Title: From Russia With Love:
1From RussiaWith Love
- Truly Integrated
- Project Scope, Schedule, Resource and Risk
Information - Vladimir Liberzon, PMP
- and Russell D. Archibald, PMP
2Need for Integrated Project Scope, Schedule,
Resource and Risk Information
- Project performance estimation that includes all
valuable factors - Reliable estimates of future project results
- Early warning of potential problems
- Proper motivation for activity performance
sequencing resource allocation
3Presentation Objectives
- Describe proven methods used in Russia
- Success Driven Project Management/SDPM Unique
aspects - Discuss its application on a sample project
- Compare SDPM with earned value critical chain
methods
4Success Driven Project Management/SDPM
- Planning Stage
- Calculate finish dates costs with the required
probabilities of their successful achievement - Set target dates, costs other restrictions
- Calculate success probabilities
- Determine contingency reserves
- Execution and Control
- Calculate current probabilities of achieving
goals - Track success probability trends
- Manage contingency reserves
5Success Probability
- System forecasts resulting required resources
contingency reserves based on user defined
acceptable probability of success to meet
specific scope, schedule cost targets - System calculates the probability of meeting
imposed targets (success probabilities)
6The Project Planning Dilemma
- Goals
- Complete project ASAP with minimum cost, also
- Develop plan with guaranteed 100 success
- But 100 plan will not be competitive today
7Resolving the Dilemma
- Competitive, realistic plan must
- Make success of project probable (something less
than 100) - But still make it acceptable to project
stakeholders - Requires evaluation negotiation of various
target success probabilities leading to
well-informed decision to proceed
8Resource Critical Path/RCP
- True (resource) critical path must reflect ALL
schedule constraints resource, finance, supply,
calendar, imposed dates - All constraints must be considered in both
forward backward passes
9All Project Information Is Inter-related
- Project scope affects schedule, resources, cost,
risk - On many projects this information is not truly
integrated because - Separation of responsibilities
- Most PM software does not properly integrate and
calculate it
10Eight Integration Methods Used
- Systematic scope definition (indentured
structures) - Network planning
- Resources
- Consumable, renewable, utilized produced
- Units, teams/crews, interchangeable units or
crews - Assigned to project activities
- Constraints in both forward backward passes
11Eight Integration Methods (Contd)
- Activity durations calculated scope or volume
rate - 5. True (resource) critical path calculated
- Logical schedule constraints
- Resource, financial supply limitations in both
the forward and backward passes
12Eight Integration Methods (Contd)
- 6. Risk uncertainties simulated probability
distribution for main project results (project
its main phases finish dates, costs, resource
requirements) - 7. Actuals reported compared, contingency
reserves tracked
13Eight Integration Methods (Contd)
- Current probabilities of success calculated and
trends determined for - Schedules
- Costs
- Resources
14Methods Unique to SDPM
- Multiple breakdown structures
- Resource information analysis
- Activity duration calculation or estimation
- Resource critical path, resource floats,
resource contingency reserves - Risk simulation success probability analysis
- Success probability trends
151. Multiple Project/Work Breakdown Structures
- Life cycle
- Deliverables
- Physical areas
- Responsibilities
- Functional type of work
- Cost account
- Contract
- Others
162. Resource Information Analysis
- Two types
- Consumable materials, supplies other
expendables - Renewable labor, equipment, facilities
- Units, teams, or assignment pools
- Norms for resource productivity
- May be utilized or produced
173. Activity Duration Calculation or Estimation
- Activity volume is estimated (any measurable
units) - Volume often used as initial estimate duration
calculated using resource productivity factors - Uncertainties forecast by varying productivity
factors
184. Resource Critical Path
- True critical path reflects ALL schedule
constraints - Network logic, resource, finance, supply,
calendar, imposed dates - Activity float must reflect ALL constraints
- Most PM software packages ignore resource
constraints on backward pass incorrect critical
path
194. Resource Critical Path/RCP (Contd)
- Activity resource float resource critical path
reflect resource constraints during backward pass - Activity resource float can be used feasibly
- Shows possible delay considering set of available
resources - Adding financial supply constraints to the
Critical Chain definition you then have RCP
205. Risk Simulation Success Probability Analysis
- Single, deterministic estimates produce plans
with low probability of success - Risk simulation produces more reliable results
- Risk simulation may be based on Monte-Carlo
approach (impossible to use for large projects)
or based on 3 scenarios approach
215. Risk Simulation Success Probability Analysis
(Contd)
- 3 estimates are made for
- Resource usage or productivity rates
- Work scope volume
- Activity duration (if estimated directly)
- Cost estimates
- Calendar/weather variation
225. Risk Simulation Success Probability Analysis
(Contd)
- Identified risk events are estimated to reflect
their consequences, including risk response plans
in optimistic, most probable or pessimistic
project scenarios. - All three scenarios are calculated.
- The probability curves are rebuilt using the
three values obtained.
235. Risk Simulation Success Probability Analysis
(Contd)
- Determine the desired probability of meeting
project finish dates, costs and resource
requirements - Obtain desired project finish date, budget,
resource requirements - These data form basis for negotiating approval
to proceed
245. Risk Simulation Success Probability Analysis
(Contd)
- Negotiations may establish new targets
- Success probability is defined as the probability
of meeting approved targets - Dates, cost, quantity
- Success probability is the best indicator of
current project status during execution
255. Risk Simulation Success Probability Analysis
(Contd)
- Target schedule is the backward (from the target
dates) resource constrained schedule using most
probable estimates - The optimistic schedule is used for setting task
schedules for project implementers - Contingency reserves or buffers
- Difference between activity start times (or cost,
material requirements) in the optimistic and
target schedules
266. Success Probability Trends
- Success probabilities are calculated periodically
stored - Their trends show current project status
- Negative (downward) success probability trend
indicates corrective action needed - Positive success probability trend indicates
performance is OK
276. Success Probability Trends (Contd)
- Success probabilities change due to
- Performance results
- Scope changes
- Cost changes
- Risk changes
- Resource changes
286. Success Probability Trends (Contd)
- Project managers are encouraged to solve
uncertainties ASAP - This can increase success probabilities even with
activity finish delays cost overruns - Postponing problem activities leads to negative
trends in success probabilities - This attribute of success probability trends is
especially useful in new product development
project management
29Illustration Software Purchase Project
- Our forum discussion now turns to sample project
Software Purchase - This project consists of 10 activities including
2 milestones and uses 3 resources - Resource productivities were estimated with 30
reliability. Thus productivities in the
pessimistic version were 30 lower and in the
optimistic version 30 higher than in the most
probable version
30Illustration Software Purchase Project
Target Schedule
31Illustration Software Purchase Project
- Lets assume that the actual productivity of the
expensive resource was 20 higher than estimated
and the low cost resource worked with a 20 lower
productivity than expected - Lets consider the most probable version as the
baseline. The baseline cost is 66,220, Target
cost (57 probability) is 70,000 - Next slide shows the success probability trends
if our assumptions were true
32Success Probability Trendsfor Software Purchase
Project
33EVA Trendsfor Software Purchase Project
- Next slide shows Cost Performance Index/CPI
Schedule Performance Index/SPI trends for the
Software Purchase project
34CPI SPI Trendsfor Software Purchase Project
35SDPM and Earned Value Analysis
- SDPM success probability trends reflect
performance results plus network dependencies
project risks - EVA reflects only performance results
- In the Sample project
- SPI exceeds 100 on August 11
- But on August 11 SPDM shows the probability of
meeting baseline finish date is equal to zero
(next slide)
36Success Probability Trendsfor Software Purchase
Project
37Earned Value Analysis
- EVA approach is not totally integrated
- EVA considers sunk costs but not
- Network logic dependencies
- Project risks
- Resource performance
- EVA problems are illustrated in the following
slides for the sample project
38Sample Project Gantt Chart
39EVA of Sample Project
- If activity 3 is started first (in spite of the
Gantt chart schedule) then after the first week
the SPI will be 10 or 1000 - But on-schedule completion will be impossible!
40EVA of Sample Project
Parameter Value
AC 100
EV 100
PV 10
SV 90
CPI 1
CPI 100
SPI 10
SPI 1000
41Using EVA
- Recommend applying EVA to critical path
activities only - Cannot use EVA from one project phase to forecast
results of another phase if resources are
different.
42Common Features SDPM Critical Chain Method/CCM
- Resource critical path is the same as Critical
Chain if we add financial and supply constraints
to the Critical Chain definition - CC project buffer is analogous to SDPM
contingency time reserve - Resource float is analogous to CC feeding
buffers - Both approaches recommend using optimistic
estimates to set schedule
43Differences With Critical Chain
- Dont agree that one should always avoid
multi-tasking - Dont accept CC assumptions that
- Critical chain never changes
- Only one project drum critical resource
exists - Our experience critical resources change in
different project phases
44Differences With Critical Chain
- CC more qualitative than quantitative
- Time cost reserve usage evaluation
- SDPM Success probability trends show if reserves
expended faster or slower than planned more
effective than - CC Qualitative judgment whether buffers were
properly utilized
45Recommendations for Implementing SDPM
- Simulate uncertainties to obtain probability
distributions - Set desired target probabilities, then calculate
requirements to meet them - Use these data to negotiate realistic commitments
46Recommendations for Implementing SDPM (Contd)
- Set agreed target dates costs, calculate
success probabilities - Set optimistic targets for project implementers
and manage calculated contingency reserves
47Recommendations for Implementing SDPM (Contd)
- Control risks, revise recalculate success
probabilities reflecting progress, changes,
risk estimation updates - Manage with success probability trends
- Negative trends take corrective action
regardless of current level of success
probabilities
48Conclusions
- For effective project management, truly
integrated information is required - Scope
- Schedule
- Resources
- Cost
- Risk
49Conclusions (Contd)
- Truly integrated information is practical to
produce - Identifying the resource critical path and
calculating success probability trends help to
produce more successful project performance
50Are These Methods Practical?
- Over past 10 years SDPM was successfully applied
to hundreds of projects in - Spider Project software automates the process
Aerospace Defense Banking Defense Engineering Construction Manufacturing Metallurgy Oil Gas Ship Building Software Development Telecommunications Others
51Questions?
- As time permits now,
- During the remainder of the Congress
- Via e-mail/Web
- Vladimir Liberzon spider_at_mail.cnt.ru
- Russ Archibald archie_at_unisono.net.mx
- Info on Spider Project package
www.spiderproject.ru
52Thanks for Listening
- We appreciate your comments
- We look forward to further feedback and exchange