Project Management in Marketing Session 6 - PowerPoint PPT Presentation

1 / 60
About This Presentation
Title:

Project Management in Marketing Session 6

Description:

Project Management in Marketing Session 6 Project Tools, Techniques and Termination ... Buying Physical or electronic Products Source: Official CIM course book ... – PowerPoint PPT presentation

Number of Views:275
Avg rating:3.0/5.0
Slides: 61
Provided by: DOMI108
Category:

less

Transcript and Presenter's Notes

Title: Project Management in Marketing Session 6


1
Project Management in MarketingSession 6
  • Project Tools, Techniques and Termination

2
Agenda
  • General Process of project Planning
  • Determining the Work breakdown structure
  • Estimating task duration
  • Tools and Techniques
  • Project Termination

3
Reasons for failure
  • Typical mistakes
  • Taking a task view
  • Optimism
  • Tracking
  • Not confronting early
  • Shackled by a plan
  • Lack of..
  • appropriate expertise and approach from Project
    Leader need to provide development
  • support from project sponsor need to
    communicate resources needed and reasons
  • ability/necessary expertise of team members
    need to select carefully
  • buy-in from end-users need to involve them in
    the project
  • project initiation

4
Project budget
  • Amount of resource required
  • Where required (i.e. doing what)
  • When required (calendarised, dd/mm/yy)
  • Who needs to sign-off (authority levels)
  • How will it be delivered

5
Determining Requirements A Resources Checklist
  • The people to be involved in the project , the
    level of their commitment and the required level
    of skills .
  • The facilities for the project planning , and
    depending on the project its implementation .
  • The equipment required such as computers ,
    cameras , or other audio visual equipment .
  • The money a budget needed to complete the task
    . There will often be an iterative process to
    determine budgets , taking account of the costs ,
    timescales etc .
  • The materials what tangibles , consumable or
    other items will be required in the process.

6
Sequencing Work
  • Scheduling refers to linking the various
    activities of a project
  • It examines the sequencing of tasks , both
    independent and interrelated.
  • By Organising into Suschedules and charts,
    detailing what will happen , when , by whom ,
    interfaces and the milestones for the tasks .
  • Once the work is listed out the following should
    be identified.
  • Predecessor tasks those required for another
    task to be completed
  • Successor Tasks those that cannot start until
    another task has been completed .
  • The schedule is a key tool in managing progress.

7
Tools
  • Project budget
  • GANTT chart
  • Network analysis
  • Project Evaluation Review Technique
  • Resource planning

8
GANTT Chart assessment basic
http//youtu.be/rm_iWKoOd0U 4m
  • Listing of all the activities to be carried out
    with the overlay of
  • Duration of each element
  • Estimated and actual task
  • Static and variable
  • Critical Path
  • Linked items (sequential or parallel)

9
Gantt Charts
Sample Gantt Chart for a production project .
Source http//www.rickwells.co.uk/images/gantt.gi
f
10
Network Analysis tools
  • Network Analysis tools Show the dependencies in
    work activities.
  • Common Analysis tools
  • CPM Critical Path Methodology
  • PERT Programme Evaluation and review
    techniques.
  • These tools concentrate on managing the total
    time for the project. Gantt charts concentrate on
    controlling time for each aspect of the project
  • The term critical path is used in place of the
    sequence of activities that takes the longest
    total time required to complete the project.
  • PERT used to determine how much time a project
    needs before it is completed, on the basis of
    activities being completed within a best worst
    and most likely estimate.

11
Critical Path Analysis or Network Analysis
  • Changes each and every time a significant
    alteration is made to the plan
  • Estimating task time for completion
  • Sequential or tandem or parallel tasks
  • Longest time allowable/shortest time
  • Drawing these into a network diagram

12
Critical Path on Gantt Chart
13
Project Management Software
  • Microsoft Project
  • Micro Planner X-Pert
  • Access (depending upon the project)
  • Excel
  • Word document tables (using formula)

14
Contingency plans - essential
  • Be realistic about
  • the time that elements of the project will take
  • how much can be done
  • other pressures on your time
  • What happens if the plan has to change?
  • More chance of keeping to time plan the earlier
    these changes are made
  • Discuss problems

15
Project reports anddocumentation extra marks
  • Project charter document - overview
  • Project management plan
  • Progress report
  • Post-completion audit

16
Core Project management Methodologies.
  • There are two common process methodologies.
  • Scalable Methodology
  • Agile methodology
  • Process
  • PRINCE stands for Projects in Controlled
    Environments.
  • It was developed by the Central Computer and
    Telecommunications Agency (CCTA) as a standard
    for IT project management by the UK Government.
  • While it was developed for IT projects, PRINCE is
    also used for non-IT projects, in both the public
    and private sectors. PRINCE2 is the latest
    version of this methodology.

17
Scalable Methodology
Source Official CIM course book PMIM, 2009
18
Agile Methodologies
  • Agile methodologies are ,
  • Adaptive rather than predictive agile
    approaches welcome changes , rather than have
    fixed plans .
  • Focused on people rather than process Process
    methods focus the processes set , and anyone
    could implement the plans . Agile approaches
    recognize that people have skills that can add to
    the project as it progresses.
  • Adaptive Project Framework
  • ADF is a customer focused methodology , which is
    based on being
  • Client focused and client driven
  • Frequent and early results reporting
  • Focused on questioning and introspection
  • Change is good when it is moving to a better
    solution .

19
Project Monitoring - assessment
  • Project monitoring is the collecting, recording
    and reporting information concerning any and all
    aspects of project performance that the project
    manager or others in the organisation need to
    know Meredith and Mantell (2000)
  • The project monitoring system comprises of
    identifying
  • the key information requirements
  • the key factors to be monitored
  • the boundaries

20
Project Control
  • Project control is the act of reducing the
    difference between plan and reality through
    Meredith and Mantell (2000)
  • Project team meetings
  • Issues lists
  • Regular reviews
  • Team member accountability
  • Milestones
  • Scheduling
  • Stakeholder meetings

21
Project Management - Summary
  • Initiation
  • Limits constraints and priorities defined
  • Planning
  • Team members selected
  • Scope of project defined
  • Potential risks identified and planned for
  • Resources required determined
  • Control
  • Deliverables created
  • Progress monitored communicated
  • Issues resolved and changes managed
  • Close out
  • Customer satisfaction measured
  • Lessons learned analysed

22
(No Transcript)
23
Project Monitoring
  • Progress report
  • Project status update
  • Extending knowledge
  • Independent reviews or project audits
  • Project meetings
  • Monitoring measures
  • Progress checks
  • Variance analysis
  • Earned value analysis and monitoring

24
Agenda
  • General Process of project Planning
  • Determining the Work breakdown structure
  • Buying Physical or electronic Products
  • Estimating task duration
  • Tools and Techniques
  • Project Termination

25
Agenda
  • General Process of project Planning
  • Determining the Work breakdown structure
  • Buying Physical or electronic Products
  • Estimating task duration
  • Tools and Techniques
  • Project Termination .

26
Buying Physical or electronic Products
Source Official CIM course book PMIM, 2009
27
Agenda
  • General Process of project Planning
  • Determining the Work breakdown structure
  • Buying Physical or electronic Products
  • Estimating task duration
  • Tools and Techniques
  • Project Termination
  • The Project report

28
Agenda
  • General Process of project Planning
  • Determining the Work breakdown structure
  • Buying Physical or electronic Products
  • Estimating task duration
  • Tools and Techniques
  • Project Termination .
  • The Project report.

29
Learning Outcomes
  • 6.1 Critically assess the importance of and
    techniques for establishing the marketing
    projects scope, definition and goals relative to
    the organisational marketing plan
  • 6.2 Utilise a range of tools and techniques to
    support project planning, scheduling, resourcing
    and controlling of activities within the project
    to enable effective and efficient implementation
  • 6.3 Utilise a variety of methods, measurements
    and control techniques to enable effective
    monitoring and measuring of progress throughout
    the project to ensure that it is completed to
    specification, on time and within budget
  • 6.4 Critically Assess the main techniques for
    evaluating effectiveness, success or failure of a
    marketing project on its completion

30
Agenda
  • General Process of project Planning
  • Determining the Work breakdown structure
  • Buying Physical or electronic Products
  • Estimating task duration
  • Determining Requirements A Resources Checklist
  • Tools and Techniques
  • Project Termination
  • The Project report

31
Agenda
  • General Process of project Planning
  • Determining the Work breakdown structure
  • Buying Physical or electronic Products
  • Estimating task duration
  • Determining Requirements A Resources Checklist
  • Tools and Techniques
  • Project Termination
  • The Project report

32
Agenda
  • Core Project management methodologies
  • Project monitoring and Control
  • Project monitoring
  • Project Monitoring System

33
General Process of Project Planning
  • Determining the work breakdown structure
  • Estimating timing and task duration
  • Determining resource requirements
  • Allocating responsibilities
  • Sequencing work
  • Developing the project schedule or network
  • Preparing the integrated planning document .

34
Determining the Work breakdown structure - WBS
WBS Implementing a customer relationship
Management System Source Adapted from Maylor.
35
Representing the Schedule
..............
Task Network
..............
..............
..............
..............
Milestones
Resource Histogram
Gantt Chart
36
Example Gantt Chart
37
Estimates
  • Not written in stone
  • Not even necessarily accurate
  • Accompanying confidence level
  • Need to be monitored throughout
  • Need to be changed each time the specification is
    changed or discoveries made

38
Agenda
  • Core Project management methodologies
  • Project monitoring and Control
  • Project monitoring
  • Project Monitoring System

39
Project Termination
  • Ideally a project is terminated once it is
    completed .
  • Alternatively it could when the project has
    problems or it fail to achieve its outcomes.
  • Activities at termination rarely affect the
    project activities .
  • Although it will affect
  • the success of the future projects.
  • The attitudes of the project team .
  • This is the final stage in project management .
  • This will be followed by the project review
    process which will use evaluation tools to
    address the dimensions of success and failure.
  • The two models of project decision making
  • Models based on the extent to which the project
    has achieved or failed to achieve its desired
    outcomes.
  • Models that compare the rpoject against generally
    accepted standards for success and failure for a
    project.

40
Project Termination Concerns
  • Terminating a project needs delicate handling and
    finesse. Successfully closing out a terminated
    project should be viewed as a greater achievement
    than closing out a successful one.
  • The team should be made aware of the rationale
    behind the termination well before the official
    announcement.
  • The team (and project manager) should be reminded
    that project termination does not always indicate
    project mismanagement.
  • Team members should be allowed and encouraged to
    document accomplishments and status of the
    terminated project.

41
Project Termination Concerns
  • The project manager should identify how the work
    completed will contribute to future projects and
    hold a celebration of the teams achievements.
  • The project manager should work with functional
    managers to reassign personnel to new projects
    and present team members plans for future
    assignments. These reassignments should be into
    comparable or higher positions, to eliminate the
    notion that the canceled project reflects on
    their capabilities.
  • The close-out must ensure that all contractual
    requirements are satisfied and all records
    properly stored. Finally, project resources must
    be released in a well-coordinated manner.

42
Criteria For reviewing Ongoing Project
Termination
  • As identified by Dean (1968) The following
    criteria are applicable for projects that are
    terminated early .
  • Low probability of technical /commercial success.
  • Low profitability / ROI / Market potential .
  • Damaging cost growth .
  • Change in competitive factors/ market needs .
  • Technical problems that cannot be resolved.
  • Competing projects having higher priority within
    the organiation or department .
  • Schedule delays .

43
Project Termination criteria
Termination Evaluation Criteria Possible tools for evaluation
Probability of technical commercial success Marketing research , profit loss analysis , value analysis
Profitability/ ROI / market potential Marketing research , profit loss analysis value analysis
Cost growth Budgeting , variance analysis
Changing competitive factors Marketing intelligence , profit / loss analysis
Technical problems that can be resolved Project viability, marketing mix analysis
Competing projects having higher priority within the organization/department Investment performance analysis , project priority review.
Schedule Days Variance analysis , impact on profit
Source Official CIM course book PMIM, 2009
44
Implementation of Project Termination
  • Project termination decisions are part of the
    project process. In minor projects many of these
    will be irrelevant . In others . In others , they
    will be key factors for future project success.
  • Personnel issues.
  • Operations /logistics / manufacturing
  • Accounting and financial matters
  • Processes
  • Information systems
  • Marketing activates.

45
Seven steps to success
  • Use an effective method
  • Invest in planning
  • Involve the customer
  • Make it manageable
  • Involve the team
  • Communicate effectively
  • Learn from mistakes

46
Project Management Methodologies
  • The two extreme of Project management
    methodologies
  • Organiations have no formal methodology
  • An Organiation wide methodology is applied for
    all products and departments .
  • Between these two extremes there are many off the
    shelf software packages . For managing projects ,
    including Microsoft projects .
  • These packages identify the core processes and
    reporting that is required is required in project
    management, and can be bought or licensed for
    application .
  • These packages are flexible enough to take
    account n of a projects unique aspects .
  • These can be customized for marketing projects
    but there are also off the shelf software
    packages specifically for marketing projects .

47
Project Management Methodologies
  • A documented process for management of projects
    that contains procedures , definitions and role
    and responsibilities
  • Prince/Prince 2
  • A clear management structure
  • Formal allocation of roles
  • Plans for resourcing and technical issues
  • Control procedures
  • A focus on deliverables

48
Project Management Methodologies
  • Scalable methodologies recognises the differences
    in project size, risk and complexity and allows a
    customised approach for each project
  • Agile methodologies allow the project to adapt to
    changes in the environment and business
    landscape
  • Adaptive rather than predictive
  • Focused on people rather than process
  • Use an adaptive project framework (ADF)

49
Project Monitoring and Control
  • Project Monitoring Monitoring is the collecting
    , reporting and recording , information
    consisting any and all aspects of project
    performance that the project manager or others in
    the organization wish to know.
  • Project Control Control is last element in the
    implementation cycle , of planning monitoring
    controlling in essence , control is the act of
    reducing the difference between plan and reality.
  • (Meredith and Mantell, 2000)

50
Estimating task duration
  • This is simply the length of time taken to
    complete an activity .
  • There are problems with establishing time periods
    include
  • Lack of experience in planning time durations for
    tasks , and in doing activities.
  • Clearly , novices will typically take longer than
    experienced workers to do the same tasks , and
    may be unaware of the problems that take time .
    Clearly lack of experience here cab lead to
    unrealistic timescales.
  • Complexity of the marketing problems often these
    involves creative tasks , for which focusing on
    time may not detract form quality .
  • Unexpected events or delays due to illnesses/etc
    . Also mistakes or other problems can add to the
    time needed. Contingencies may have to be built
    into the systems .
  • Novices tend t underestimate the amount of work
    involved in any tasks . Expert project managers
    tend to use the longest predicted duration in
    scheduling , as this allows for possible delays .

51
Project Monitoring
  • Tracking and monitoring progress helps to ensure
    an effective efficient project, by reviewing
    project implementation against the approved plan
    and budget.
  • This involves tracking data about activities and
    progress.
  • The design of a realistic chain of results,
    outcomes , outputs and activities is particularly
    important.
  • Though Monitoring alone cannot make a successful
    project, timely monitoring can help identify and
    avoid necessary the 3 Cs that challenge projects.
  • Crises
  • Catastrophe
  • Change
  • The triple constrains minimum forms of review
  • Time
  • Cost
  • Performance.

52
  • Reporting Progress
  • Commonly monitoring is communicated to others
    through reports and meetings. Prepared by either
    the project team or independent auditors.
  • Reports also form the record on which project
    history will be based.
  • Project Status reports.
  • Provides updates on the project status. routine
    reports)
  • An executive status report status update
    prepared on a schedule (monthly, quarterly)
    highlighting top level issues to parties who are
    not directly involved in the project activities,
    such as sponsors and other stakeholders.
  • Project Progress status report prepared on a
    regular time schedule.
  • Usually the above reports are prepared by those
    in key roles in the project
  • These enable all to be aware of plans to reduce
    problems or recover form problems.

53
  • Extending Knowledge
  • You can find templates for projects status
    reports on Microsoft's websites.
  • Exception Reports Prepared for specific members
    , for specific areas. Or when a scope change has
    been made
  • Special Analysis Reports Communicating the
    findings of a particular tool or activity , where
    there is learning to be shared. This is a formal
    working paper or white paper.
  • Independent Reviews Or Project Audits.
  • Independent reviews would be required on a
    periodic basis throughout the projects. This is
    especially common in large or complex projects.
    But can be applied in smaller risky projects.
  • These reviews or audits focus on the
    implementation process, ensuring that the project
    plans are being followed. They also examine how
    problems and variations are being managed.

54
  • Monitoring Measures
  • The major monitoring tools are
  • Progress Checks
  • Progressing according to plan or Progressing
    according to work packages or incremental
    milestones.
  • Variance Analysis - examining differences in
    variables such as cost and time on predetermined
    criteria. Progress of project against schedule or
    expenditure against budget generally conducted in
    top level performance aspects.

55
Variance Analysis
  • Variance analysis enables future planning and the
    management of performance through
  • Cost measurement
  • Cost variance
  • Cost performance index
  • Schedule measurement
  • Schedule variance
  • Schedule performance index
  • Budget forecasting
  • Estimate to complete
  • Estimate to completion
  • Traffic light control
  • The project scorecard
  • Corrective action plans

56
  • Earned Value Analysis- This is essentially about
    comparing expenditure against budgets.
  • called the baseline
  • A quantitative project management monitoring
    tool. Central to late project analysis.
  • compares the costs and progress of elements of
    work against the budgeted costs and planned
    activities from WBS.
  • The information required are
  • - Planned Value Budgeted cost of work
    scheduled (BCWS)
  • - Actual cost (AC)
  • -Earned Value - the total project budget at a
    given point in the life cycle. (BCWP)- Budgeted
    cost of work performed.

57
Resource PlanningHistogram
58
The Project Monitoring System
  • Identify the Information Requirements
  • Identify The key factors to be monitored
  • Identify the boundaries.
  • The project monitoring system has to be specified
    at the project initiation, Typically this will
    look at the
  • Data collection process
  • The standards
  • Performance criteria.

59
Introduction to Critical Path
60
The Project Report
  • Project report identifies the success of the
    project .
  • Project history to encourage learning .
  • A project success report focuses on the outcomes
    of the project , and should identify ,
  • Whether the projects objectives have been met and
    identifying the success of the project on the
    basis of this .
  • A comparison of the performance against the
    planned target time and cost .
  • Whether the original project plan needs changes,
  • Analysis of any changes to time , cost , outcomes
    during the project .
  • Any other organizational requirements e.g. staff
    performance testing etc.
Write a Comment
User Comments (0)
About PowerShow.com