About This Presentation
Title:

GBA 573 Final Presentation

Description:

Glen Fields - Final Project Presentation How Projects Get Started Overview Project is to: Perform an assessment at Disneyland Optimize Maintenance and Reliability ... – PowerPoint PPT presentation

Number of Views:71
Avg rating:3.0/5.0
Slides: 19
Provided by: Glen185
Learn more at: http://carl.sandiego.edu
Category:

less

Transcript and Presenter's Notes

Title: GBA 573 Final Presentation


1
GBA 573 Consulting

Glen Fields - Final Project Presentation
2
What Sets CSI Apart...
GBA 573 Consulting
  • Company Background
  • Located in San Diego, CA
  • 5 Engineering Consultants
  • Established in 2002
  • Specialize in Facility Assessment, Strategy
    Development, and Project Management

3
How Projects Get Started
4
Overview
  • Project is to
  • Perform an assessment at Disneyland
  • Optimize Maintenance and Reliability Program
  • Develop Customized Computer Reliability Software
    Program
  • Install Wireless Sensors to Monitor Equipment
  • Document Findings and Present to Management

GBA 573 Consulting
5
Deliverables
  • Deliverables of the Project are
  • Assessment and Benchmark prior to Project
    Implementation
  • Equipment and Technology Matrix
  • Microsoft Project Schedule
  • Recommended Training Matrix
  • Identification and Documentation of Park Goals
    for the Condition Monitoring Program
  • Consultation of Work Flow Diagram for Optimized
    Implementation of Condition Monitoring Program

GBA 573 Consulting
6
Maintenance Optimization
GBA 573 Consulting
7
Work process
  • Identify Issues That Affect Maintenance Work
    Process
  • Capture As Is Work Process
  • Develop To Be Work Process Diagram

GBA 573 Consulting
8
Work Processes
  • The CMMS system is used to plan and schedule the
    work, track machine history, and to track cost
    and savings information. Some of the key goals
    are prioritization of WOs, elimination of
    unnecessary PMs, and program justification.
  • A key role of the IT group is the identification
    of the criticality of plant machinery so the work
    can be prioritized. Resources and technologies
    are assigned to plant assets based on equipment
    or systems importance to the production cycle.
    Performance of critical equipment is tracked and
    reported.
  • Condition Monitoring plays a key role in
    acceptance and certification of plant equipment.
    Formal processes have been established to insure
    PDM is used on new and reworked equipment,
    incoming oils are inspected for quality, IR is
    used before shutdowns, and root cause studies are
    performed on all critical equipment failures.
    Feedback loops are in place on all WOs and
    regular meetings are scheduled to discuss
    critical issues.
  • Quality and Reliability are a way of life not a
    periodic process.

GBA 573 Consulting
9
Work Process Designed for Maintenance Optimization
What
RM Equipment Failures
Scheduled PM Tasks
Work Closeout
Work Execution
PdM Equip. Condition Directed Feedback
PAM Root Cause Analysis Identifies
Equip. Condition
GBA 573 Consulting
10
Technology
  • Identify Which Rides at Disneyland are Critical
  • Based on the Criticality of the Ride, Assign
    Monitoring Technology
  • Integrate Information Into an Equipment and
    Technology Matrix
  • Install Monitoring Sensors on Equipment

GBA 573 Consulting
11
Condition Based Maintenance Program Elements
GBA 573 Consulting
12
Technology
  • Recommended Condition Monitoring Technologies
  • Wireless Vibration Monitoring Sensors
  • Wireless Lubrication Monitoring Sensors
  • Infrared Thermography

GBA 573 Consulting
13
Equipment and Technology Matrix
GBA 573 Consulting
14
Work Culture and Management
  • Continued Focus on Benchmarking Facility
  • Establish Vision
  • Identify Goals
  • Establish Global Metrics (SMART)
  • Specific
  • Measurable
  • Achievable
  • Reasonable
  • Timely
  • Upper Management Visability

GBA 573 Consulting
15
Work Culture and Management
  • Plant managers know the importance of program,
    understand the financial impact, invest in the
    people and technology, and communicate regularly
    with the maintenance department.
  • A formalized plan for plant reliability has been
    established and the impacted Team members.
    Performance measures are established, tracked,
    and reported on a regular basis. All members of
    the Team are asset owners and the emphasis is on
    elimination of critical equipment failures.
  • Regular meetings are scheduled with all
    departments to communicate findings, plan
    strategies, look at WO optimization ,and to
    optimize resource utilization. . Work Teams are
    established to break down reporting barriers and
    equipment ownership is assigned at the crafts
    level to empower the resources.

GBA 573 Consulting
16
People / Skills
  • Establishing and Understanding Roles and
    Responsibilities
  • Developing and Maintaining Sponsorship
  • Event Reporting
  • Condition Assessment Reporting
  • ROI Calculations
  • Correlation of Technical Data
  • Financial Aspects of Program

GBA 573 Consulting
17
Program Costs
GBA 573 Consulting
18
Schedule
  • Detailed Project Schedule Developed
  • Project Estimated at 6 Weeks

GBA 573 Consulting