Title: Rock Riffle Design Course
1Rock Riffle Design Course
2Goals of Streambank Restoration
- Work With Nature
- Reduce Sediment
- Protect Cropland
- Protect infra-structure
- Improve Water Quality
- Improve Aquatic Habitat
- Make it Affordable
3Lanes Balance
4200 years of Human Activity on the Landscape
- Cleared the Timber
- Plowed the Prairie
- Drained the Wetlands
- Straightened the Streams
- Leveed the Floodplains
- Built Cities with Large Areas of Concrete,
Asphalt and Rooftops
5Results of Human Activity on Stream dynamics
- Increased Runoff
- Increased Stream Slope
- Reduced Floodplain Width
6Design Philosophy
- Work WITH the Natural Processes.
- Know Where Nature is Taking the Stream.
- Determine the Cause of The Problem
- Treat Only the Cause
- Let Nature Finish Healing The Banks
- Keep the Cost Down
7Channel Evolution Model (CEM)
8Stream Stabilization Techniques
- 4 Major Practices Used in Illinois
- Rock Riffle Grade Control Structures (stage II or
III) - Stone Toe Protection (stage III or IV)
- Bendway Weirs (stage IV)
- Stream Barbs (stage IV)
9Rock Riffle Grade Control Structures (stage II/
III streams)
- Stabilize the Bed
- Creates Riffle/Pool Sequence
- Dissipates Energy
- Aerates Water
- Permit Fish Passage
- Aesthetically Attractive
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16Determine Stability
- Review I E Data
- CEM Stage?
- Entrenchment Ratio?
17(No Transcript)
18(No Transcript)
19(No Transcript)
20(No Transcript)
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25McCray Stream Site
- Valley slope 0.0028
- Surveyed slope ave. 0.0024 (slightly lower)
- Bed in Riffle ---Clay (exposed in riffle bed)
- Width/Depth ratio 10.3 (just over 10)
- Entrenchment Ratio 1.28 (just under 1.4)
- 2 elements suggest Grade Control
- 2 elements outside suggested range (barely)
26Channel Geometry Considerations
- Sine Wave Flow
- Anticipated Scour Depth
- Radius Curvature/Bankfull Width Ratio (should be
more than 1.8) - Existing Riffle Location
- Existing Riffle Spacing
27(No Transcript)
28(No Transcript)
29Scour Depth
- Assume Scour Depth will equal Max. Bankfull Flow
Depth - Assumes bed material allows full Sine Wave Flow
to develop over time
30(No Transcript)
31Radius of Curvature
- Ave radius 2.3 times bankfull width (Leopold)
- Range generally from 1.6 to 4.5 times bankfull
width (natural streams) - 2.3 is the optimum for hydraulic efficiency
- 1.8 is the suggested minimum under guidelines
32(No Transcript)
33Locating Riffles
- 5 to 7 Bankfull widths (28 ft)
- Expect Spacing--140 to 196 ft.
- Located at Cross-over Points
34(No Transcript)
35(No Transcript)
36(No Transcript)
37(No Transcript)
38Read The Channel
- Knickzones and Headcuts
- May be hundreds of feet long
- Little or no bedload in crossover pts.
- Will not be bedload material (sand wave)
- Increasing bank height downstream?
-
- Stable Points? (Bedrock, Culvert, etc)
39(No Transcript)
40Gather Survey Data
- Bed Profile
- Water Surface Profile
- Typical X-Section _at_ Riffles (detailed)
- Low Bank Profile
- Stream Cross-over Points (Stations) or surveyed
planform
41Plot profile
- Channel Grade (riffle to riffle)
- Riffle Spacing
- Compare low bank vs. channel grade
- Pool Depths
- Stable Points
42(No Transcript)
43Riffles
44Existing Riffles?
- Stations 000, 425, 590, 825, 1020
- 1150, 1320, 1375, 1475 1550,1640, 2020
- 12 riffles in 2020 ft. --Ave. Spacing 168 ft.
- Max. Spacing --425 ft.
- Min. Spacing-- 55 ft.
45Low Bank
Grade Line
Profile
46(No Transcript)
47Bank Heights
48Plot Cross-Section(s)
- Bankfull depths
- Riffle Crest Elev.
49(No Transcript)
50Determine New Gradeline
- Slope (will be greater than existing slope)
- Stable Upstream(flood out headcut/knickzone)
- Stable Downstream(Culvert/Stable Grade, etc)
- Blend into existing channel bed (generally 1.0
ft. height or less _at_ last riffle)
51(No Transcript)
52Locate Riffles and Crest Elev.
- Geometrically Correct
- Uniform Gradeline
- 6 Bankfull Width spacing?
- Backwater to Toe of Upstream Riffle
53(No Transcript)
54(No Transcript)
55Planned Riffles
56Riffle Spacing
- Existing Riffles range from 55 ft. to 425 ft.
- (2 to 15 bankfull widths)
- Ave. 168 ft. (6 bankfull widths)
- Planned Riffles range from 210 ft. to 370 ft.
- (7.5 to 13 bankfull widths)
- Ave. 233 ft. (8.3 bankfull widths)
- Too Wide?
57Riffle Spacing (cont.)
- Concern is natural flow pattern and siltation
problems if spacing is too wide. - Experience has not shown spacing to be as
critical as once thought (especially with silt
and sand bed streams) - Attempt to locate riffles near existing riffles
at cross-over points and put backwater on tail of
upstream riffle.
58Check for increased Flooding(when necessary)
- Bankfull Specific Energy Line
- Critical Flow Depth
- Critical Specific Energy Line
- Allowable Riffle Height Bankfull Specific
Energy - Critical Specific Energy
59(No Transcript)
60Max. Riffle Ht. CalculationSpecific Energy Line
- Energy Line Bkf Depth Velocity squared
divided by 2 times gravity - Energy Line 2.7 (5.1sq./ 2 x 32.2)
- Energy Line 2.7 (26.01/64.4)
- Energy Line 2.7 .40 3.1 ft.
61Max. Riffle Ht. CalculationCritical Flow Depth
- Critical Depth (Q sq. divided by gravity times
width sq.) raised to the 1/3 power - Critical Depth (350 sq./32.2 x 28 sq.) raised
to 1/3 power - Critical Depth (122,500/32.2 x 784) 1/3
- Critical Depth (122,500/28142) 1/3
- Critical Depth (4.35) 1/3power 1.63 ft.
62Max. Riffle Ht. CalculationCritical Energy Line
- Critical Energy Line 1.5 times Critical Flow
Depth - Critical Energy Line 1.5 x 1.63
- Critical energy Line 2.45 ft.
63Max. Riffle Ht. Calculation
- Max. Riffle Ht. Allowable without raising water
surface profile or creating backwater effect
Energy Line - Critical Energy Line - Max. Riffle Ht 3.1 - 2.45
- Max. Riffle Ht. 0.65 ft.
64Max. Riffle Ht. Calculation Summary
- Specific Energy Line 3.1 ft.
- Critical Flow Depth 1.63 ft.
- Critical Specific Energy Line 2.45
- Max. Allowable Riffle Ht. W/O effecting water
surface elev. Specific Energy Line - Critical
Specific Energy Line or - 3.1 ft. - 2.45 ft. 0.65 ft. max. ht.
65Critical Velocity Estimate
- Velocity at Critical Flow(Vc) (gravity x
critical flow depth) raised to the 0.5 power - Vc 32.2 x 1.63 (raised to 0.5 power)
- Vc 52.5 (raised to 0.5 power)
- Vc 7.24 ft/sec.
66(No Transcript)
67What if I Raise Flood Surface Profile?
- Will I increase Out of Bank Flooding?
- Will I effect instream pipe outlets, tile, etc.
- Is the increase in flood surface profile
acceptable to all effected parties?
68(No Transcript)
69(No Transcript)
70Compute Quantities and Cost
- Determine Stone Size from CriticalVelocity
Calculations (double size for safety) - Quantity Chart
- Average County Cost per Ton of Stone
71(No Transcript)
72(No Transcript)
73(No Transcript)
74(No Transcript)
75(No Transcript)
76Cost of RipRap
- Statewide Average is about 25 per ton installed
- Check with local quarries/truckers for delivered
price of A-5 or A-6 stone---Add 3 to 5 per ton
for installation - quarry run or shot-rock CAN be
acceptable--Check with designer for O.K. before
using and plan on being at site during delivery.
77ROCK RIFFLE
78Construction Layout
- Riffles must be located at stream crossover
points where flow goes from one side to the
other. (riffles) - Riffles should be located slightly upstream of
existing riffle so backslope can blend into
existing riffle--also places maximum water depth
closer to apex of bend and dissipates energy in
pool.
79Sequencing
- Build from Upstream to Downstream
- Riffles will not seal and pond water until
voids are filled with sediment. - Can speed up pooling by placing a few inches of
fine silt/clay on front face of riffle.
80Bed Key
- 4 ft. minimum width
- 3 ft. minimum depth/or to bedrock
- Extends across channel bottom and 3-4 ft. into
outer bank. - Doesnt need to be larger material
- Do not over excavate! Easy to lose stone in bed
key
81Bank Key
- 4 ft. minimum width
- 5 ft. minimum depth
- Construct with a 1.5 on 1 slope into bank so that
as vertical banksstabilize the key is not
exposed - No need to fill key trench out to original
bank. - Top Elev. approx.1 ft. below top bank
82Riffle Crest
- Build Crest to elevation before starting on
backslope - Use largest material in gradation
- Place crest stones individually with thumb if
possible - Build Crest with slight V shape using control
elevation as low point in v.
83Backslope
- Build with 201 backslope
- Place next largest stone available from gradation
immediately downstream of Crest stones. - Flare the backslope up the channel sides slightly
(1.5 ft?) - Leave backslope rough to aerate flow and
provide resting places for fish passage.
84Blending into Exit Channel
- H-4 dimension is depth to place material below
existing channel bed at exit. - Most streambeds are soft enough that material
can be pressed into channel bed without
excavating
85Alignment
- Align Crest so that desired exit is at 90 degrees
to Crest. - If channel has a sharp bend near tail of riffle
use Stone Toe Protection downstream to protect
against increased velocity near riffle exit.
(Riffle backslope has a 5 grade)
86Follow-up and Maintenance
- Check each structure after first major storm
(near bankfull flow) - Some movement and of smaller stone and sorting of
material is expected. - If any crest stone moves it should be repaired
immediately