Title: I. Vasserman
1LCLS First Undulator Prototype Magnetic
Measurements
2Outline
- Magnetic measurements key measurements and
issues - Mechanical stability
- Temperature effects
- End phasing
- Summary
3Critical Tolerances (per undulator section
undulator and quadrupole)/Achieved
Trajectory walk-off ?x?, y 2?m 0.5?m
A/A0 1 2 0.1
?-2?n 10 deg
?y 50?m
Complex Amplitude of Radiation
Phase slippage over the length of one undulator
section
4Magnetic Measurements (key measurements and
issues)
- Coil measurements
- Moving coil used as reference (especially for
horizontal field) - Field integrals (no multipole components)
- Hall probe measurements
- Both vertical and horizontal field
- Fixed gap
- Easier to tune field integrals and phase errors
(no gap dependence) - Small gap ( 6.4 mm)
- Shimming more complicated
5Magnetic Measurements (key measurements and
issues), continued
- High magnetic field stability
- Very precise measurements needed
- Reproducibility of measurements must be ltlt
required precision of the field ?Beff/Beff 1.5
x 10-4 ( 2 Gauss 1 µm gap change) - Earth field 0.15 Gauss --gt 2.0 µm trajectory
offset (requirement) - Obtaining the exact field is a challenge
- To obtain the real trajectory environmental
field in the tunnel has to be taken into account
6Hall Probe Horizontal Field Measurements
- Test of Hall probe horizontal field measurements
using Sentron Hall probe done for Undulator A in
1998 showed good agreement with moving coil
reference measurements. It means that planar Hall
probe effect and cross talk between two sensors
is not so big - LCLS undulator is longer by 1 m and has stronger
vertical field that exaggerates the errors of
measurements. A test was done to check the
horizontal field readings of a Sentron probe in
presence of vertical field - Results show that for small perturbations and
small horizontal field this probe could be used
for tuning but final trajectory measurements
should be compared with reference done by moving
coil
7Horizontal Field Nonlinearity vs. Vertical Field
- Measurements done with 2-axis probe in
calibration magnet - The angle ? 1 degree was introduced to have X-
component of - magnetic field
- BxBy ?
- Hall probe sensitivity 5V/T
- Cross talk is evident
- BxBy ?
8Table II. Magnetic Measurement Parameters
achieved
- Absolute Hall probe
- calibration accuracy 0.5 Gauss
- Reproducibility
- - Particle beam angle at exit
- and entrance 2.5 G-cm/0.001 mrad
- - Displacement at exit and
- entrance 3400 G-cm/ 0.0004 mm
- - Beff RMS error 0.15 Gauss
- - Phase error 0.02 degree
9Shimming
- Novel trajectory shims
- Phase shims
- Mechanical shims
10Shims .phase (flat) and trajectory (side)
Both types of shims
Trajectory shims
11Temperature Dependence
- Accurate measurements of temperature dependence
of Beff need to take into account temperature
dependence of Hall probe - Temperature dependence of recent Hall probes
typically lt10-4 / C? - Two of three Sentron probes (S/N 157 and 367 at
APS) have temperature dependence close to
specified - Result of calibration for third Hall probe (S/N
409 using the APS calibration magnet) shows large
deviation from vendor data - (?Beff/Beff)/?T appears to be 3.0 x 10-5 /?C if
Hall probe temperature dependence is neglected
(one calibration file is used) - (?Beff/Beff)/?T -5.5 x 10-4 /?C when Hall
temperature dependence is taken into account - ?T 0.3 ?C will result in ?Beff/Beff
requirement of 1.5 x 10-4) - Undulator end-phase corrections will relax the
temperature stability requirement
12Hall Probe Temperature Calibration
Coefficient 1.0021 was applied to the curve of
26.85 deg to coincide with 23.2 degree The shape
is close and one coefficient could be used for
each temperature
13Time for undulator to reach thermal equilibrium
- Temperature response at downstream (D/S) and
upstream (U/S) end of prototype core and nearby
air in the magnetic measurement laboratory
It takes one hour to stabilize the room
temperature More than 24 hrs is needed for
titanium core
14Mechanical Stability
- The prototype was removed from the bench and
moved twice around APS storage ring. - Prototype was aligned and measured at the bench
before and after being moved
Beff (Gauss) rms (Gauss) of Beff
Before move (23.5 ?C) 13724.7 0.1
After move (23.6 ?C) 13724.3 0.22
15Undulator End Phasing
- Full range is 0.1 mm
- Implemented into the design
- Sensitivity to field deviations from one
undulator section to the next can be made lower
by using the end-gap correction system - Remotely controlled at the sub-micron level
PZT translator located at the end of the
undulator to adjust the magnetic gap of the end
section. This adjusts the phasing between
undulators
16Undulator End Phasing (contd)
- End-phase corrections effect on the FEL
performance - Calculations of complex amplitude of radiation
amplitude - Simulations of beam bunching using code RON
- Measured phase versus end-gap change
- - Full range for one end 0.100 mm is
0.16 period 29
17Undulator End Phasing (contd) Complex Amplitude
of Radiation
- Complex amplitude of radiation, A(L) defines
the intensity of radiation and is almost 100
compared to ideal case - Ideal case
- Regular part of the device cosine-type field
distribution versus z - Ends from measured data
- Measured slippage length for 113 periods of phase
was 3.668 m at 6.35 mm gap (K value of 3.729) - With two devices in a row, an error of 7x10-4 in
?Beff/Beff of the second device could be
corrected by applying an end-phase correction of
24.5 from both ends of the device - Complemented by detailed RON simulations (R.
Dejus) using random uniform distribution of Keff
an error of up to 10x10-4 could be compensated
by end phase correction
18Undulator End Phasing (contd) Complex Amplitude
of Radiation
- Absolute value of complex amplitude of radiation
versus z for two devices - Second device field changed by 7x10-4
- Phase correction of 24.5 applied
Correcting phase of upstream end of 2nd undulator
is important for maximizing length of vector
(absolute value of radiation amplitude)
19Undulator End Phasing (contd) RON Simulations
- ?Beff/Beff variation from undulator to undulator
for 33 undulators with and without end-phase
corrections _at_ 1.2 mm-mrad and 1.5 ?
Curves from top to bottom 1. Ideal case 2-4
with corrections 5-7 no corrections
20Conclusions
- Measurements and tuning were done
- The prototype met all stringent mechanical and
magnetic tolerances after a few design changes
and magnetic tuning - Tuning time is about two days after the exact
effective field is set - Setting of exact effective field with accuracy
better than 1.5x10-4 is a challenge - End-phase corrections of 29 total range allows
compensation of ?Beff/ Beff of 8.2x10-4 or
1.5C - Lessons learned to simplify production
- - The biggest source of errors is variation
of pole heights on assembled device. The
tolerances for 1st prototype were 0.05 mm - Do not need to measure individual magnet blocks
in the half-period fixture with Hall probe with
such pole height errors - Mechanical tolerances of 0.025mm for gap
uniformity will facilitate the tuning