Title: The Katzen Arts Center
1(No Transcript)
2(No Transcript)
3The Katzen Arts Center Washington, D.C.
Introduction
Excavation Support System Analysis
MEP Coordination
LEED Certification Analysis
Conclusions
Acknowledgements
Questions
The Pennsylvania State University Senior Thesis
Spring 2005
Jessica A. Potkovick Construction Management
Option
4INTRODUCTION
5PROJECT INFORMATION
Project Location 4400 Massachusetts Ave., NW
Washington, D.C. 20016 Function
Academic Space, Performance Center, Gallery Size
330, 000 SF Stories 6 Stories Cost 41,
000,000 Project Delivery CM _at_ Risk Construction
Dates May 1, 2003 May 15, 2005
6PROJECT TEAM
Building Occupant American University Architect
/Engineer Einhorn Yaffee Prescott Consultants
EDAW, Inc. (Landscaping) Alpha Corporation
(Civil) Cagley Associates,
Inc. (Structural) Miller,
Beam, Paganelli, Inc. (AV Acoustic)
Fisher Dachs Associates (Theatre)
Claude R. Engel Lighting Consultant
(Lighting) Construction Manager Holder
Construction Company
7ARCHITECTURE AND BUILDING SYSTEMS
- Architecture
- Gateway to Campus
- Layout Primarily Linear with Serpentine Effect
- Three Building Components
- Two Rotundas
- Roof Terrace/Roof Garden
- Water Feature
- Façade Limestone Veneer with CMU Backup,
Ground Face CMU, or Aluminum Storefront - Skylights
8ARCHITECTURE AND BUILDING SYSTEMS
- Structural
- Cast-in-Place Concrete
- Lighting/Electrical
- LED Emergency Lighting and Parkpack in Parking
Levels - Academic Fluorescent, Recessed Parabolic
Lights - Gallery Low Brightness, Recessed Fluorescent
Wall Wash and Downlights - Performance Directional Downlights and
Ellipsoidal Spotlights - Power 3 phase, 4 wire Switchboard Operating at
3000A, 480/277V - 75kVA, 480-120/280V Phase Transformer
- Two 3 phase, 4 wire Panelboards at 480/277V and
120/277V - Mechanical
- VAV and Constant Air Systems
- Six AHUs, Two Cooling Towers, Two Chillers,
- Location Parking Level 1 (Central Plant), 3rd
Floor (Secondary Plant)
9EXCAVATION SUPPORT SYSTEM ANALYSIS
10EXCAVATION SUPPORT SYSTEM ANALYSIS
- Background
- Original Excavation Support System
- Issue
- Current Excavation Support System
- Goals
- Investigate Original and Current Excavation
Support Systems - Determine the Impact of Switching Systems
- Analyze other possible solutions in terms of
constructability, cost, and schedule in order to
recommend a solution for detailed analysis.
11ORIGINAL EXCAVATION SUPPORT SYSTEM
- Soldier Piles
- Tiebacks
- Timber Lagging
12CURRENT EXCAVATION SUPPORT SYSTEM
- Posts and Soldier Piles
- Bracing
- Timber Lagging
13IMPACT
- Schedule
- Division of Component A into two Parts
- Interrupts Excavation Flow
- Slower Excavation Period
- Deconstruction of Bracing Required
- Cost
Additional Requirements Cost
Piles 20,815.28
Reaction Post 45,909.36
Web Stiffeners 2,340.00
Mobilization 248.50
Subtotal 69,313.14
Total Cost (w/Location Factor) 67,164.43
14ALTERNATE SOLUTIONS
- Steep Angle Tiebacks
- Soldier Piles (Driven Close)
- Sheet Piles
- Slurry Wall
- Sheet Piles Slurry Wall
- Secant Piles
- Purchase Property
- Purchase Property and Sell Back
15ADVANTAGES/DISADVANTAGES
- Disadvantages
- Soil Bearing Capacity
- Additional Cost
- Additional Construction Time
- Site Constraints
- Advantages
- Potential for Payback
- Constructability Plan Remains the Same
16CONCLUSION
- Current Excavation Support System
- Had Major Impact on Constructability
- Little Impact on Schedule/Cost
- Therefore
An alternate solution must have as little
schedule/cost impact as possible.
- Suggestions for Further Detailed Analysis
- Purchase Property
- Purchase Property/Sell Back
17MEP COORDINATION
18MEP COORDINATION AND CAD IMPLEMENTATION
- Background/Proposal
- MEP Coordination Process
- Previous Research
- Goals
- Identify Areas MEP Contractors could use 3D CAD
Technology - Create a CAD Implementation Plan for Holder
Construction
19PLAN
Foreman Planning/Field Supervision
Construction Sequencing/Scheduling
Estimating
As-Builts
Hire Staff
Marketing
Shop Drawings
Project Planning
Technology Selection
Material Management
20CONCLUSION
- -Mike Duwell, Preconstruction Manager
- Holder Comments
21LEED CERTIFICATION ANALYSIS
22LEED CERTIFICATION ANALYSIS
- Background
- Evolution of Research Proposal
- Goals
- Determine Goals of the USGBC
- Determine Needs of the Building Industry
- Compare the objectives of the USGBC and the
opinions of the building industry to establish if
their needs are being met. If not, suggest
actions for meeting those needs.
23USGBC INTERVIEW
- Intention was to Identify
- History and Organization Goals
- Statistics on LEED Project Applicants vs. Actual
Project Certifications - Credits Most/Least Often Applied For
- Process/Timeline of Version Revision
24USGBC INTERVIEW
- Sabrina Morelli, LEED Coordinator
- LEED Letter Templates
- Documentation Requirements
- Rating System Language
- Certification Process
- Rating System Updates
- LEED Version 2.2
25BUILDING INDUSTRY SURVEY
- Survey Goals
- Why Owners choose not to go for/complete a LEED
certification? - Determine the current process used to document
credit fulfillment. - Determine satisfaction with current LEED
documentation requirements. - Identify how familiar the industry is with
current changes in the process and if they
believe they are positive. - Identify difficult credits to achieve and why.
26BUILDING INDUSTRY SURVEY
- -13 Responses
- LEED Letter Templates
- Documentation Requirements
- Rating System Language
- Certification Process
- Rating System Updates
- LEED Version 2.2
27CONCLUSIONS
- USGBC
- Provide a detailed list of specific credit
requirements. - Modify the reference guide so that designer and
contractor requirements are addressed separately
or create individual designer and contractor
guides. - Offer assistance with credit evaluation
throughout the course of the project. - Or, create a position at the USGBC for LEED
Inspectors. - Continue to find ways to streamline the
documentation process and reduce the amount of
time and paperwork that is required to put
submittals together.
- Building Industry
- Take an active part in the public comment
period. - Offer contractor focused LEED training to
associates and subcontractors to clarify LEED
certification process and rating system.
28CONCLUSIONS
29- Excavation Support System Analysis
- Goals
- Examine both the original and current systems
and determine the impact of switching. - Determine if there is an alternate solution for
further detailed analysis by investigating other
systems in terms of constructability, schedule,
and cost. - Conclusion
- Major Impact on Constructability Little Impact
on Cost and Schedule - Further Investigate Purchasing the Property or
Purchasing the Property/Selling Back - MEP Coordination
- Goal
- Create a CAD Implementation Plan for Holder
Construction - Conclusion
- Currently in Process of Similar Plan
- LEED Certification Analysis
- Goal
- Determine if the goals of the USGBC are aligned
with the needs of the Building Industry. - Conclusion
- Needs are not currently met Satisfaction will
most likely improve following the release of LEED
Version 2.2.
30I would like to thank the following people for
their assistance and support
Holder Construction Company American
University Penn State Faculty United States
Green Building Council Building Industry
Members Family and Friends
31Questions?