Status of the Powering Interlock system - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Status of the Powering Interlock system

Description:

Title: Slide 1 Author: russ Last modified by: puccio Created Date: 3/24/2004 6:22:33 PM Document presentation format: On-screen Show Company: CERN Other titles – PowerPoint PPT presentation

Number of Views:73
Avg rating:3.0/5.0
Slides: 10
Provided by: russ2156
Category:

less

Transcript and Presenter's Notes

Title: Status of the Powering Interlock system


1
Status of the Powering Interlock system
  • Markus Zerlauth Bruno Puccio
  • AB-CO-IN

2
Architecture
LHC Ref DB
PVSS Operator Console (in the Field Control Room
or CCC )
Ethernet Technical Network

PLC in non-radiation area
PIC
Profibus
Power Converter
Power Converter
QPS
PC_PERMIT
Power Converter
QPS
Power Converter
QPS
QPS
CIRCUIT_QUENCH
PC_FAST_ABORT
Remote I/O (close to clients)
POWERING_FAILURE

DISCHARGE_ REQUEST
PC_DISCHARGE_ REQUEST
ABORT
UPS
Beam Permit
Beam Interlock sys.
AUG
3
36 PICs for 28 Powering Subsectors, managing
1600 electrical circuits, using more than 1000
cables, handling 2400 interlock signals
4
PIC Racks in UA83
for A.L8
for X.L8
for M.L8
5
Hardware Commissioning planning for the PIC
Interlock team composed of only 3 people (Markus,
Robert Pierre)
Validation of commissioning performed via
automated procedures tools
Individual test of the PIC
PIC involved in short-circuits tests
Powering Tests
Additional resources still expected (time needed
for training of personnel)
6
Status of the different levels of the project
(1/3)
  • Despite initial delay the activity is progressing
    well
  • (thanks
    to Frederic Hervé)
  • Lab tests are going to start soon
  • ALARMS and PM have to be included

  • (discussions started, tbc)

PVSS layer
Ethernet Technical Network

7
Status of the different levels of the project
(2/3)
PVSS layer
Ethernet Technical Network
  • PLC program is working and functionality tested
  • Together with PVSS tests, communication tests to
    be started
  • Worry about CPU module performance
  • bug in the last version available on the market
  • acknowledged from Siemens but no change before
    next generation (in 2006?)

Equipment layer CPU part

PIC
Profibus

8
Status of the different levels of the project
(3/3)
PVSS layer
Ethernet Technical Network
Equipment layer CPU part

PIC
Profibus
I/O part
  • For the different boards, patch-panels,
    sub-units
  • Prototypes validated
  • Entering now in the pre-series phase
  • all hardware foreseen for end of July
  • Wiring and assembly will be made at CERN

  • (workshop and/or Interlock
    Team)

9
Summing-up
  • Preparation in progress no show-stopper for the
    3 layers (PVSS side, Siemens CPU I/O parts)
  • 2 PICs are going to commissioned in Sep.05
  • 2 others PICs for the Arc 7-8 in Dec.05
  • One more in UA83
  • One in UJ76. Radiation issues gt system moved in
    TZ gallery?
  • The units will be fully tested in the lab in
    August gt dismounted and re-mounted in the
    undergrounded area by the interlock Team.
  • Dependencies issues?
  • All copper cables (TS/EL) are already there

  • (check performed for LSS8L, and partially done in
    large part of LHC)
  • UPS should be present in the racks (gttbc)
  • Ethernet should be OK (gttbc)
  • Remote Reset connection should be OK (gtGuy)


In conclusion (for the time being) we are
optimistic to be on time!
Write a Comment
User Comments (0)
About PowerShow.com