Title: Transmission Expansion Cost Drivers
1Transmission Expansion Cost Drivers
- NARUC
- Portland, Oregon
- David Mead
- Vice President, Engineering
- Southern California Edison
2SCE has one of the nations largest and oldest
electrical systems.
- Operating for 121 years
- Covering 50,000 square miles of central, coastal
and Southern California - Serving a population of more than 13 million via
4.8 million customer accounts in 428 cities - Added 386,000 new meters over the last five years
(77.2k/year) - 17.6 Billion T D Assets (2006)
First Predecessor Company to SCE Established in
1886 Consolidated Edison (NY) was founded in
1823.
3What Is Driving The Need For Transmission
- Replacement of aging infrastructure presents a
growing challenge - New records are continuing to be set for peak
demand throughout the state - In addition to load growth, we are obligated to
comply with increasing regulatory requirements on
renewable energy - California Renewable Portfolio Standard
- 20 by 2010
- Possibly 33 by 2020 (statute under
consideration) - California Greenhouse Gas (GHG) regulation
4What Are The Cost Escalators To New Transmission
- State Regulatory processes are lengthy, costly
and require significant resources - Duplicative environmental reviews
- Federal agencies are difficult to navigate and
slow to approve - BLM
- US Fish and Wildlife
- US Forest Service
- Interstate projects must have sufficient
benefits to avoid state opposition as
intrusive - Public more engaged and mobilize opposition
quickly - Land availability and changes to California
Eminent Domain laws - Escalating project construction costs
5Permits And System Constraints Complicate The
Issue
- Permitting and licensing decisions from
regulatory/jurisdictional agencies contain
significant changes impacting project scope and
schedule - Multiple and significant mitigation measures
- Limits construction methods and hours
- Routes permitted are often different than
proposed - New routes outside of existing right-of-way
- Fully utilized electrical systems make
construction outages even more challenging - Outage availability due to peak demand
- Construction window narrow
6Execution Has Its Own Set of Challenges
- Competition for resources
- Materials
- International trade/demand
- Extraordinary inflation
- Equipment
- Long lead times and price increases
- Labor
- Numerous large expansion projects
- Replacement of aging utility infrastructure
- Fuel
7Public Opposition
- The public is more engaged and opposition
mobilizes quickly - Creating an unassailable need statement is
critical to managing public opposition - Regulatory/permitting jurisdictions view
undergrounding as the answer to public concerns
on visual impacts - Costly and only benefits a small percentage of
ratepayers - Communities benefiting should carry the cost
- Changes to Eminent Domain is example
8Public Opposition Acronyms A Quiz!
- NIMBY
- NOPE
- BANANA
- NIMET
- CAVE
- NIABY
- LULU
- NEIUROW
- BNMHYMWBS
Not In My Back Yard
Not On Planet Earth
Build Absolutely Nothing Anywhere Near Anyone
Not In My Elected Term
Citizens Against Virtually Everything
Not In Anyones Back Yard
Locally Unwanted Land Use
Not Even In Utility Right-Of-Way
Build Near My House Your Mama Will Be Sorry
9Transmission Planned and Under Construction for
Renewable Generation Delivery
- SCE pursuing numerous renewable transmission
projects - Tehachapi Renewable Transmission Project delivers
4500 MW of primarily wind generation. - Acceleration of SCEs construction of the
California phase of Devers-Palo Verde 2 500 kV
project to deliver renewable generation from
Colorado River area to Southern California. - Eldorado Ivanpah 230 kV project to deliver 1400
MW of primarily solar generation. - Developing comprehensive transmission plans for
solar and wind generation integration in several
other areas of San Bernardino and Riverside
counties. - Above projects in various stages of project
development with the capability of delivering
over 7,000 MW of renewable generation.
10Tehachapi Renewable Transmission Project
- Delivers 4500 MW of renewable generation
- 2.7 Billion
11Tehachapi Renewable Transmission Project Segment 1
- The Certificate of Public Convenience and
Necessity issued by California Public Utilities
Commission - Contained 179 mitigations measures, the
predominant issues - 46 are visual
- 33 are biology
- 22 are cultural
- Contained two major route changes
- US Forest Service
- Record of Decision
- Requires helicopter construction
- Requires narrow window on construction
12Tehachapi Renewable Transmission Project
- Segments 4-11 Certificate of Public Convenience
and Necessity currently in Regulatory review - Segment 8 regulatory evaluation is currently
reviewing the proposed route and 4 alternative
routes plus an undergrounding option - Any of 4 alternates or undergrounding the
preferred route will add significant costs to the
project - Segment 6 and 11 Double circuit proposal for
Angeles National Forest - Elevation and icing issues
13If We Build it They Will Come
- The market will produce the Generators
- The utilities will provide the Transmission
access - Will it be done in the current proposed
timetables? - Without more creative solutions, it will be
difficult - If we are able to meet the current schedule
demands - Costs are rising and may be higher than necessary
- Grid quality and reliability is at risk if we
dont pay attention - The process can end up more contentious than it
should be
14Conclusions
- Transmission investment opportunities are
exciting and unprecedented - Southern California Edison 5.5 billion in 5
years - Investments needed to access renewable energy,
serve growing loads, and replace aging
infrastructure - Obtaining project approvals is a daunting
challenge weve learned much over the last few
years - Managing the escalating costs will be key for
utilities and our customers