Risk Management - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Risk Management

Description:

Title: An Introduction to Systems Engineering Author: Chuck Last modified by: Chuck Created Date: 8/26/2006 4:06:08 PM Document presentation format – PowerPoint PPT presentation

Number of Views:81
Avg rating:3.0/5.0
Slides: 28
Provided by: homew59
Category:

less

Transcript and Presenter's Notes

Title: Risk Management


1
Risk Management
2
Risks and Risk Management
  • Risks are potential events that have negative
    impacts on safety or project technical
    performance, cost or schedule
  • Risks are an inevitable fact of life risks can
    be reduced but never eliminated
  • Risk Management comprises purposeful thought to
    the sources, magnitude, and mitigation of risk,
    and actions directed toward its balanced
    reduction
  • Beneficial Risk - The same tools and perspectives
    that are used to discover, manage and reduce
    risks can be used to discover, manage and
    increase project opportunities (increased
    performance).

3
  • What if?

4
IF
  • Predict IF Identify
  • Evaluate IF Analyze
  • Plan for IF Plan
  • Tracking IF Track
  • Budget for IF Control

5
Risk Management
  • Laws
  • Terms
  • Types of Risk
  • Risk Management

6
Laws
  • Murphys Law
  • If something can go wrong it will go wrong
  • Finagles Law of Dynamic Negatives (corollary to
    Murphys Law
  • Things will go wrong at the worst possible time

7
What is Risk Management?
Risk management is a continuous and iterative
decision making technique designed to improve the
probability of success. It is a proactive
approach that
  • Seeks or identifies risks
  • Assesses the likelihood and impact of these risks
  • Develops mitigation options for all identified
    risks
  • Identifies the most significant risks and chooses
    which mitigation options to implement
  • Tracks progress to confirm that cumulative
    project risk is indeed declining
  • Communicates and documents the project risk
    status
  • Repeats this process throughout the project life

8
Risk Matrix
Impact
Probability of Occurrence
9
Risk Warning Signs
  • TPMs
  • Schedule Projections
  • Cost Projections
  • Supplier problems
  • Late technology demonstrations

10
Types of Risk
  • Technical Risks
  • Programmatic Risks
  • Cost
  • Schedule
  • Supportability Risks
  • Beneficial Risks

11
Risk Analysis
  • What Could Go Wrong
  • What is the Probability
  • What is the Magnitude of Impact
  • Cost
  • Schedule
  • Performance
  • Alternate Strategies (Off Ramps)

12
Beneficial Risk
  • High Risk High Payoff
  • Mitigation Strategy
  • Alternate Plans
  • Criteria
  • Schedule
  • Budget

13
Risk Handling
  • Have a Plan
  • Total Program
  • Budget (Cost / Schedule) for Plan
  • Get Buy-In
  • Monitor Status
  • Metrics
  • Close out

14
Risk In General
  • Risk is Healthy
  • Not Identifying Risk shows
  • You dont understand the program
  • AND/OR
  • You are dishonest
  • AND/OR
  • You think the customer is stupid
  • Identify all potential Risk
  • Knock them down with Mitigation Plans

15
Summary
  • Its risky not to embrace risk.

16
SE Technical Program Mgmt
  • Key focus of systems engineering
  • includes the direction of a totally integrated
    effort of system design, test and evaluation,
    production, and logistics support over the system
    life cycle
  • The goal is timely deployment of an effective
    system, sustaining it, and satisfying the users
    need at an affordable cost.
  • Involves balancing a systems cost, schedule, and
    performance while controlling risk.

17
Technical Performance Measures
  • TPMs are measures of the system technical
    performance that have been chosen because they
    are indicators of system success. They are based
    on the driving requirements or technical
    parameters of high risk or significance - e.g.,
    mass, power or data rate.
  • TPMs are analogous to the programmatic measures
    of expected total cost or estimated
    time-to-completion (schedule).

18
Technical Performance Measures
  • Actual versus planned progress of TPMs are
    tracked so the systems engineer or project
    manager can assess progress and the risk
    associated with each TPM.
  • The final, delivered system value can be
    estimated by extending the TPM trend line and
    using the recommended contingency values for each
    project phase.
  • The project life trend-to-date, current value,
    and forecast of all TPMs are reviewed
    periodically (typically monthly) and at all major
    milestone reviews.

19
TPMs Are Tools
  • Technique of predicting the future value of a key
    technical performance parameter
  • Continuous verification confirms progress and
    identifies variances
  • Assessed values falling outside established
    tolerances indicate the need for management
    attention

20
Why TPMs
  • A well thought out TPM program provides
  • Early warning of technical problems
  • Supports assessments of the extent to which
    operational requirements will be met
  • Assesses the impacts of proposed changes made to
    lower-level elements in the system hierarchy on
    system performance.

21
Balancing Cost, Sked, Performance
22
Selecting TPMs
  • Parameters to be tracked are typically based on
    the combined needs of the customer and the
    contractor
  • Contractor may track more items than are reported
    to the customer, as the contractor needs
    information at a more detailed level than does
    the customer program office.
  • Customer requires visibility into the technical
    performance of key elements of the work breakdown
    structure
  • Especially those which are needed to meet system
    key performance parameters (KPPs), are cost
    drives, lie on critical path or high risk items

23
Example TPM
Shipboard Fire Control System
Power Density Detection Range Slew Time Tx Ant
Side lobes CW Ant Side lobes Tx Track Acc AM
Noise FM Noise Pointing Acc Weight Radiated
Power MTBF MTTR Range Res Angle Res
CW Transmitter
Data Processor
Antenna
Slew Time MTTR Side Lobes Beam Width
AM/FM Noise Radiated Pwr MTBF
MTBF Memory Proc Speed MTTR
24
TPM Selection
  • The level of the system at which parameters are
    selected is based on how readily the information
    supports timely design decisions.
  • For example, the timely identification and
    neutralization of targets and threats are
    essential to both the operational effectiveness
    and survivability of a ship.
  • If there is a risk associated with meeting the
    detection range requirement allocated to the
    ships fire control system, then the technical
    manager will want to have data that supports
    design decisions related to achieving both the
    system and subsystem performance during the
    design process, such as predicted (and actual)
    radiated power and data processor speed.

25
TPM Selection
  • These are metrics that can be measured under
    laboratory conditions before costly and
    time-consuming fabrication, integration, and
    conformance testing of higher assemblies and
    continued monitoring assures that required values
    are met under actual environmental conditions and
    system loading.
  • Thoughtful selection of the parameters to measure
    can minimize unpleasant surprises in formal
    developmental and operational testing.

26
Conceptual TPM Graphic
27
Team Project
  • Make sure you have at least 4-5 TPMs for your
    project. They must be presented in graphical
    form like previous slide
Write a Comment
User Comments (0)
About PowerShow.com