Title: LCLS Photon Systems Status
1LCLS Photon Systems Status
John Arthur LCLS Photon Systems Manager
- Technical status and accomplishments
- Response to FY2007 continuing resolution
- LCLS/LUSI coordination
2Recommendations from Oct 2006
- Put effort into design of critical x-ray optics
components (mirrors and thin crystals) - Make LCLS Photon Systems and LUSI work together
to optimize designs and commissioning plans
Putting both recommendations into practice
3XTOD Status
- Still in advanced design phase
- Nearly all components at least through conceptual
review - Staying on schedule
- About to start major procurements
- Hardware installation can start 11-07
- LLNL team is working well with SLAC
4XTOD design for attenuators and x-ray intensity
monitors
4.5 meter long, gas attenuator high pressure N2
section
Upstream embedded gas detector
Embedded (Be) solid attenuators
Downstream embedded gas detector
5XTOD working with x-ray mirror vendors
vendor 2, loc. 1
vendor 1, loc. 1
LLNL Zygo 20 images of Si test substrates by two
vendors
0.37 mm
0.37 mm
LLNL full-aperture interferometry images of Si
test substrates by two vendors
Vendor 2
Vendor 1
6Effects of 2007 CR on XTOD
- Procurements and some design effort were delayed
- New plan was developed
- Commissioning optics in FEE ready for first light
- Beam transport to NEH ready by late FY2008
- All work on Tunnel and FEH delayed until FY2009
- All work finished by early FY2010
7XES Status
- In design phase
- AMO instrument design going well
- 2-d detector development going well
- Controls area was behind, catching up
- Working with Radiation Physics on PPS items
- Ready for installation starting 11-07
8Concept for AMO Instrument
Focusing optics
Experimental chamber
Diagnostics chamber
9X-ray shutter and mirror layout
From the LCLS operating modes Physics
Requirements Doc
10Effects of 2007 CR on XES
- Some design effort was delayed
- New plan was developed
- Safety and controls work in NEH ready late FY2008
- First-stage AMO instrument ready late FY2008
- Work in FEH delayed until FY2009
- Some AMO instrumentation delayed until FY2009
- All work finished by early FY2010
11LUSI-LCLS Integration Working Group
The Working Group was created by Keith Hodgson
and John Galayda to
- Define the interface between LCLS and LUSI
- Resolve issues overlapping this interface
- Formalize with Interface Control Documents
- Find common solutions to common problems
- Experimental instrumentation, diagnostics
- Standardization where appropriate
12Working Group Members
- Jerry Hastings (LUSI)
- John Arthur (LCLS)
- Yiping Feng (LUSI instrument scientist, controls)
- David Fritz (LUSI instrument scientist,
diagnostics) - Stefan Moeller (LCLS Endstation Systems Manager)
- Hal Tompkins (LCLS x-ray installation,
commissioning) - Other LCLS/LUSI staff as needed
Co-chairs
13Issues before the Working Group
- Experimental data flow and interface standards
- Vacuum hardware and controls standards
- Conventional facilities/hutches
- Installation/commissioning
14Summary
- XTOD and XES are still in design phase, though
XTOD is moving into procurement and XES will
follow soon - FY2007 continuing resolution forced some delays,
extension of project - Technical issues are being resolved with no big
problems - Should be ready for installation starting 11-07
- FEE, NEH ready in FY2009, FEH ready in FY2010
- Coordination with LUSI is going well, has been
formalized