Title: RF%20System%20Improvements%20for%20Performance%20and%20Reliability
1RF System Improvements for Performance and
Reliability
- Dan Van Winkle
- Kirk Bertsche, John Fox, Themis Mastorides,
Claudio Rivetta, Heinz Schwarz
2Brief Outline
- Current performance and future plans
- Brief RF System Review
- What keeps us up at night
- Longitudinal Growth Rates
- Aborts
- General ongoing global issues
- Conclusions and Outlook
3- Current and Planed Performance
4Current performance and future plans
- Run 6 Parameters (max achieved)
- LER HER
- Beam Current 3.026 (1.4X) 1.96 A (2X)
- RF Voltage 4.05 16.5 MV
- Cavities 8 28
- Klystrons 4 11 (1.8X)
- Voltage/Cav 506 590 kV
- Klystron Pwr 755.1 845.9kW
5Current performance and future plans
- Run 7 Parameters (max planned)
- LER HER
- Beam Current 4.00 (1.9X) 2.2 A (2.2X)
- RF Voltage 5 17.5 MV
- Cavities 8 28
- Klystrons 4 11 (1.8X)
- Voltage/Cav 625 625 kV
- Klystron Pwr 1005 980 kW
6- Brief Overview of PEP-II RF System
7The PEP-II LLRF
STATION REF (EPICS)
SAT LOOP
476 MHz REF
Gap Loop
STATION REF (EPICS)
HVPS
RF CAV
TUNER LOOP
Klystron
IQ MOD
120W Driver
-
-
IQ DEMOD
DIRECTLOOP
- 15 Stations
- 4 LER
- 11 HER
- 8 Cavities LER
- 28 Cavities HER
BEAM
Slow Loop (EPICS)
COMB LOOP
Fast Loop (Electronics)
476 MHz
Baseband
8The PEP-II LLRF
LLRF VXI Crate
1.2 MW Klystron
Fast Interlock Chassis
120W Klystron Pre-Amplifier
Temperature Controlled LLRF Blue Box
9- Insomnia Producing Problems
10What Keeps us up at Night
- Longitudinal Growth Rates
- Grow Damp measurements in 2003 showed 5-10X
greater growth rates than predicted by a linear
model.
11Longitudinal Growth Rates
- Previous MAC talks have addressed various ideas
weve tried which include - Non-Linear Modeling Effort (Claudio Rivetta Talk)
- Klystron Linearizer (MAC Oct 06 Talk)
- Klystron Pre-Amplifiers (MAC Oct 06 Talk
Preliminary)
12Solution Flow Diagram
High Growth Rates Observed
Linearizer Project
Non-linear Model
Comb Rotation
Pre-amp Evaluation
New Pre-Amps
Reduced Growth Rates Observed
13Longitudinal Growth Rates
- Today, Ill Discuss
- Progress since last MAC on
- Identifying key parameters and measurements for
replacement amplifiers - Progress on purchasing and replacement
- Results of new installations
14- Pre-Amplifier Specification and Measurements
15Klystron Pre-Amplifiers
Swept Low Level Carrier
Small (network analyzer swept) signal injected
along with large carrier to simulate small signal
modulation on CW carrier
Full Power Carrier
16Klystron Pre-Amplifiers
Unusual (distorted) response seen when carrier is
present Since we use the amplifier with carrier
and small signal modulation, the modulation
sees this response rather than the flat
(desirable) response.
17Klystron Pre-Amplifiers
- Old Data showed LR4-2, HR12-2 and HR12-6 were
especially bad in small signal response
18Klystron Pre-Amplifiers
- LR4-2 Distortion affected ability to implement
comb rotation
LR42 was nearly unstable with 20 degrees of comb
rotation. Simulations show this is due to
non-linear pre-amplifier response.
19Klystron Pre-Amplifiers
Non-linear distortion is also a key parameter of
these amplifiers. Rather than use two large
tones as is typically done in a TOI measurement,
we decided to try a new technique similar to our
network analyzer technique. Namely, a small
signal in the presence of a large signal.
20Klystron Pre-Amplifiers
21Klystron Pre-Amplifiers
22Klystron Pre-Amplifiers
In this case, AmpC was a class A amplifier
powered off 240V AC. Amp B was a class AB
amplifier powered of 120V. We chose amp B based
upon good enough performance and much less
expensive price
23- New Pre-Amp Performance In Station
24Klystron Pre-Amplifiers
STATION REF (EPICS)
476 MHz REF
IQ DEMOD
Gap Loop
ADC
RF CAV
Klystron
IQ MOD
120W Driver
-
-
IQ DEMOD
DIRECTLOOP
DAC
BEAM
COMB LOOP
Built in stimulus driver allows for unique
in-situ measurements
25Klystron Pre-Amplifiers
- New Amps installed in all stations
26Klystron Pre-Amplifiers
27Klystron Pre-Ampliers
- Since Last October
- Significant Time spent characterizing and
specifying amplifiers in a new way. - Found Vendor who met specs
- Bought 17 and installed 15 new pre-amplifiers
- Amplifiers show much improved response and allow
for 20 degrees of comb filter rotation
28Longitudinal Growth Rates
- Conclusions
- We now feel system is prepared to move to higher
current realms in terms of longitudinal growth
rates - Further work may include
- Asymmetric Combs
- RFP asymmetry calibrations
29What else keeps us up?
- Aborts
- Biggest Contributors are cavity arcs during
startup after down (Heinz S.) - We also had many issues with the HVPS systems
(things breaking) - Things we plan to work on are
- PGE Power Dips (55 Aborts during run 6)
- LR4-4 Drive Glitches (41 Aborts during run 6)
30HVPS Dips
31Whats Going On?
Constant Running
Swing Required of 5W to keep output constant at
900 kW
Power can not reach 900 kW and goes over the top
For 77 kV _at_ 900 kW Output, 24 W Input
For 77.5 kV _at_ 900 kW Output, 22 W Input
For 76.5 kV _at_ 900 kW Output, 27 W Input
32HVPS Dips
- What to do?
- Lower drive power on Klystron
- Upside
- Allows for greater head room
- More linear running
- Downside
- Cant reach as high power
- Higher Collector Power
33HVPS Dips
- Since these dips appear to be coming from PGE,
there is very little we can do locally to
mitigate them. - Constant monitoring of drive set-points will be
required - For peak currents, we may need to live with the
occasional power dip abort
34LR4-4 Drive Dips
- Ongoing problem since 2005
- AIM HVPS monitor shows noise burst
- Followed by Klystron Forward wiggle
- Followed by very short dropout in drive signal
- Followed by beam abort
35LR4-4 Drive Drop
- Drive mysteriously drops (or rises)
- Cavity responds after delay
36LR4-4 Drive Dips
- Things Tried so far
- Replaced several modules (not well controlled
study) - Moved drive set point
- Low trip rate and missing measurement points
makes this difficult to diagnose - Plans
- New klystron being installed. Will let run for
some time to see if this makes any difference
(not likely) - Begin plan for swapping various modules. Likely
culprits are gap module and RFP module. Will
start with one then wait 2-3 weeks, then swap
another. - Extra Monitoring on HVPS signals to attempt to
understand mysterious HVPS noise burst - More plans to be developed in LLRF ongoing
meetings. This will become high priority.
37 38General Ongoing Issues
- Cavity Tuning Polynomials
- Polynomial fits for cavity de-tuning vary with
temperature - Occasionally cavity temperatures have been varied
without concern for these polynomials (RF experts
not notified) - Net result is constant tuning of RF stations as
current is pushed. - Machine seems to run better after stations are
given tune cavities and make polynomials tune
ups. - This process take time without beam so
administration is reluctant to do except when
necessary
39General Ongoing Issues
- Cavity Tuning Polynomials
- We are working on scheme to make this process
run-able by operators. - Process must be bullet proof
- Will remind operators to run at opportunistic
times when we are without beam for 30 minutes
40 41Summary and Conclusions
- Much progress has been made over the last 3-5
years in improving the reliability and
performance of the PEP-II RF systems. Some
highlights are - Re-designed RFP modules
- Re-designed IQA modules
- Fixed Stuck Tuner Problem
- Better temperature control on blue boxes
- Designed new R2 COMB Module (reduced two VXI
modules to one) - New pre-amplifiers
- Comb rotation for better beam stability
- Filters on RE signals
- Non-linear modeling for low order model
longitudinal damping improvement - Low Group Delay Woofer for increase low order
mode damping - Gage Board diagnostics for transverse and
longitudinal troubleshooting - Matlab GUIs for fault files
- Matlab GUIs for tune cavities and make
polynomials - RF training for operators
- Model based RF station tuning
- AIM module diagnostics of HVPS signals
- SLAC Klystrons in most stations
42Summary and Conclusions
- The PEP-II RF system is running relatively well
(2.5 aborts per day) considering the complexity
of the overall system. - This rate is still too high, but there will be
difficulties in reducing this rate due to the
lack of big ticket aborts to go after. - We will (of course) continue working on these
issues to the last day of running.
43Summary and Conclusions
- Finally
- Running at the highest currents will require
constant vigilance - If we lose a station, we WILL NOT be able to
continue running at full current
44Acknowledgements
- Technical Review and Discussions
- Dmitry Teytelman, Mike Browne, John Dusatko, Jim
Sebek, Ron Akre, Vojtech Pacak, Alan Hill, Kirk
Bertsche - Original Concept and Design
- Paul Corredoura, Rich Tighe and Flemming
Pedersen - Support and Permission
- Uli Wienands, John Seeman, Mike Sullivan
- All this work was done under contract
DE-AC02-76SF00515 from the U.S. Department of
Energy
45The PEP-II RF TEAM
- High Power RF
- Alan Hill, Heinz Schwarz, Vojtech Pack, Al Owens,
Ron Akre - Accelerator Research Department
- John Fox, Claudio Rivetta,
- Controls Department
- Mike Browne, John Dusatko, David Brown, Bill Ross
- High Voltage
- Marc Larrus, Dick Cassel, Paul Bellomo, Serge
Ratkovsky - Control Software
- Mike Laznovsky
- Accelerator Dept
- Mike Sullivan, Uli Wienands, William Colocho,
Franz-Josef Decker, Alan Fisher, Stan Ecklund,
Mat Boyes, Kirk Bertsche - Management
46References
- Dan Van Winkle MAC 06 Talk
- http//www.slac.stanford.edu/dandvan/mac_1006_dvw
R3.ppt - Dan Van Winkle MAC 04 Talk
- http//www.slac.stanford.edu/dandvan/MAC_12_04.pp
t - Dan Van Winkle Internal Linearizer Review
- http//www.slac.stanford.edu/dandvan/project_revi
ew_3_08_06.ppt - Claudio Rivetta et al PRST Longitudinal
Simulation Paper - http//prst-ab.aps.org/pdf/PRSTAB/v10/i2/e022801
- Dan Van Winkle - EPAC 06 Klystron Linearizer
- http//www.slac.stanford.edu/pubs/slacpubs/11750/s
lac-pub-11945.pdf - John Fox RF Amplifier Selection PAC 07
- http//www.slac.stanford.edu/pubs/slacpubs/12500/s
lac-pub-12636.pdf - Dan Van Winkle LLRF Workshop 2007 Invited Talk
- http//www/dandvan/llrf07.ppt