Title: Project Management Concepts
1Project Management Concepts
2Project, Defined
- A project is an endeavor to accomplish a specific
objective through a unique set of interrelated
tasks and the effective utilization of resources. - It has a well-defined objective stated in terms
of scope, schedule, and costs. - Project s are born when a need is identified by
the customer the people or organization willing
to provide funds to have the need satisfied. - It is the people (project manager and project
team), not the procedures and techniques, that
are critical to accomplishing the project
objective. - Procedures and techniques are merely tools to
help the people do their jobs.
3Examples of Projects
- Planning a wedding
- Designing and implementing a computer system
- Hosting a holiday party
- Designing and producing a brochure
- Executing an environmental clean-up of a
contaminated site - Holding a high school reunion
- Performing a series of surgeries on an accident
victim
4There is a need
Project is born
Project life cycle (4 phases)
5(No Transcript)
6Phases of the Project Life Cycle 1
- The first phase involves the identification of a
need, problem, or opportunity. - The need and requirements are usually written by
the customer into a document called a request for
proposal (RFP).
7Phases of the Project Life Cycle 2
- The second phase is the development of a proposed
solution to the need or problem. - This phase results in the submission of a
proposal. - The customer and the winning contractor negotiate
and sign a contract (agreement).
8Phases of the Project Life Cycle 3
- The third phase is performing the project.
- Different types of resources are utilized
- Results in the accomplishment of the project
objective
9Phases of the Project Life Cycle 4
- The final phase is terminating the project.
- Perform close-out activities
- Evaluate performance
- Invite customer feedback
10The Project Management Process
- The project management process means planning the
work and then working the plan. - 7 steps of planning
- 1. Clearly define the project objective.
- 2. Divide and subdivide the project scope into
major pieces - 3. Define the specific activities for each piece
(work package) - 4. Graphically portray the activities that need
to be performed fro each work package in order to
accomplish the project objective in the form of
network diagram. - 5. Make a time estimate for how long it will take
to complete each activity resources needed. - 6. Make a cost estimate for each activity.
- 7. Calculate a project schedule and budget to
determine whether the project can be completed
within the required time, with the allotted
founds, and with the available resources.
11Project Control Process
12Work Breakdown Structure (WBS)
- The second step is to determine what activities
need to be performed. - A list of all the activities must be developed.
- The WBS is a hierarchical tree of end items to be
accomplished. - A work item is one small piece of the project.
- A work package is the lowest-level item.
13(No Transcript)
14Microsoft Project WBS
151. Start new project
- Turn on the Project Guide
- On the Tools menu, click Options, and then click
the Interface tab. - In the Project Guide settings section, select the
Display Project Guide check box. - Manually set up a new project
16Project Project Informationor View Turn on
project guide
http//office.microsoft.com/en-us/project/HA102639
631033.aspx
17Tools - Options
18(No Transcript)
192. Tasks
- There are four major types of tasks
- 1. Summary tasks - contain subtasks and their
related properties - 2. Subtasks - are smaller tasks that are a part
of a summary task - 3. Recurring tasks - are tasks that occur at
regular intervals - 4. Milestones - are tasks that are set to zero
duration and are like interim goals in the
project
20Add tasks
21Insert new task
22Outlining tasks
23- Tools Options - check Show project summary
task
24(No Transcript)
25Predecessor
26Tasks can be linked in four ways
- Finish-Start FS Predecessor finishes and the
other starts - Start-Finish S-F Task begins at the same time as
its predecessor - Finish-Finish F-F Both tasks finish at the same
time - Start-Start S-S Start of the predecessor
determines when the other starts
27Constraints
- Certain tasks need to be completed within a
certain date. - Intermediate deadlines may need to be specified.
- By assigning constraints to a task you can
account for scheduling problems. - There are about 8 types of constraints and they
come under the flexible or inflexible category.
28(No Transcript)
293. Managing task
30Defining a Timeline
- Find an optimistic value, D(o),
- a pessimistic value, D(p) and
- a realistic value, D(r) .
- Then Duration ( D(o) D(p) 4 x D(r) ) / 6
31The importance of tracking progress
- Techniques to manage projects effectively
- Critical Path Management (CPM) and
- Program Evaluation and Review Techniques (PERT).
- They are similar and you will now often find the
technique referred to as CPM/PERT. - The technique involves using network models to
trace the links between tasks and to identify the
tasks which are critical to meeting the
deadlines. Once you've identified the critical
path, any delay on any part of the critical path
will cause a delay in the whole project. It is
where managers must concentrate their efforts. - In MS Project, you use the Tracking Gantt diagram
to show the critical path in red and you can see
the PERT diagram by looking at the Network
view.
32Gantt Chart View critical path
- A Gantt chart is a type of bar chart that
illustrates a project schedule. - Critical path View More views - Detail Gant
33PERT diagram - Network view
34Views
- Views allow you to examine your project from
different angles based on what information you
want displayed at any given time. - You can use a combination of views in the same
window at the same time. - Project Views are categorized into two types
- Task Views (5 types)
- Resource Views (3 types)
35Saving a baseline
- Baseline plan The original project plans used to
track progress on a project. - The baseline plan is a snapshot of your schedule
at the time that you save the baseline and
includes information about tasks, resources, and
assignments. - You can set a baseline for your project, enabling
you to compare your progress with the original
plan and any additional baselines you set at
milestones throughout your project.
36Saving a Baseline
- Tools Tracking Save Baseline
http//office.microsoft.com/home/video.aspx?asseti
dES102776241033width1024height768startindex
0CTT11OriginHA102751251033appWINPROJver12
37Resources
38Manage the project resources
- people
- equipment
- supplies
- Resources are of three types
- work resources, material resources and cost
resources. - Work resources complete tasks by expending time
on them. They are usually people and equipment
that have been assigned to work on the project
(you track their participation by the amount of
time they spend). - Material resources are supplies and stocks that
are needed to complete a project. You assign
material resources by the quantity that you need
two tons of gravel or 300 gallons of diesel fuel,
for instance. Because materials aren't measured
by time, quantities usually affect only the cost
of your project. Materials affect dates or
duration only when you have to wait for those
materials to become available. - Cost. Cost resources are the new kid on the
Project 2007 block, and they're strictly cost no
time, no quantitiesjust dollars. Expenses, such
as travel or fees, increase the project price
tag, but they aren't associated with work or
material resources. - You must start by identifying the resources
available along with their costs. - Resource costs will be multiplied by duration to
calculate project costs. - You have to open the Resource sheet to specify
the project resources and costs.
39(No Transcript)
40Fields in the Resource Sheet may be blank or
contain different types of information depending
on the type of resource. For example, a work
resource doesn't have a Material label, and costs
are calculated initially as dollars per hour.
Material resources have a cost per unitper
pound, gallon, or pieceand the Material label
field defines the units. Cost resources receive a
value only when you assign them to tasks.
41(No Transcript)
42(No Transcript)
43Use the Detail Gantt view to find slack (float)
- On the View menu, click More Views.
- In the Views list, click Detail Gantt, and then
click Apply. - On the View menu, point to Table, and then click
Schedule. In the chart portion of the view, slack
appears as thin bars to the right of tasks, with
slack values adjoining the regular Gantt bars.
44(No Transcript)
45To shorten a project schedule
- Reduce duration of activities on critical path
- More resources
- Change their scope
46Technically Constrained Activity Sequence
47Resource-Constrained Planning
48Painting Project Showing Needed Resources
49Create a budget for your project
- Step 1 Create budget resources for your project
- Step 2 Assign the budget resources to the
project summary task - Step 3 Enter values for the budget resources
- Step 4 Categorize resource costs according to
their budget type - Step 5 Group resources to view how they compare
against the budget
50Step 1 Create budget resources for your project
- Create Budget-Travel and Budget-Labor on your
resource sheet
View Resource Sheet
51Check the check box for Budget
52Step 2 Assign the budget resources to the
project summary task
- Gent chart view Tools Options View Tab
Show project summary task (check box) - Task is added to the top of the project list.
Select this task. - Click on Button Assign Resources
- Select the two budget resources you created
earlier and click Assign
53Step 3 Enter values for the budget resources
- View Resource Usage view
- Add Budget Cost and Budget Work fields (columns)
- Insert Column Budget Cost and Budget Work
- Add values for travel and Labor cost
54Add 15,000 for Budget-Travel and 30,000 for
Budget-Labor (Budget Work column)
55Step 4 Categorize resource costs according to
their budget type
- Create custom filed (column)
- Open Resource Sheet view
- Tools Customize Fields
- Choose Resource text filed and rename Budget Type
56Select Option Button Roll down unless manually
entered
Add field to the resource sheet view Insert
column choose Budget Type column ( you can now
identify your resources as labor or travel
57(No Transcript)
58Step 5 Group resources to view how they compare
against the budget
- Resource Usage view
- Project Group by No Group Customize Group
By - Select the Budget Type field
59(No Transcript)
60Viewing Project Cost Information
- Right click the Select All button and click Cost
- Or
- View Table Entry Cost
61Reports
- Cost Report Reports - Reports Costs Cash
Flow - Edit Column list
- Project Summary report Reports Overview
Project Summary
62Resource Usage Report
63Current Activity Reports