Title: Workshop on
1Workshop on Enforcement of Contract Clauses
Timely Recovery on 23-24th February, 2012
TOPIC
Time and Cost Over-run in AAI Projects (Causes
and Solutions)
2Cost overrun
- A cost overrun, also known as a cost increase or
budget overrun, is an unexpected cost incurred in
excess of a budgeted amount due to an
under-estimation of the actual cost during
budgeting.
3Cost Overrun.
- Cost overrun is common in infrastructure,
building, and technology projects. A
comprehensive study of cost overrun published in
the Journal of the American Planning Association
in 2002 found that 9 out of ten construction
projects had underestimated costs. Overruns of 50
to one hundred percent were common.
4Cost escalation
- Cost overrun should be distinguished from cost
escalation, which is used to express an
anticipated growth in a budgeted cost due to
factors such as inflation.
5Continu..
- Professor Bent Flyvbjerg of Oxford University
believes that big public-works projects almost
always have cost overruns due to strategic
misrepresentation"that is, lying", as he defines
the term.
6Time Overrun
- A time overrun, also known as a time increase is
an unexpected time incurred in excess of a
estimated/ allocated time.
7- Interesting Facts
- Nine (9) out of Ten (10) infrastructure projects
fall victim of cost escalation - Cost escalation generally varies from 10 to 50
- Cost escalation exists across twenty (20) Nations
and five (5) Continents it is a global
phenomenon. India is NOT an exception. - Cost escalation appears to be more pronounced in
Developing Nations than in Developed Nations - Cost escalation has not decreased over the past
70 years - No learning seems to take place - The worst part is that the pattern has not
changed for the past 90-95 years - Bandra-Worli Sea Link cost escalated from Rs.300
to Rs.1600 Crores with Five (5) years delay -
- Contd..
8- Interesting Facts.
- According to the Economic Survey of India for
2005-06 till September 2005, of the 683
infrastructure projects, having an estimated cost
of Rs.2,81,890/- Crores, spread over 16 sectors,
171 projects (25) are having cost over runs to
the tune of 38.87 as compared to their latest
approved estimates. There are 247 projects (36)
which have a time over run, ranging from one (1)
to 168 months. - The project that look best on paper have the
largest cost over run. - Public Ownership - Problematic because of
lengthy/complicated procedures. - Private Ownership - Successful in cost
control due to over simplification. - Most of the projects of Delhi Metro of DMRC have
been completed on time and within budget
9Cost overrun in Central Public Sectors
- The analysis of the Ministry of Statistics and
Programme Implementation shows that cost overrun
in projects even with respect to the original
approved cost have come down from 62 in March,
1991to 12 in March, 2008 and the increased to
21 in September 2010. This has resulted into
indirect savings of more than 2,50,000 crore over
a period of 10 years. This has been possible due
to the dedicated effort of the infrastructure and
Project Monitoring Division of MOSPI and
10- Other Ministries. The increasing trend of in
cost overruns in the recent years is mainly due
to the impact of high increase in the cost bulk
materials such as cement and steel in 2006-07 and
recent recession. The trend of cost overruns is
depicted in the Figure 1.
11Time overrun in Central Public Sectors
- The analysis of time overrun in terms of
percentage of projects running behind their
original schedule also shows a declining trend.
Percentage of projects behind schedule declined
from 62 in 1991 to lowest ever to 31.72 in
March 2001, to 34.13 in March 2007 and
increased again to 52.10. The increasing trend
of percentage of delayed projects is also due to
the same reasons as in case of cost overruns.
The projects in the Highway, Power, Petroleum,
Shipping and Ports, Telecommunication, Steel,
Fertilizers and Railway sectors suffered the
most. The trend of percentage of delayed
projects is depicted in Figure2.
12Trend of projects running behind schedule w.r.t.
original schedule
13Project Management Triangle
Scope
Schedule
Cost
14Project Management Triangle
- Project constraints have been listed as
quality," "time," and "cost. These are also
referred to as the "Project Management Triangle,"
where each side represents a constraint. One side
of the triangle cannot be changed without
affecting the others.
15Project Management Triangle
- The time constraint refers to the amount of time
available to complete a project. The cost
constraint refers to the budgeted amount
available for the project. The scope constraint
refers to what must be done to produce the
project's end result. These three constraints are
often competing constraints increased scope
typically means increased time and increased
cost, a tight time constraint could mean
increased costs and reduced scope, and a tight
budget could mean increased time and reduced
scope.
16Status of Projects in AAI as on 31.1.2012
Total Ongoing Projects 52 Annex I II
Projects in Progress within time 0 Annex I II
Projects delayed upto 25 of stipulated time 06 Annex I II
Projects Delayed upto 50 of stipulated time 08 Annex I II
Projects Delayed more than 50 of stipulated time 38 Annex I II
Status of Mega Projects at Kolkata Chennai Airports Annex III
17STATUS OF ONGOING PROJECTS
Annex-I
Engineering Works
Region Total On-going Projects Projects in progress within time Delay up to 25 of Stipulated time Delay up to 50 of Stipulated time Delay more than 50 of Stipulated time
Northern 06 0 01 01 04
Southern 08 0 02 0 06
Western 7 0 01 02 04
Eastern 11 0 01 03 07
North-Eastern 03 0 - - 03
TOTAL 35 0 05 06 24
18Annex-II
STATUS OF ONGOING PROJECTS
CNS Works
Region Total On-going Projects Projects in progress within time Delay up to 25 of Stipulated time Delay up to 50 of Stipulated time Delay more than 50 of Stipulated time
All Regions 17 0 01 02 14
19Annex-III
STATUS OF MEGA PROJECTS AT KOLKATA CHENNAI
PARAMETER Kolkata Airport Chennai Airport
Estimated Cost (Crs.) 1602.61 1808.00
Stipulated Date of Completion 05.05.2011 23.01.2011
Present Physical Progress 93 96.5
Delay already occurred 33 54
20A CAUSES OF TIME COST OVERRUN
- I Preparation of Faulty Estimates
- - Inadequate site condition survey/data for
finalizing Scope of Work - - Improper Design Drawings
- - Unrealistic Time Period fixed for Completion
- - User Consultation Process not done.
21CAUSES OF
- Preparation of Faulty estimate (Contd)
- - Rates not based on actual market rates
- - Narrow range of approved makes
- - Non- consideration of rehabilitation of
existing - structure/services at the time of planning
- - Factors of insurgency / disturbed area
22CAUSES OF
- II Delay in applying/issuing of NOC / clearance
from statutory authorities - III Delay in Environmental Clearance
- IV Non-availability of complete land/site free
from encumbrances
23CAUSES OF
- V Selection of consultant contract agencies
- - Selection without assessing Technical
Financial capability - - Lack of experience in similar nature
of work
24CAUSES OF
- VI Delay in issue of working design drawings
- VII Delay in issue of NOTAM indicative of
prior lack of coordination - VIII Frequent changes in scope of work, drawings
specifications
25CAUSES OF
IX Delay in rehabilitation of existing
structures / services X Non-availability of
construction material (points to inadequate site
survey resulting into costly substitution at a
later date) XI Incomplete/Improper nomenclature
of items in contract agreement
26CAUSES OF
- XII Lack of co-ordination amongst the various
disciplines and other airport functionaries - XIII Inadequate monitoring system
27B SOLUTIONS
- Estimate should be based on actual site data
/drawings - Scope of work should be well defined finalized
in consultation with user Agencies - 3. Presumptions should be minimized
28SOLUTIONS..
- 4. Realistic time frame to be kept
- 5. Proper Market Survey for estimates
- 6. Proprietary / Imported items should be
minimized. - 7. Timely action for statutory clearances
29SOLUTIONS..
- 8. Technical Sanctioning Authority to ensure
- availability of land
- 9. Advance / timely actions for diversion of
services/obstructions relocation of structures
etc. - 10. Proper Selection of Consultant Contract
- agency
30SOLUTIONS..
- 11. Regular monitoring of performance of
consultants/contract agency - 12. Yearly performance evaluation mechanism for
timely action to weed out non- performing
contract agencies/consultants - 13. Timely issuance of working drawings
31SOLUTIONS..
- 14. Proper co-ordination among the disciplines
other airport functionaries - 15. Penalty Clause for deficiency in services of
Consultant/Contract Agency - 16. Timely decisions/ approvals / sanctions
- regular monitoring of Projects
32C ACTIONS REQUIRED / TAKEN IN AAI
- 1. Advance actions to remove hindrances,
structures, diversion of services coming in the
alignment of the project structures - 2. Clear and well defined scope of work vetted
by all stakeholder departments within AAI - 3. Dedicated and independent PMQA cell to
monitor progress of work.
33ACTIONS ..
-
- 4. Web enabled project monitoring software
being put into place - 5. Delegation of power is decentralized with
accountability - 6. Project In-charge to monitor slippages in
targets.
34- The GOAL can be achieved if we have WILL,
COMMITMENT, DEDICATION AND PASSION to feel the
need and purpose.
35Workshop on Enforcement of Contract Clauses and
Timely Recovery
- Important tips for effective contract management
- Immediately on receipt of letter of acceptance,
open site order book. - Hand over the site. This is important, since
time allowed in contract for execution of work
commences from 10th day after the date on which
the Engineer-in-Charge issues written orders to
commence the work. - If handing over site is made in phases. Please
make an entry in site order book to the extent
site handed over.
36- In accordance with clause 13, insist time
progress chart from the contractor. - Closely monitor the progress made. Compare the
progress achieved in relation to clause 13.1 of
contract. This clause envisage progress of work
with relation to time lapsed. - In case, there is backlog in the progress,
promptly issue a diligence notice. The notice
should highlight the slippages.
37Workshop on Enforcement of Contract Clauses and
Timely Recovery.
- Clause 32 of contract envisages compensation for
delay. This clause stipulate that the
contractor, if failed to maintain the required
progress (as agreed), they are liable to pay
compensation . Hence, diligence notice should
invariably notify the intended action for breach
caused. - Closely watch the progress at the portion of
site handed over. - Read the contract thoroughly.
- Take timely decision.
-
38THANK YOU