Title: CRS Sanction


1
CRS Sanction
2
  • We will discuss-
  • Commission of Railway Safety
  • (a) Brief history,
  • (b) Organisation
  • (c) Functions / Duties
  • Extracts from P- Way manual

3
CRS - BRIEF HISTORY.
  • To exercise effective control over the
    construction operation of the first
    railways in India, which were entrusted to
    private companies, consulting engineers
    were appointed under the govt. of India.
  • Later, when the govt. undertook the
    construction of railways, the consulting
    engineers were designated as government
    Inspectors.

4
  • In 1883, Their position was statutorily
    recognised, Later on, the Rly. Inspectorate was
    placed under the Rly. Board which was
    established in 1905.
  • The Rly. Inspectorate was subsequently
    placed in the year 1940 under the
    ministry of transport and communication. In
    an attempt to give better status, Rly.
    Inspectorate was redesigned as commissioner
    of Rly. Safety in the year 1961.
  • Present position is that there is a CRS
    headed by CCRS Hq. _at_ Lko. Under the ministry
    of civil aviation.

5
There are three parts- Regulation Inspec
tion Operation
6
Function / Duties
  • The main task of the commission of Rly.
    Safety is to direct, advice caution the Rly
    executives with a view to ensure that
    all reasonable precautions are taken in
    regard to soundness of rail construction
    safety of train operations.
  • (i) Opening of new lines.
  • (ii) Introduction of new rolling stocks.
  • (iii) Works in existing lines.
  • (iv) Inspections of existing lines.
  • (v) Sanction of infringement to Schedule of
    Dimensions.
  • (vi) Inquiry into serious accidents.

7
Organization
Chief Commissioner of Railway Safety - Dy. CRS
(General) - Dy. CRS (Electrical) - Dy. CRS
(Mechanical) - Dy. CRS (Operating) - Dy. CRS
(ST)
8
Organisation
CRS Circles Jurisdiction
Northern Circle, New Delhi Northern Railway, DMRC
North Eastern Circle, Lucknow North Eastern Railway, North Central Railway
North East Frontier Circle, Kolkata North East Frontier Railway, Kolkata Metro
Eastern Circle, Kolkata Eastern Railway, East Central Railway
South Eastern Circle, Kolkata South Eastern Railway, South East Central Railway, South East Coast Railway
South Central Circle, Secunderabad South Central Railway
Southern Circle, Bangalore Southern Railway, West Coast Railway
Central Circle, Mumbai Central Railway, West Central Railway, KRCL
Western Circle, Mumbai Western Railway, North Western Railway
9
Extracts from P- Way manual, Chapter XIII
(PARAS 1301 TO 1310 Including correction slip
no 111)
  • Safety of traveling public is governed by rules
    laid down in
  • IR act 1989 (24 of 1989) .( as amended from time
    to time).
  • General rules for IR.
  • The Rly. (opening for public carriage of
    passengers) Rules, 2000 ( as amended from time to
    time).
  • IR schedule of dimensions ( as amended from time
    to time).
  • Above rules specify the authority competent to
    sanction procedure for obtaining sanction

10
Works requiring sanction of CRS
  • Under section 23 of IR act 1989 (24 OF 1989)
    chapter 7of rules for opening Rly 2000, the
    sanction of CRS is required for execution of any
    work on open line which will affect running of
    trains carrying passengers any temporary
    arrangement necessary for carrying it out except
    in emergency.
  • For commencement opening of following works,
    when they are connected with Rly, sanction of CRS
    shall be obtained-

11
  • Additions, extensions,alternations to running
    lines.
  • Alterations to points crossings in running
    lines.
  • New signalling interlocking installations or
    alterations to existing .
  • New stations, temporary or permanent. Or
    extensions.

12
  • The construction (but not the removal) of an ash
    pit on running line.
  • Heavy re-grading of running lines involving
    raising/lowering of track in excess of 500 mm.
  • New bridges including road over and under
    bridges, foot over bridges, strengthening ,
    raising, reconstruction, dismantling or extension
    of existing bridges

13
  • Addition or replacement of existing girders
    including provision of temporary girders. here
    bridges includes subways also affecting running
    lines.
  • Provision, shifting, de-manning, down
    grading,manning of unmanned LCs, upgrading
    involving changes in method of working closing
    down of LCs.
  • Permanent diversion (deviation) more than 2 Kms
    in length without any station in between
    irrespective of length when new station involved.
    This is treated as new lines as per sec. 21to 23
    of Rly. act 1989

14
  • Temporary diversions irrespective of length
    except those laid for restoration of through
    communication after accident.
  • Additions or alterations to electrical
    installations of track equipped for electrical
    traction.
  • ------

15
Application for sanction of works
  • Application for sanction made 30 days in advance
    of expected commencement of work. If work not
    taken up within 12 months from date of sanction,
    CRS approached for renewal of sanction.
  • In case of divisional works,application made by
    Sr. DEN and /or Sr. DSTE for track, bridge
    signalling/interlocking works as the case may be.
    When no JA grade officer exists in any deptt. of
    the division, DRM/ADRM should sign the
    application. In case of works of construction
    organization, whether civil engg or S T
    application will be signed by JA grade officer
    for CE/C or CSTE/C as the case may be.

16
  • In case of works involving civil engg ST
    both,application shall be signed jointly by both
    deptts. following instructions as given above.
  • Name designation of signatory should invariably
    be mentioned.

17
Documents to accompany application
  • Documents to accompany application are detailed
    in annexure 13/1 they should be complete in
    every respect.
  • A track certificate, indicating that track is
    suitable for maximum axle load there in, shall be
    given along with application, signed by Dy. CE
    (track) counter signed by CTE/CE

18
  • For a major bridge or when non standard girders
    or designs are used, Dy. CE / bridges should
    issue a certificate on form 13 /3 indicating that
    bridge is designed to carry axle loads proposed
    to run, along with application. This certificate
    is also counter signed by CBE /CE.
  • For the purpose of track bridge certificates as
    per annexure 13/2 13/3, COM should also be
    consulted in regard to types of locomotives
    rolling stock to be used, their axle loads
    speeds.

19
Submission of safety certificate
  • CRS in according sanction,may or may not propose
    to inspect the work.
  • If CRS decides to inspect the work prior to
    opening, he will, after inspection, communicate
    in writing his sanction to open the work.
  • If CRS decides not to inspect work, safety
    certificate in form 13/5 along with certificates
    referred to there in shall be submitted to CRS
    before work is opened. This will be done by
    engineer in charge of work

20
  • Safety certificate for engg works should be
    signed by ADEN counter signed by DEN. If any
    conditional sanction is given, it should be
    specifically certified that stipulated conditions
    are fulfilled
  • Safety certificate despatched to CRS
    expeditiously.

21
Deviations from plans approved by CRS
  • Prior approval of CRS is necessary,if, plans
    already approved by CRS have any deviations,
    especially, which affects layout of lines or
    arrangements of signals or working rules.

22
Application for running new type of
locomotive/rolling stock
  • Application in this case,in form xvii of rules
    2000 shall be made by CE one month in advance
    giving following details Load diagram,
    certificate for track strength, certificate for
    girder strength, speed clearance certificate
    issued by RDSO, reports of test runs /
    oscillation trials obtained from
    RDSO,infringements of max min dimensions for
    running locomotive or rolling stock. Certificate
    on form 13/4 signed jointly by CE CME in case
    of steam diesel locomotives and by CE and CEE
    in case of electric locos.
  • Certificate should also be signed by COM CSTE
    if max permissible speed is proposed to be
    raised.

23
Notification to rly officials when opening works
  • No new work affecting running of trains or
    traffic working at stations should be brought
    into use until staff of all departments have been
    notified by means of a circular issued by DSO /
    DOM

24
Works arising out of accidents including breaches
  • Abbreviated procedure as laid down in section 24
    of IR act 1989 is reproduced below
  • When accident has occurred resulting in temporary
    suspension of traffic, and either the original
    line and work has been rapidly restored to
    original standard, or a temporary diversion has
    been laid in absence of CRS, it should be opened
    for public carriage of passengers, subject to
    following conditions

25
  • Rly servant in-charge of work has certified in
    writing that opening of restored line and work or
    temporary diversion, will not, in his opinion be
    attended with danger to public using the line and
    work or diversion.
  • As soon as may be, notice by telegraph, of
    opening of line work or diversion sent to CRS

26
  • The certificate on form 13/6 in accordance with
    section 24 of rly act 1989 must be written out
    signed by representative of Engg Deptt in-charge
    of work before opening it. The certificate be
    despatched by telegram to officers concerned
    followed by confirmatory copies by letter.
    Engineering representative shall hand over a copy
    of certificate to representative of operating
    department at site of accident the latter will
    not permit the passage of traffic over restored
    road, until he gets this certificate.

27
  • Diversions should be tested by running a material
    train or light engines before opening to public
    traffic.
  • Certificate telegraph advice need not be sent
    to CRS if line is restored for through
    communication within 24 hours.If use of temp
    diversion is likely for more than 3 days, CRS may
    take earliest opportunity to inspect it.

28