Title: LHC Systems
1LHC Systems
- Cryogenics.as seen by Beam Handlers
- G. Arduini, S. Redaelli
- Many thanks to
- A. Butterworth, S. Fartoukh, M. Giovannozzi, A.
Rijllart, L. Serio, F. Zimmermann
2Outline
- LHC Cryogenic system overview
- Instrumentation and Signals
- Cryo-Organization during Beam Commissioning
- Application SW
- Cryogenics powering
- Cryogenics commissioning with beam
- What could go wrong during beam commissioning?
- Tools needed
- Summary
3LHC cryogenic system layout
L. Serio
4LHC Cryogenic System layout
- No redundancy for sector 2-3 in case of problems
with the cryogenic unit in point 2 and no fast
cool-down possible - Naming
- Q Cryogenic System
- S, U Surface, Undergorund
- C, R, I Warm compressor, Refrigerator,
Interconnection Box
5LHC Cryogenic Components in Tunnel
6Instrumentation and signals
- Available instrumentation and signals in the
tunnel - Pressure gauges (PT)
- Temperature gauges (TT)
- Level gauges (LT)
- Valve opening (CV)
- Virtual flow meters at the valves (based on
pressure drop and temperature measurements,
tables on He characteristics, valve opening,
etc..) (FT)
7Instrumentation and signals
L. Serio
8Instrumentation and signals
9Cryo-Organization during Beam Commissioning
- On-line
- Planned 1 8 h shift on-call operators and
experts - Possible 2 8 h shift on-call experts (as for
HW commissioning) - Ideal 3 8 h shift on-call experts
- In the case of process faults (e.g. spurious
faults, partial HW faults) the presence of a
cryo-operator could limit the recovery time and
even avoid beam-dumps and could be essential in
case of teething problems - Off-line
- Cryogenic Performance Panel (CPP Chair L.
Serio) - Analyze off-line, manage all aspects of cryogenic
performance, - Study, propose improvements of functional
procedure and consolidations, - Record and track cryogenic sub-system performance
in relation to their manufacturing and test data. - Design and set-up of the tools for the additional
on-line monitoring of the cryogenics during beam
commissioning - ? provide crucial feedback for the steering of
the beam commissioning
10Application SW
- High level of detail in the application available
in CCC. - Possible to navigate through the Cryogenic
system.
- Four access levels (the first three with
password) - Administrator omnipotent
- Expert login for experts only, direct control on
each piece of equipment of the cryo system.
Possibility to change interlock level. - Operator can operate the system, accessing the
equipment but cannot change interlock levels. - Monitor Read access only ? this is the mode in
which we should use the application - Under deployment nominative access with
role-based rights
11Sector 7-8 Navigation bar
12Sector 7-8 (arc)
- GreenOK
- YellowWarning
- RedNot Ok
- BlueInvalid Data
- PurpleNot Avail.
13Sector 7-8 Navigation bar
14Sector 7-8 Inner Triplet L8 DFBX
15Temperature overview for each sector
16Signal overviews for the Sectors
Cold Mass temperatures
Pressures
He levels
Line C temperatures
17Sector 7-8 (arc)
18Trends
- Predefined sets or operator defined
- Possibility to select the trend of one parameter
from overview or synoptic plot
19Cryogenics Post-Mortem - General information
- PM analysis based on check functions defined by
experts - LabView Logic specified by the Cryogenics
Performance Panel in Excel tables, interpreted by
a LabView program, this is part of the Magnet PM
analysis software provided by CO/MA. - Four PM event triggers CRYO_START,
CRYO_MAINTAIN, QUENCH, ALARM. They can be
triggered on request ? PM can be used also as
analysis tool! - For the moment, only expert logic is implemented
- The tools seem flexible it should be possible to
add a beam-oriented logic for the PM analysis. - PM application retrieves data from the logging
data-base - Delay of a few minutes before data are available
for analysis - Inconsistency between the logging and measurement
DB have been observed - Filtering and smoothing of the data before
transfer to the logging DB can false the trends - ? why not accessing the measurement data-base?
20Cryogenics Post-Mortem application - snapshots
Buttons that simulated 4 PM events (CRYO_START,CRY
O_MAINTAIN,QUENCH,ALARM)
Display of selected signals
Main table with results of PM analysis (analysis
type and results given)
Signals for the plot
Faulty signals (did not pass the test)
Signals with no data (last acquisition reported)
21Some additional features
Sorting results (signal name, analysis
type) Possibility to save and retrieve the
results of the analysis are available and
required in particular if access to the
measurement DB is implemented
Signals to graph
22Cryogenics conditions for powering
- There will be three logic states for each
powering sub-sector - Conditions to authorize magnet powering
(CRYO_STARTTRUE and CRYO_MAINTAINTRUE) - Conditions that do not authorize magnet powering
but if there is already current in the magnets
there is no request for discharge (the conditions
of magnet powering were met at the time of the
start of powering but have disappeared meanwhile)
(CRYO_STARTFALSE and CRYO_MAINTAINTRUE) - Conditions that do not authorise magnet powering
and request a slow current discharge
(CRYO_STARTFALSE and CRYO_MAINTAINFALSE) - 32 Powering sub-sectors
- 3 types per sector
- ITD1 (in IR2 and 8)DFBX (8 in total)
- Matching Section standalone magnets _at_ 4.5
KDFBM,DFBL,DSL (12 in total) - ARC DFBA (8 in total)
- 4 RF modules
23CRYO_START / MAINTAIN
- No direct connection of Cryo with BIC but only
with PIC - Only insulation vacuum is directly interlocked to
cryogenics (lt10-3 mbar, expect a steady state of
10-6 mbar if no leaks). - No direct connection (no interlocking) between
Beam Vacuum and Cryogenics Bad beam vacuum ?
Higher heat load ? CRYO_START and CRYO_MAINTAIN
might disappear
24Cryogenics commissioning with beam
- Assumptions
- The Cryogenics system should be fully
commissioned during the HW commissioning period ?
in that case its behaviour as a function of the
powering levels (energy dependence) should be
understood - The main remaining unknown is the interplay of
the beam with the cryogenics system - Heat load on the beam screen due to
- resistive dissipation of image currents
- synchrotron radiation
- electron cloud
- Heat load on the cold masses due to
- Nuclear inelastic beam-gas scattering (depending
on the vacuum level) - Other type of beam losses (e.g. beam halo losses
and energy deposition from the induced showers)
25Cryogenics commissioning with beam
per aperture
600
900
1300
2200
L. Tavian LTC 2/6/2004 F. Zimmermann LTC
6/4/2005
26Cryogenics commissioning with beam
LHC Design report L. Tavian LTC 2/6/2004
- A priori no need for dedicated time for
cryogenics studies with beam but parasitic
follow-up of the behaviour of the cryogenics in
the presence of beam as a function of its
parameters ? monitoring by Cryogenics Performance
Panel. Its feedback will be crucial in steering
the commissioning (in particular the increase in
intensity)
27Critical elements
- Are there elements which are more critical than
others? - Magnets
- Q6 in IR1 and 5 (standalone magnet at 4.5 K) as
evidenced by quench behaviour - MQTLs
- In general SC magnets close to collimation areas
and triplets in the interaction points - Q4 close to the beam dump area
- Interaction with and feedback from MPP is vital
to define critical elements - RF
- Coupling with the rest of the sector might be an
issue - Little margin for the pressure levels ? Beam dump
at 1.5 bar - Cryo limit could be reached if we try to run with
less cavities but higher field - Sector 2-3 no redundancy
- Sector 3-4 and 4-5 are the most critical
- From the point of view of the heat load (due to
the additional load from the RF in IR4) - 4-5 is also critical from the point of view of
the temperature due to the hydrostatic heads
because of the slope on the LHC ring
28What could go wrong during beam commissioning?
L. Serio AB/OP shut-down courses 7/3/2007
Cryo commissioning presently ongoing is the first
chance to test all the systems together and their
interactions. More might have to be learned when
we will start to inject beam.
29What could go wrong during beam commissioning?
- Quenches will be the routine
- More than 14 cells or full sector ? recovery up
to 48 hours - In case of fast discharge (even w/o quench) ? 2 h
recovery (heating due to eddy currents).
L. Serio Training Day for the Commissioning of
the LHC Powering System 29/3/2007
30What could go wrong during beam commissioning?
- Strong correlation cryogenics vacuum
- Vacuum transients might result from
- excessive condensation of gases on the beam
screen in the cells adjacent to a quenched one ?
warming-up of the Beam Screen (to 40 K) might be
required (few hours required) before injecting - Operation of the beam screen at temperatures
close to 24 K (instead of 20 K) e.g. as a result
of localized losses can result in emission of CO
from the Beam Screen and reduced lifetime
V. Baglin Chamonix XIII
31What could go wrong during beam commissioning?
- Heat loads above specifications
- In that case heat load measurements and
comparison with expectations are essential before
any increase in intensity - The resolution in heat load on the beam screen is
0.5 W/cell to be compared with 280 W/cell as
expected beam induced heat load at nominal
intensity at 7 TeV. The expected margin in
nominal conditions is 40 W/cell. Possible mean
to see pressure bumps? - Local heating on cold masses can be measured with
the resolution of a cell and localization within
a cell might be possible by measurements of the
temperature difference between magnets - EM-interference induced by the beam on the
sensors - Past experience (SPS) has shown that sensors
(e.g. temperature sensors) can be affected by the
beam presence in particular for high intensity - Main difference sensors are not in direct view
of the beam - Countermeasures redundancy and filtering
- This should manifest itself as a
non-deterministic behaviour of some of the
control loops. - Could be a nightmare
32Tools needed
- Certainly we will need a summary of the Cryo
Maintain/Start conditions for the different
Sub-Sectors - Available soon
L. Serio
33Tools needed
- If the Cryogenics parameters start to drift on
time scales of minutes probably there is not much
that we (or the Cryogenics Expert) can do to
re-establish stable conditions and save the
beam - Follow-up of the trends when the mode of
operation is changed (intensity or energy
variation) is vital for planning the
commissioning steps and minimizing down-time - We could specify analysis types relevant for LHC
operation in the PM and trigger it via alarms (on
trends) or external triggers. - Define virtual heat loads on beam screens and
cold masses from temperature, flow, pressure
measurements and heater setting (started by CPP) - Monitor heat load and temperatures on beam screen
and cold mass, correlate with vacuum, beam
intensity, beam losses and compare with
expectations - Add temperature/flow trends to identify
critical behaviour based on signal evolution - Later fixed-displays could take overonce the
measurements and measurement devices are fully
mastered and the needs and problems clarified
34Summary
- The behaviour of the cryogenics as a function of
the powering levels (energy dependence) should be
understood before beam commissioning ? a priori
no dedicated time required during beam
commissioning but the beam presence might
introduce additional unexpected effects. - The presence of cryo-operators on 3 x 8 h shift
during beam commissioning could help to sort-out
potential teething problems of the cryo-system
and to reduce beam down-time during the
commissioning. - Interaction with CPP and MPP should be
strengthened in order to focus on the critical
elements and refine the analysis tools for beam
commissioning. - Detailed SW tools exist to assist the expert in
the control of the cryogenic system - For beam operation heat loads are probably the
most meaningful parameters understanding of
their trends could be very useful to identify and
anticipate problems. The resolution (also
spatial) should be sufficient. - Non-expert tools need to be enhanced ? The
post-mortem analysis fishing in the measurement
DB could be a powerful tool for the Beam
Commissioning period although later fixed
displays could be developed.
35References
- LHC Design Report Chapter 11 - Cryogenics
- LHC-Q-ES-0004 (EDMS 710799) The circuit of the
LHC cryogenic system - LHC-Q-ES-0003 (EDMS 710797) Functional analysis
of the LHC cryogenic system process - L. Serio, Cryogenics and powering - Training Day
for the Commissioning of the LHC Powering System
29/3/2007 - L. Serio, LHC Cryogenics AB/OP shut-down
Courses 7/3/2007 - L. Tavian, LTC 02/06/2004
- F. Zimmermann, LTC 06/04/2005
- V. Baglin, Vacuum Transients during LHC
Operation, Chamonix XIII