Title: G-2 Cryogenic System


1
G-2 Cryogenic System
2
Maintenance Items
  • Readily defendable
  • Refurbish expansion engine
  • Cost basis previous expansion engine
    refurbishment
  • Spare parts for expansion engine
  • Cost basis- previously purchased parts
  • Recertify relief valves
  • Cost basis RHIC relief valve recertification
  • Compressor maintenance
  • Cost basis -estimate from compressor manufacturer
  • Replace polyflow tubing
  • Cost basis- known tubing cost
  • Replace valve positioners
  • Cost basis valve positioners purchased for RHIC
  • Flow controllers on power leads
  • Cost basis flow controllers purchased for RHIC

3
Modifications/Upgrades
  • Fix Known Helium Leaks
  • How far from being defendable?
  • Need to review system leaks and determine
    difficulty in locating/fixing them
  • Time and Effort needed to make it defendable
  • 1 engineering man week
  • 1 technician man week
  • Reexamine Coalescers for potential oil carryover
  • How far from being defendable?
  • Size and cost charcoal adsorbent system
  • Time and Effort needed to make it defendable
  • 4 engineering man days
  • Revamp heat shield LN2 system
  • How far from being defendable?
  • Need to size new valves to make accurate cost
    estimate
  • Time and Effort needed to make it defendable
  • 2 Engineering man days

4
Modifications/Upgrades
  • Gas purification equipment
  • How far from being defendable?
  • Need to size purification equipment
  • Get preliminary quote
  • Determine how it integrates into the G-2
    cryogenic system
  • Time and Effort needed to make it defendable
  • 1 engineering man week
  • Smaller heat shield valve on Inflector
  • How far from being defendable?
  • Need to size valve
  • Need to get price quote
  • Time and Effort needed to make it defendable
  • 1 Engineering man day
  • Revamp Magnet Warmup System
  • How far from being defendable?
  • Need to determine warmup system design
  • Size valves and components to get

5
Refrigerator Operations
  • Oil in G-2 Refrigerator
  • The G-2 refrigerator ran at a higher average
    temperature last run
  • Unclear as to what extent oil has permeated the
    G-2 Refrigerator
  • 3 man weeks of engineering
  • 3 man weeks of technician time
  • Using SSC Plan B refrigerator
  • Need to quantify G-2 Heat load
  • Need to estimate mount effort to get plan B
    refrigerator operational
  • Determine amount effort needed to integrate the
    refrigerator into the G-2 system
  • 1 man month of engineering