Joint Report to Select Committee on Appropriations - PowerPoint PPT Presentation

About This Presentation
Title:

Joint Report to Select Committee on Appropriations

Description:

Joint Report to Select Committee on Appropriations by Northern Cape Department of Health Northern Cape Department of Roads & Public Works supported by – PowerPoint PPT presentation

Number of Views:43
Avg rating:3.0/5.0
Slides: 9
Provided by: Richard1606
Category:

less

Transcript and Presenter's Notes

Title: Joint Report to Select Committee on Appropriations


1
Joint Report toSelect Committee on Appropriations
  • byNorthern Cape Department of HealthNorthern
    Cape Department of Roads Public
    Works supported byNational Department of
    Health (Infrastructure)
  • 08 August 2012

2
1. PURPOSE
  • This report provides progress made on the
    construction of the Northern Cape Provincial
    Mental Health Hospital
  • It follows the visit to the project site by the
    Select Committee on Appropriations on the 24th
    January 2012

3
2. INITIAL CONTRACTOR
  • Aug 2005 Provincial Tender Board awarded contract
    to Vista Park/JOH Arch Investments, to commence
    Sept 2005
  • Delays in bulk earthworks meant that contractor
    only commenced Feb 2006
  • Revised completion date set at 20 March 2008 due
    to late start and bad weather
  • By 2007 slow construction was noted, including
    poor workmanship incomplete remedial work
  • By August 2009 contractor 565 days behind
    schedule
  • Penalties totalling R11.3 million levied but not
    deducted
  • Contractor failed to submit revised construction
    program but instead submitted claim for extension
    of time and costs
  • Slow delivery compounded by water penetration
    caused structures to deteriorate
  • Non-payment to sub-contractors caused delays -
    cash flow
  • Poor supervision of workforce by contractor

Report commissioned in 2011 by NC DRPW into the
initial tendering and contracting process (Gobodo
Forensic Investigative Accounting)
4
3. TERMINATION OF INITIAL CONTRACTOR
  • Poor performance
  • Feb 2008 contractor requested to provide
    definitive plan to complete project by 20 Mar
    2008
  • April 2008 contractor failed to complete project
    or submit required completion plan. Contractor
    informed they were in breach of contract
  • Feb 2009 contractor submitted claim for extension
    of time with costs
  • Revised program requested from contractor, who
    gave new completion date of May 2010
  • Mar-Dec 2009 senior management tried to find
    solution to incessant delays
  • Dec 2009 NC DRPW terminated contract, subject to
    legal processes
  • The court process and liquidation of the
    contractor
  • Jan 2010 to Oct 2011 contractor repeatedly
    challenged NC DRPW through courts
  • Lengthy delay, with the construction site legally
    under the control of contractor, resulted in
    significant deterioration due to weathering,
    vandalism and theft
  • Oct 2011 contractor was liquidated before court
    could make final ruling
  • Surety or guarantee?
  • 2 (R5 million) of contract value was provided
    through Investec for a period of 24 months
  • 4 (R10.2 million) retention from contract was
    kept by the client after termination
  • Increase of the original contract amount
  • Significant variations in cost caused by
    averaging methodology used to estimate costs at
    outset
  • Design work continued while construction was
    underway
  • R420 million was spent on the initial part of
    this project

5
4. NEW CONTRACTOR
  • Appointment
  • Late 2011 Inyatsi Construction appointed using
    JBCC contract. Site hand-over 21 Dec 2011
  • Contract value R400.57 million for the hospital,
    internal roads and guardhouse, excluding
    professional fees
  • 24-month project - completion Jan 2014
  • Scope of work and latent deficiencies
  • Late 2011 structural reports commissioned to
    estimate remedial work and inform the bill of
    quantities - R6.78 million
  • Jun 2012 sample drilled courses to determine
    concrete strength conducted - two of three passed
    the tests
  • Aug 2012 further strength tests conducted on some
    surface beds and concrete slabs - preliminary
    findings indicate significant variation in
    strength. Load tests conducted - awaiting
    laboratory reports
  • Performance of the new contractor
  • CIDB down-graded contractor from 9GB to 7GB
    during final stages of awarding contract.
  • Advice sought from CIDB on how to proceed 3
    options under consideration, including cancelling
    the contract
  • Contractor already falling behind time schedule,
    monthly expenditure is 50 less than cash flow
    projections

6
5. CLIENT BUDGETARY CONCERNS
  • No capital budget currently available for this
    project - expenditure being paid from budget for
    another Hospital Revitalisation Project
  • Significant and unexpected increase in the
    capital cost of electric sub-station is being
    reviewed
  • Additional costs for prolongation fees not yet
    quantified

7
6. RECOMMENDATIONS
  • Strengthened quality assurance processes
  • Further independent evaluation of integrity of
    structure
  • Establish Joint Management/Consultative Committee
  • Professional service providers to provide reports
    on legacy issues, including architectural
    engineering design, on-site monitoring and
    payments for work done
  • Resident engineer
  • Take necessary actions and agree on contractual
    way forward, including
  • Possible contractual actions
  • Possible legal actions
  • Formulation of improved contract administration
    processes
  • Demolition of inappropriate construction
  • Revision of inappropriate design

8
Thank you
  • Northern Cape Department of Health
  • Northern Cape Department of Roads Public Works
  • supported by
  • National Department of Health (Infrastructure)
Write a Comment
User Comments (0)
About PowerShow.com