Title: CRS Sanction
1CRS Sanction
2- We will discuss-
- Commission of Railway Safety
- (a) Brief history,
- (b) Organisation
- (c) Functions / Duties
- Extracts from P- Way manual
3CRS - BRIEF HISTORY.
- To exercise effective control over the
construction operation of the first
railways in India, which were entrusted to
private companies, consulting engineers
were appointed under the govt. of India. - Later, when the govt. undertook the
construction of railways, the consulting
engineers were designated as government
Inspectors. -
4 - In 1883, Their position was statutorily
recognised, Later on, the Rly. Inspectorate was
placed under the Rly. Board which was
established in 1905. - The Rly. Inspectorate was subsequently
placed in the year 1940 under the
ministry of transport and communication. In
an attempt to give better status, Rly.
Inspectorate was redesigned as commissioner
of Rly. Safety in the year 1961. - Present position is that there is a CRS
headed by CCRS Hq. _at_ Lko. Under the ministry
of civil aviation.
5There are three parts- Regulation Inspec
tion Operation
6Function / Duties
- The main task of the commission of Rly.
Safety is to direct, advice caution the Rly
executives with a view to ensure that
all reasonable precautions are taken in
regard to soundness of rail construction
safety of train operations. - (i) Opening of new lines.
- (ii) Introduction of new rolling stocks.
- (iii) Works in existing lines.
- (iv) Inspections of existing lines.
- (v) Sanction of infringement to Schedule of
Dimensions. - (vi) Inquiry into serious accidents.
7Organization
Chief Commissioner of Railway Safety - Dy. CRS
(General) - Dy. CRS (Electrical) - Dy. CRS
(Mechanical) - Dy. CRS (Operating) - Dy. CRS
(ST)
8Organisation
CRS Circles Jurisdiction
Northern Circle, New Delhi Northern Railway, DMRC
North Eastern Circle, Lucknow North Eastern Railway, North Central Railway
North East Frontier Circle, Kolkata North East Frontier Railway, Kolkata Metro
Eastern Circle, Kolkata Eastern Railway, East Central Railway
South Eastern Circle, Kolkata South Eastern Railway, South East Central Railway, South East Coast Railway
South Central Circle, Secunderabad South Central Railway
Southern Circle, Bangalore Southern Railway, West Coast Railway
Central Circle, Mumbai Central Railway, West Central Railway, KRCL
Western Circle, Mumbai Western Railway, North Western Railway
9Extracts from P- Way manual, Chapter XIII
(PARAS 1301 TO 1310 Including correction slip
no 111)
- Safety of traveling public is governed by rules
laid down in - IR act 1989 (24 of 1989) .( as amended from time
to time). - General rules for IR.
- The Rly. (opening for public carriage of
passengers) Rules, 2000 ( as amended from time to
time). - IR schedule of dimensions ( as amended from time
to time). - Above rules specify the authority competent to
sanction procedure for obtaining sanction
10Works requiring sanction of CRS
- Under section 23 of IR act 1989 (24 OF 1989)
chapter 7of rules for opening Rly 2000, the
sanction of CRS is required for execution of any
work on open line which will affect running of
trains carrying passengers any temporary
arrangement necessary for carrying it out except
in emergency. - For commencement opening of following works,
when they are connected with Rly, sanction of CRS
shall be obtained-
11- Additions, extensions,alternations to running
lines. - Alterations to points crossings in running
lines. - New signalling interlocking installations or
alterations to existing . - New stations, temporary or permanent. Or
extensions.
12- The construction (but not the removal) of an ash
pit on running line. - Heavy re-grading of running lines involving
raising/lowering of track in excess of 500 mm. - New bridges including road over and under
bridges, foot over bridges, strengthening ,
raising, reconstruction, dismantling or extension
of existing bridges
13- Addition or replacement of existing girders
including provision of temporary girders. here
bridges includes subways also affecting running
lines. - Provision, shifting, de-manning, down
grading,manning of unmanned LCs, upgrading
involving changes in method of working closing
down of LCs. - Permanent diversion (deviation) more than 2 Kms
in length without any station in between
irrespective of length when new station involved.
This is treated as new lines as per sec. 21to 23
of Rly. act 1989
14- Temporary diversions irrespective of length
except those laid for restoration of through
communication after accident. - Additions or alterations to electrical
installations of track equipped for electrical
traction. - ------
15Application for sanction of works
- Application for sanction made 30 days in advance
of expected commencement of work. If work not
taken up within 12 months from date of sanction,
CRS approached for renewal of sanction. - In case of divisional works,application made by
Sr. DEN and /or Sr. DSTE for track, bridge
signalling/interlocking works as the case may be.
When no JA grade officer exists in any deptt. of
the division, DRM/ADRM should sign the
application. In case of works of construction
organization, whether civil engg or S T
application will be signed by JA grade officer
for CE/C or CSTE/C as the case may be.
16- In case of works involving civil engg ST
both,application shall be signed jointly by both
deptts. following instructions as given above. - Name designation of signatory should invariably
be mentioned.
17Documents to accompany application
- Documents to accompany application are detailed
in annexure 13/1 they should be complete in
every respect. - A track certificate, indicating that track is
suitable for maximum axle load there in, shall be
given along with application, signed by Dy. CE
(track) counter signed by CTE/CE
18- For a major bridge or when non standard girders
or designs are used, Dy. CE / bridges should
issue a certificate on form 13 /3 indicating that
bridge is designed to carry axle loads proposed
to run, along with application. This certificate
is also counter signed by CBE /CE. - For the purpose of track bridge certificates as
per annexure 13/2 13/3, COM should also be
consulted in regard to types of locomotives
rolling stock to be used, their axle loads
speeds.
19Submission of safety certificate
- CRS in according sanction,may or may not propose
to inspect the work. - If CRS decides to inspect the work prior to
opening, he will, after inspection, communicate
in writing his sanction to open the work. - If CRS decides not to inspect work, safety
certificate in form 13/5 along with certificates
referred to there in shall be submitted to CRS
before work is opened. This will be done by
engineer in charge of work
20- Safety certificate for engg works should be
signed by ADEN counter signed by DEN. If any
conditional sanction is given, it should be
specifically certified that stipulated conditions
are fulfilled - Safety certificate despatched to CRS
expeditiously.
21Deviations from plans approved by CRS
- Prior approval of CRS is necessary,if, plans
already approved by CRS have any deviations,
especially, which affects layout of lines or
arrangements of signals or working rules.
22Application for running new type of
locomotive/rolling stock
- Application in this case,in form xvii of rules
2000 shall be made by CE one month in advance
giving following details Load diagram,
certificate for track strength, certificate for
girder strength, speed clearance certificate
issued by RDSO, reports of test runs /
oscillation trials obtained from
RDSO,infringements of max min dimensions for
running locomotive or rolling stock. Certificate
on form 13/4 signed jointly by CE CME in case
of steam diesel locomotives and by CE and CEE
in case of electric locos. - Certificate should also be signed by COM CSTE
if max permissible speed is proposed to be
raised.
23Notification to rly officials when opening works
- No new work affecting running of trains or
traffic working at stations should be brought
into use until staff of all departments have been
notified by means of a circular issued by DSO /
DOM
24Works arising out of accidents including breaches
- Abbreviated procedure as laid down in section 24
of IR act 1989 is reproduced below - When accident has occurred resulting in temporary
suspension of traffic, and either the original
line and work has been rapidly restored to
original standard, or a temporary diversion has
been laid in absence of CRS, it should be opened
for public carriage of passengers, subject to
following conditions
25- Rly servant in-charge of work has certified in
writing that opening of restored line and work or
temporary diversion, will not, in his opinion be
attended with danger to public using the line and
work or diversion. - As soon as may be, notice by telegraph, of
opening of line work or diversion sent to CRS
26- The certificate on form 13/6 in accordance with
section 24 of rly act 1989 must be written out
signed by representative of Engg Deptt in-charge
of work before opening it. The certificate be
despatched by telegram to officers concerned
followed by confirmatory copies by letter.
Engineering representative shall hand over a copy
of certificate to representative of operating
department at site of accident the latter will
not permit the passage of traffic over restored
road, until he gets this certificate.
27- Diversions should be tested by running a material
train or light engines before opening to public
traffic. - Certificate telegraph advice need not be sent
to CRS if line is restored for through
communication within 24 hours.If use of temp
diversion is likely for more than 3 days, CRS may
take earliest opportunity to inspect it.
28