Workshop on - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Workshop on

Description:

Most of the projects of Delhi Metro of DMRC have been completed on time and within budget The analysis of the Ministry of Statistics and Programme Implementation ... – PowerPoint PPT presentation

Number of Views:171
Avg rating:3.0/5.0
Slides: 39
Provided by: GME93
Category:
Tags: delhi | metro | workshop

less

Transcript and Presenter's Notes

Title: Workshop on


1
Workshop on Enforcement of Contract Clauses
Timely Recovery on 23-24th February, 2012
TOPIC
Time and Cost Over-run in AAI Projects (Causes
and Solutions)
2
Cost overrun
  • A cost overrun, also known as a cost increase or
    budget overrun, is an unexpected cost incurred in
    excess of a budgeted amount due to an
    under-estimation of the actual cost during
    budgeting.

3
Cost Overrun.
  • Cost overrun is common in infrastructure,
    building, and technology projects. A
    comprehensive study of cost overrun published in
    the Journal of the American Planning Association
    in 2002 found that 9 out of ten construction
    projects had underestimated costs. Overruns of 50
    to one hundred percent were common.

4
Cost escalation
  • Cost overrun should be distinguished from cost
    escalation, which is used to express an
    anticipated growth in a budgeted cost due to
    factors such as inflation.

5
Continu..
  • Professor Bent Flyvbjerg of Oxford University
    believes that big public-works projects almost
    always have cost overruns due to strategic
    misrepresentation"that is, lying", as he defines
    the term.

6
Time Overrun
  • A time overrun, also known as a time increase is
    an unexpected time incurred in excess of a
    estimated/ allocated time.

7
  • Interesting Facts
  • Nine (9) out of Ten (10) infrastructure projects
    fall victim of cost escalation
  • Cost escalation generally varies from 10 to 50
  • Cost escalation exists across twenty (20) Nations
    and five (5) Continents it is a global
    phenomenon. India is NOT an exception.
  • Cost escalation appears to be more pronounced in
    Developing Nations than in Developed Nations
  • Cost escalation has not decreased over the past
    70 years - No learning seems to take place
  • The worst part is that the pattern has not
    changed for the past 90-95 years
  • Bandra-Worli Sea Link cost escalated from Rs.300
    to Rs.1600 Crores with Five (5) years delay
  • Contd..

8
  • Interesting Facts.
  • According to the Economic Survey of India for
    2005-06 till September 2005, of the 683
    infrastructure projects, having an estimated cost
    of Rs.2,81,890/- Crores, spread over 16 sectors,
    171 projects (25) are having cost over runs to
    the tune of 38.87 as compared to their latest
    approved estimates. There are 247 projects (36)
    which have a time over run, ranging from one (1)
    to 168 months.
  • The project that look best on paper have the
    largest cost over run.
  • Public Ownership - Problematic because of
    lengthy/complicated procedures.
  • Private Ownership - Successful in cost
    control due to over simplification.
  • Most of the projects of Delhi Metro of DMRC have
    been completed on time and within budget

9
Cost overrun in Central Public Sectors
  • The analysis of the Ministry of Statistics and
    Programme Implementation shows that cost overrun
    in projects even with respect to the original
    approved cost have come down from 62 in March,
    1991to 12 in March, 2008 and the increased to
    21 in September 2010. This has resulted into
    indirect savings of more than 2,50,000 crore over
    a period of 10 years. This has been possible due
    to the dedicated effort of the infrastructure and
    Project Monitoring Division of MOSPI and

10
  • Other Ministries. The increasing trend of in
    cost overruns in the recent years is mainly due
    to the impact of high increase in the cost bulk
    materials such as cement and steel in 2006-07 and
    recent recession. The trend of cost overruns is
    depicted in the Figure 1.

11
Time overrun in Central Public Sectors
  • The analysis of time overrun in terms of
    percentage of projects running behind their
    original schedule also shows a declining trend.
    Percentage of projects behind schedule declined
    from 62 in 1991 to lowest ever to 31.72 in
    March 2001, to 34.13 in March 2007 and
    increased again to 52.10. The increasing trend
    of percentage of delayed projects is also due to
    the same reasons as in case of cost overruns.
    The projects in the Highway, Power, Petroleum,
    Shipping and Ports, Telecommunication, Steel,
    Fertilizers and Railway sectors suffered the
    most. The trend of percentage of delayed
    projects is depicted in Figure2.

12
Trend of projects running behind schedule w.r.t.
original schedule
13
Project Management Triangle
  • Quality

Scope
Schedule
Cost
14
Project Management Triangle
  • Project constraints have been listed as
    quality," "time," and "cost. These are also
    referred to as the "Project Management Triangle,"
    where each side represents a constraint. One side
    of the triangle cannot be changed without
    affecting the others.

15
Project Management Triangle
  • The time constraint refers to the amount of time
    available to complete a project. The cost
    constraint refers to the budgeted amount
    available for the project. The scope constraint
    refers to what must be done to produce the
    project's end result. These three constraints are
    often competing constraints increased scope
    typically means increased time and increased
    cost, a tight time constraint could mean
    increased costs and reduced scope, and a tight
    budget could mean increased time and reduced
    scope.

16
Status of Projects in AAI as on 31.1.2012
Total Ongoing Projects 52 Annex I II
Projects in Progress within time 0 Annex I II
Projects delayed upto 25 of stipulated time 06 Annex I II
Projects Delayed upto 50 of stipulated time 08 Annex I II
Projects Delayed more than 50 of stipulated time 38 Annex I II
Status of Mega Projects at Kolkata Chennai Airports Annex III
17
STATUS OF ONGOING PROJECTS
Annex-I
Engineering Works
Region Total On-going Projects Projects in progress within time Delay up to 25 of Stipulated time Delay up to 50 of Stipulated time Delay more than 50 of Stipulated time
Northern 06 0 01 01 04
Southern 08 0 02 0 06
Western 7 0 01 02 04
Eastern 11 0 01 03 07
North-Eastern 03 0 - - 03
TOTAL 35 0 05 06 24
18
Annex-II
STATUS OF ONGOING PROJECTS
CNS Works
Region Total On-going Projects Projects in progress within time Delay up to 25 of Stipulated time Delay up to 50 of Stipulated time Delay more than 50 of Stipulated time
All Regions 17 0 01 02 14
19
Annex-III
STATUS OF MEGA PROJECTS AT KOLKATA CHENNAI
PARAMETER Kolkata Airport Chennai Airport
Estimated Cost (Crs.) 1602.61 1808.00
Stipulated Date of Completion 05.05.2011 23.01.2011
Present Physical Progress 93 96.5
Delay already occurred 33 54
20
A CAUSES OF TIME COST OVERRUN
  • I Preparation of Faulty Estimates
  • - Inadequate site condition survey/data for
    finalizing Scope of Work
  • - Improper Design Drawings
  • - Unrealistic Time Period fixed for Completion
  • - User Consultation Process not done.

21
CAUSES OF
  • Preparation of Faulty estimate (Contd)
  • - Rates not based on actual market rates
  • - Narrow range of approved makes
  • - Non- consideration of rehabilitation of
    existing
  • structure/services at the time of planning
  • - Factors of insurgency / disturbed area

22
CAUSES OF
  • II Delay in applying/issuing of NOC / clearance
    from statutory authorities
  • III Delay in Environmental Clearance
  • IV Non-availability of complete land/site free
    from encumbrances

23
CAUSES OF
  • V Selection of consultant contract agencies
  • - Selection without assessing Technical
    Financial capability
  • - Lack of experience in similar nature
    of work

24
CAUSES OF
  • VI Delay in issue of working design drawings
  • VII Delay in issue of NOTAM indicative of
    prior lack of coordination
  • VIII Frequent changes in scope of work, drawings
    specifications

25
CAUSES OF
IX Delay in rehabilitation of existing
structures / services X Non-availability of
construction material (points to inadequate site
survey resulting into costly substitution at a
later date) XI Incomplete/Improper nomenclature
of items in contract agreement
26
CAUSES OF
  • XII Lack of co-ordination amongst the various
    disciplines and other airport functionaries
  • XIII Inadequate monitoring system

27
B SOLUTIONS
  • Estimate should be based on actual site data
    /drawings
  • Scope of work should be well defined finalized
    in consultation with user Agencies
  • 3. Presumptions should be minimized

28
SOLUTIONS..
  • 4. Realistic time frame to be kept
  • 5. Proper Market Survey for estimates
  • 6. Proprietary / Imported items should be
    minimized.
  • 7. Timely action for statutory clearances

29
SOLUTIONS..
  • 8. Technical Sanctioning Authority to ensure
  • availability of land
  • 9. Advance / timely actions for diversion of
    services/obstructions relocation of structures
    etc.
  • 10. Proper Selection of Consultant Contract
  • agency

30
SOLUTIONS..
  • 11. Regular monitoring of performance of
    consultants/contract agency
  • 12. Yearly performance evaluation mechanism for
    timely action to weed out non- performing
    contract agencies/consultants
  • 13. Timely issuance of working drawings

31
SOLUTIONS..
  • 14. Proper co-ordination among the disciplines
    other airport functionaries
  • 15. Penalty Clause for deficiency in services of
    Consultant/Contract Agency
  • 16. Timely decisions/ approvals / sanctions
  • regular monitoring of Projects

32
C ACTIONS REQUIRED / TAKEN IN AAI
  • 1. Advance actions to remove hindrances,
    structures, diversion of services coming in the
    alignment of the project structures
  • 2. Clear and well defined scope of work vetted
    by all stakeholder departments within AAI
  • 3. Dedicated and independent PMQA cell to
    monitor progress of work.

33
ACTIONS ..
  • 4. Web enabled project monitoring software
    being put into place
  • 5. Delegation of power is decentralized with
    accountability
  • 6. Project In-charge to monitor slippages in
    targets.

34
  • The GOAL can be achieved if we have WILL,
    COMMITMENT, DEDICATION AND PASSION to feel the
    need and purpose.

35
Workshop on Enforcement of Contract Clauses and
Timely Recovery
  • Important tips for effective contract management
  • Immediately on receipt of letter of acceptance,
    open site order book.
  • Hand over the site. This is important, since
    time allowed in contract for execution of work
    commences from 10th day after the date on which
    the Engineer-in-Charge issues written orders to
    commence the work.
  • If handing over site is made in phases. Please
    make an entry in site order book to the extent
    site handed over.

36
  • In accordance with clause 13, insist time
    progress chart from the contractor.
  • Closely monitor the progress made. Compare the
    progress achieved in relation to clause 13.1 of
    contract. This clause envisage progress of work
    with relation to time lapsed.
  • In case, there is backlog in the progress,
    promptly issue a diligence notice. The notice
    should highlight the slippages.

37
Workshop on Enforcement of Contract Clauses and
Timely Recovery.
  • Clause 32 of contract envisages compensation for
    delay. This clause stipulate that the
    contractor, if failed to maintain the required
    progress (as agreed), they are liable to pay
    compensation . Hence, diligence notice should
    invariably notify the intended action for breach
    caused.
  • Closely watch the progress at the portion of
    site handed over.
  • Read the contract thoroughly.
  • Take timely decision.

38
THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com