Title: Earned Value
1Earned Value
JOEL VIRAY jviray_at_lmrsolutions.com
2TOPICS
- What is Earned Value Management?
- Why do I need it?
- How do I do it?
- Earned Value Reporting
- Earned Value System
3What is Earned Value?
A Managers Tool for Integrated Cost, Schedule
and Technical Performance Management
Technical
Schedule
Earned Value
Cost
CSSR
CPR
Other Information
- Earned Value is an objective measurement of how
much work has been accomplished on a project and
at what cost - Provide early alerts to performance slippage
- Earned Value indicates how much of the budget
should have been spent in view of the amount of
work done so far
4Why use EVM?
- Accurate picture of project status
- cost, schedule, AND technical
- Early and accurate identification of trends and
problems - Basis for corrective action
- Supports mutual goals of contractor and customer
- bring project in on schedule and cost
5How Does Earned Value Work?
- Successful EVM management requires several key
practices - Identify each project deliverable
- Develop a schedule for the completion of each
deliverable - Assign a value to each deliverable
6Terminology
- ACWP Actual Cost of Work Performed
- BCWP Budgeted Cost of Work Performed
- BCWS Budgeted Cost of Work Scheduled
- SPI Schedule Performance Index
- (EV/Planned Value) or (BCWP/BCWS)
- CPI Cost Performance Index
- (EV/Actual Cost) or (BCWP/ACWP)
- EAC Estimate at Completion
- BAC Budget at Completion
7WHY DO I NEED IT?
EVM - A Simple Example
- Your project
- total budget of 100,000
- 12 month effort
- produce 20 units
- How are you doing? Is everything going to plan?
- How far along are you? (64, 50, gt40)
- Is this where you expected to be or do you need
to take action?
- Status
- spent to date 64,000
- time elapsed 6 months
- units produced 8 complete or 40 Complete
8Earned Value the Math
EVM - A Simple Example
- Your project
- total budget of 100,000
- 12 month effort
- produce 20 units
- The Basics
- BAC Budget at Completion 100,000
- BCWS Plan 50,000
- ACWP Actuals 64,000
- BCWP Performance 5,000/unit 40,000
- Status
- spent to date 64,000
- time elapsed 6 months
- units produced 8 complete or 40 Complete
9EVM - A Simple Example
- Your project
- total budget of 100,000
- 12 month effort
- produce 20 units
- Earned Value
- BAC 100,000 ACWP 64,000
- BCWS 50,000 BCWP 40,000
- The Variance Measures
- CV Cost Variance BCWP-ACWP -24,000
- SV Schedule variance BCWP-BCWS -10,000
- CV CV/BAC -20
- SV SV/BAC -10
- CPI BCWP/ACWP 40,000/100,000 0.4
- SPI BCWP/BCWS 40,000/50,000 0.8
- Status
- spent to date 64,000
- time elapsed 6 months
- units produced 8 complete or 40 Complete
10Earned Value Trend Graph
125K
Cost Variance 20K
100K
75K
ACWP 64K
BCWS 50K
Cost
50K
25K
Earned Value (Work Completed) 40K
10K
0
TIME NOW
J
F
M
A
M
J
J
A
S
O
N
D
M
J
J
A
S
O
N
D
J
F
TIME FRAME
11Sample Project Second Story Deck
- Stands 10 feet off the ground
- Measures 12 x 12 feet
- Set of stairs will lead to the ground
- Will be supported with 4 posts resting on
concrete footings - Footings must extend below frost line (4 feet)
- Homeowner (and friends) will construct with
standard materials
12Planned Values for Deck Replacement Project
13Measuring Performance
- End of Day 5
- Planned 34 hours of work
- Expended 36 hours
- Earned 26 hours
14(No Transcript)
15Measuring Performance
16Measuring Performance
- CPI (EV/Actual Cost)
- 26/36 0.72
- We are realizing 7.2 hours of result for every 10
hours of actual effort expended - SPI (EV/Planned Value)
- 26/34 0.76
- We are realizing 7.6 hours of result for every 10
hours of planned effort
17Corrective Action
Stakeholder Priority General Approach Possible Approaches
Maintain project schedule Sacrifice product Reduce scope of other part of project (hand railings) Stop digging and hope building inspector doesnt notice
Sacrifice cost Work overtime Have a friend help (more pizza and beer) Rent a back-hoe
18Re-Baseline Plan
19Why do we need Early Warning?
Course corrections are easier when you have time
to make adjustments Its too late when youre
this close to the iceberg!
20STATING THE OBVIOUS
- EVM will not solve your problems - only you can
do that! - A good tool is POINTLESS if you dont TAKE ACTION
based on the information it gives you!!!
21EPM Solution Architecture
Line of Business Applications WAW DIFMS SOSSLDCA
DA More
Internal/External Databases