the official
announcement. - The team (and project manager) should be reminded
that project termination does not always indicate
project mismanagement. - Team members should be allowed and encouraged to
document accomplishments and status of the
terminated project.
41Project Termination Concerns
- The project manager should identify how the work
completed will contribute to future projects and
hold a celebration of the teams achievements. - The project manager should work with functional
managers to reassign personnel to new projects
and present team members plans for future
assignments. These reassignments should be into
comparable or higher positions, to eliminate the
notion that the canceled project reflects on
their capabilities. - The close-out must ensure that all contractual
requirements are satisfied and all records
properly stored. Finally, project resources must
be released in a well-coordinated manner.
42Criteria For reviewing Ongoing Project
Termination
- As identified by Dean (1968) The following
criteria are applicable for projects that are
terminated early . - Low probability of technical /commercial success.
- Low profitability / ROI / Market potential .
- Damaging cost growth .
- Change in competitive factors/ market needs .
- Technical problems that cannot be resolved.
- Competing projects having higher priority within
the organiation or department . - Schedule delays .
43Project Termination criteria
Termination Evaluation Criteria Possible tools for evaluation
Probability of technical commercial success Marketing research , profit loss analysis , value analysis
Profitability/ ROI / market potential Marketing research , profit loss analysis value analysis
Cost growth Budgeting , variance analysis
Changing competitive factors Marketing intelligence , profit / loss analysis
Technical problems that can be resolved Project viability, marketing mix analysis
Competing projects having higher priority within the organization/department Investment performance analysis , project priority review.
Schedule Days Variance analysis , impact on profit
Source Official CIM course book PMIM, 2009
44Implementation of Project Termination
- Project termination decisions are part of the
project process. In minor projects many of these
will be irrelevant . In others . In others , they
will be key factors for future project success. - Personnel issues.
- Operations /logistics / manufacturing
- Accounting and financial matters
- Processes
- Information systems
- Marketing activates.
45Seven steps to success
- Use an effective method
- Invest in planning
- Involve the customer
- Make it manageable
- Involve the team
- Communicate effectively
- Learn from mistakes
46Project Management Methodologies
- The two extreme of Project management
methodologies - Organiations have no formal methodology
- An Organiation wide methodology is applied for
all products and departments . - Between these two extremes there are many off the
shelf software packages . For managing projects ,
including Microsoft projects . - These packages identify the core processes and
reporting that is required is required in project
management, and can be bought or licensed for
application . - These packages are flexible enough to take
account n of a projects unique aspects . - These can be customized for marketing projects
but there are also off the shelf software
packages specifically for marketing projects .
47Project Management Methodologies
- A documented process for management of projects
that contains procedures , definitions and role
and responsibilities
- Prince/Prince 2
- A clear management structure
- Formal allocation of roles
- Plans for resourcing and technical issues
- Control procedures
- A focus on deliverables
48Project Management Methodologies
- Scalable methodologies recognises the differences
in project size, risk and complexity and allows a
customised approach for each project - Agile methodologies allow the project to adapt to
changes in the environment and business
landscape - Adaptive rather than predictive
- Focused on people rather than process
- Use an adaptive project framework (ADF)
49Project Monitoring and Control
- Project Monitoring Monitoring is the collecting
, reporting and recording , information
consisting any and all aspects of project
performance that the project manager or others in
the organization wish to know. - Project Control Control is last element in the
implementation cycle , of planning monitoring
controlling in essence , control is the act of
reducing the difference between plan and reality. - (Meredith and Mantell, 2000)
50Estimating task duration
- This is simply the length of time taken to
complete an activity . - There are problems with establishing time periods
include - Lack of experience in planning time durations for
tasks , and in doing activities. - Clearly , novices will typically take longer than
experienced workers to do the same tasks , and
may be unaware of the problems that take time .
Clearly lack of experience here cab lead to
unrealistic timescales. - Complexity of the marketing problems often these
involves creative tasks , for which focusing on
time may not detract form quality . - Unexpected events or delays due to illnesses/etc
. Also mistakes or other problems can add to the
time needed. Contingencies may have to be built
into the systems . - Novices tend t underestimate the amount of work
involved in any tasks . Expert project managers
tend to use the longest predicted duration in
scheduling , as this allows for possible delays .
51Project Monitoring
- Tracking and monitoring progress helps to ensure
an effective efficient project, by reviewing
project implementation against the approved plan
and budget. - This involves tracking data about activities and
progress. - The design of a realistic chain of results,
outcomes , outputs and activities is particularly
important. - Though Monitoring alone cannot make a successful
project, timely monitoring can help identify and
avoid necessary the 3 Cs that challenge projects.
- Crises
- Catastrophe
- Change
- The triple constrains minimum forms of review
- Time
- Cost
- Performance.
52- Reporting Progress
- Commonly monitoring is communicated to others
through reports and meetings. Prepared by either
the project team or independent auditors. - Reports also form the record on which project
history will be based. - Project Status reports.
- Provides updates on the project status. routine
reports) - An executive status report status update
prepared on a schedule (monthly, quarterly)
highlighting top level issues to parties who are
not directly involved in the project activities,
such as sponsors and other stakeholders. - Project Progress status report prepared on a
regular time schedule. - Usually the above reports are prepared by those
in key roles in the project - These enable all to be aware of plans to reduce
problems or recover form problems.
53- Extending Knowledge
- You can find templates for projects status
reports on Microsoft's websites. - Exception Reports Prepared for specific members
, for specific areas. Or when a scope change has
been made - Special Analysis Reports Communicating the
findings of a particular tool or activity , where
there is learning to be shared. This is a formal
working paper or white paper. - Independent Reviews Or Project Audits.
- Independent reviews would be required on a
periodic basis throughout the projects. This is
especially common in large or complex projects.
But can be applied in smaller risky projects. - These reviews or audits focus on the
implementation process, ensuring that the project
plans are being followed. They also examine how
problems and variations are being managed.
54- Monitoring Measures
- The major monitoring tools are
- Progress Checks
- Progressing according to plan or Progressing
according to work packages or incremental
milestones. - Variance Analysis - examining differences in
variables such as cost and time on predetermined
criteria. Progress of project against schedule or
expenditure against budget generally conducted in
top level performance aspects.
55Variance Analysis
- Variance analysis enables future planning and the
management of performance through
- Cost measurement
- Cost variance
- Cost performance index
- Schedule measurement
- Schedule variance
- Schedule performance index
- Budget forecasting
- Estimate to complete
- Estimate to completion
- Traffic light control
- The project scorecard
- Corrective action plans
56- Earned Value Analysis- This is essentially about
comparing expenditure against budgets. - called the baseline
- A quantitative project management monitoring
tool. Central to late project analysis. - compares the costs and progress of elements of
work against the budgeted costs and planned
activities from WBS. - The information required are
- - Planned Value Budgeted cost of work
scheduled (BCWS) - - Actual cost (AC)
- -Earned Value - the total project budget at a
given point in the life cycle. (BCWP)- Budgeted
cost of work performed.
57Resource PlanningHistogram
58The Project Monitoring System
- Identify the Information Requirements
- Identify The key factors to be monitored
- Identify the boundaries.
- The project monitoring system has to be specified
at the project initiation, Typically this will
look at the - Data collection process
- The standards
- Performance criteria.
59Introduction to Critical Path
60The Project Report
- Project report identifies the success of the
project . - Project history to encourage learning .
- A project success report focuses on the outcomes
of the project , and should identify , - Whether the projects objectives have been met and
identifying the success of the project on the
basis of this . - A comparison of the performance against the
planned target time and cost . - Whether the original project plan needs changes,
- Analysis of any changes to time , cost , outcomes
during the project . - Any other organizational requirements e.g. staff
performance testing etc.