Title: Presentation on SAMDI budget 2002/3 and 2003/4


1
Presentation on SAMDI budget 2002/3 and 2003/4
2
Introduction
  • This presentation focuses on
  • Sources of SAMDI revenue
  • Total revenue
  • Expenditure for 2002/3
  • Projections for next three years

3
Revenue by source for 2002/3
  • Grand total R 41,648 million
  • - Vote R 26,370 million
  • - Cost Recovery R 6,778 million
  • - Donor R 8,500 million

4
SAMDITotal Revenue for the Department
5
(No Transcript)
6
Cost Recovery
  • AIM To support SAMDI business through
  • the recovery of costs on services rendered
    through fair and recognised outsourcing
    processes.
  • SAMDI is expected to finance the delivery of its
    mandate through payment for its services.

7
Trade Account
  • Total Revenue (April 2002-Mar 2003)
  • R 6,778,947 (Generated from charges)
  • 1036 invoices issued to the value of
  • R 13,049,089
  • Total Debtors outstanding
  • R 4,628,111
  • Tariffs revised during October 2002
  • - Inclusion of consultation fees
  • - Inclusion of professional management
  • fees

8
Donor funding
  • Public Service Management Development Programme
    (PSMDP) - Funded by the European Commission

9
PSMDP project purpose.
  • The overall objective of the PSMDP was to enhance
    the capacity and performance of the South African
    Public Service through targeted training and
    development initiatives.
  • The project purpose was to build management
    training and development capacity in the state
    sector through support for SAMDI, and in the
    tertiary sector through support for JUPMET, and
    to train additional public servants in a range of
    relevant management and development skills.


10
Result areas for SAMDI (1-4)
  • Result 1 Experienced managerial team This
    result area focused on improving skills within
    SAMDI to ensure the sustainability
  • Result 2 Training for public managers
    Programmes for both generic and specialised
    management development training.
  • Result 3 Capacity building in personnel and
    labour relations This result area specialised in
    building capacity to HRM and labour relations
    skills.
  • Result 4 Better equipped new managers Training
    in this result area emphasised the importance of
    Batho Pele People First.

11
Result areas for JUPMET (5-8)
  • JUPMET result areas (5 8)
  • Result 5 More highly developed existing middle
    and senior level public service managers
    Training for public service managers according to
    needs.
  • Result 6 Trained middle and senior managers in
    specialist skill areas Tailor-made courses in
    specialist areas for particular departments,
    including non-governmental organisations
  • Result 7 Increase in graduate numbers in
    post-graduate public administration degrees
    Training for experienced public servants and
    staff in post-graduate studies.
  • Result 8 Capacity building within the JUPMET
    consortium Activities aimed at building relevant
    capacity in all members of the consortium, with
    particular emphasis on historically disadvantaged
    universities.

12
Expenditure on PSMDP (AWP 1 June 2001 31
December 2002)
  • Donor Funding R 39,6 million
  • Expenditure
  • Result area 1 R 6,148,520
  • Result area 2 R13,282,060
  • Result area 3 R 8,875,576
  • Result area 4 R 3,117,485
  • PAT/ CC R 2,743,606
  • Result area 5-9 R 2,617,394
  • 2000 payments R 1,716,551
  • TOTAL R 38,501,165

13
Persons Trained
  • The persons trained (PT) for Results 1 4
    (SAMDI) of AWP 2001/2 (1 June 2001 until end
    December 2002) was 23,400 and 105,000 person
    training days (PTD),
  • Results 5 9 (JUPMET) the PT target was 1,290.
    The output is inconclusive due to an outstanding
    audit report

14
Highlights
  • Successful implementation of the AWP 2001/2 under
    the management of PAT
  • Unqualified external audit opinion for 1 June to
    31 December 2001on funds management by PAT
  • Development of an M E framework
  • Establishment of a quality assurance unit
  • Training programmes are outcomes-based

15
Highlights continue
  • Database of service providers updated
  • Well-established archiving and information
    recovery system
  • Development and implementation of an exit
    strategy for project close-down
  • Adherence to EC tender procedures and modalities
    35 tenders approved by EC

16
Projections SAMDI revenue

Year 2003/4 2004/5 2005/6
Vote 42,261 38,759 35,211
Cost recovery 10,000 15,000 20,000
Donor 6,400 4,000 -
Total 58,661 57,759 55,211
17
Rationale
  • The targets aim at making SAMDI largely self
    sustainable.
  • SAMDI is meeting targets on cost recovery.

18
Projections for revenue and expenditure for the
trading account
R million 2002/3 2003/4 2004/5 2005/6
Non- tax revenue 0,5 10,0 15,0 20,0
Transfers received 4,270 25,629 19,661 14,726
Total revenue 4,770 35,629 34,661 34,726
19
Projected donor funding
  • Flemish project approved w.e.f 20 January 2003

20
Objectives
  • Overall objective- To enhance management
    capacity of a core group of senior, middle and
    junior managers in Lampoon and KwaZulu-Natal
    Provinces to facilitate optimum leverage for
    service delivery to citizens
  • Specific objective- The development of
    integrated management and strategic leadership
    competencies for senior, middle, and emerging
    managers, customised to provincial and
    departmental priorities and needs.

21
Result areas
  • Result 1- Three separate but inter-connected,
    customised management development programmes for
    senior, middle, and emerging managers designed
    and planned
  • Result 2- Critical mass of managers trained in
    accordance with outcomes based training and adult
    learning principles, incompliance to SAQA
    requirements.
  • Result 3- Information provided on the enabling
    environment required for effective implementation
    of learning.

22
Cross-sectoral themes
  • Gender course attendance profiles
  • Disability integrated into training material
    venues accessible to people with disability.
  • Information and communication integrated into
    course material
  • Good governance anti-corruption and
    accountability part of course material
  • HIV/AIDS management in the workplace.

23
Flemish - Funding
  • Total value of the project is 1,084,273 euro at
    an exchange rate of 8.76 the value is
  • R 9.5 million.
  • SAMDI counter funding support to Project through
    staff, infrastructure, accommodation etc.

24
Flemish - Funding
  • Total value of the project is 1,084,273 euro at
    an exchange rate of 8.76 the value is
  • R 9.5 million.
  • SAMDI counter funding support to Project through
    staff, infrastructure, accommodation etc.

25
Conclusion (Main challenge)
  • Payments by departments (debtors)
  • Provincial departments to be encouraged to pay
  • THANK YOU