Title: PITFALLS OF CODE ENFORCEMENT
1PITFALLSOF CODE ENFORCEMENT
- Stephanie E. Karr
- Curtis, Heinz, Garrett OKeefe, P.C.
- St. Louis, Missouri
2Exercise of Police Power
- Code Enforcement is a mechanism to protect the
public health, safety and welfare. - Code Enforcement, when utilized properly, falls
under the umbrella of the citys police power.
3- A nuisance is a condition which causes a hazard
or some detriment to the public health, safety
and welfare
4LACK OF CAUSAL CONNECTION
5Causal Connection
- A causal link must be shown between the alleged
violator and the alleged nuisance. - City of St. Louis v. Benjamin Moore Co., 226
S.W.3d 110 (Mo. 2007) (nuisance action to recover
costs for abatement of lead paint in homes) - City of St. Louis v. Varahi, Inc., 39 S.W.3d 531
(Mo.App.E.D. 2001) (city failed to prove that
hotel's hourly rental policy, reputation and
arrests in vicinity of hotel caused public
nuisance of prostitution on street outside
hotel)
6PROCEDURAL DEFICIENCIES
7Abatement
- If the property owner fails to remedy the
nuisance, the city may take action to abate the
nuisance - The costs incurred by the city in abating the
nuisance may be recovered from the property owner
by issuance of a Special Tax Bill such costs
are a lien on the property.
8General Proceduresfor Abatement
- Written Notice reasonably calculated to reach the
intended recipients - Opportunity for owner or possessor to be heard by
representative of the city - Reasonable time for abatement by owner/possessor
reasonable time depends on the condition to
be abated and other considerations such as
weather conditions - Findings and determination of nuisance after
hearing
9Statutory Procedures
- Section 67.398 Any ordinance authorized by
this section may provide that if the owner fails
to begin removing or abating the nuisance within
a specific time which shall not be less than
seven days of receiving notice that the nuisance
has been ordered removed or abated, or upon
failure to pursue the removal or abatement of
such nuisance without unnecessary delay, the
building commissioner or designated officer may
cause the condition which constitutes the
nuisance to be removed or abated.
10Statutory Procedures
- Section 71.780 Such nuisances may be
suppressed by the ordinances of said cities, or
by such act or order as the charters of said
cities authorize them to adopt.
11Statutory Procedures
- Section 71.285 Expedited procedures for
abatement of high grass and weeds and litter and
trash in certain cities
12Statutory Procedures
- Section 67.400 and 67.410 Vacation, Repair or
Demolition of Dangerous Buildings
13Section 67.450
- In the event any building or structure is
wrongfully demolished by a cityor is demolished
without adhering to the procedures provided in
sections 67.400 to 67.450, the cityshall be
liable for damages as determined by a court of
law in a suit brought by the party so damaged. - This section does not require ownership of the
building in order to recover for wrongful
demolition and, therefore, does not preclude
damages and recovery by non-owners, including
tenants, lien holders, or other interested
parties.
14Defective Notice
- Arbogast v. City of St. Louis, 285 S.W.3d 790
(Mo.App.E.D. 2009) - June, 2000 Plaintiff buys and moves into
property - May, 2001 Fire damages structure
- Plaintiff moves out and registers change of
address - with Post Office (did not register new address
with Assessors Office) - July, 2001 Mail to Plaintiff is returned to
sender with notification of new address
15July 2001 July 2002 Plaintiff receives mail at
new address including mail from other City
departments August and October, 2001 City had
to board up building twice because of
squatters and others who removed boards and
other items from property October,
2001 Citys Building Department served notice of
condemnation and potential demolition on
Plaintiff by posting it on the damaged
structure and by regular mail to the subject
property Deadline to appeal notice or to
remedy violation was October 29, 2001 Mailed
Notice was returned to City No appeal was
filed February, 2002 Structure demolished
16On Plaintiffs action for wrongful demolition,
jury awarded Plaintiffs 65,000 Action not
dismissed for failure to exhaust administrative
remedies because of defective notice that rule
does not apply when the government fails to
provide parties with notice and an opportunity to
be heard in accordance with the requirements of
due process.
17Sufficient Notice
- Government must provide notice reasonably
calculated, under all the circumstances, to
apprise interested parties of the pendency of the
action and afford them an opportunity to present
their objections. - If the government becomes aware prior to a taking
that its attempt at notice has failed, due
process requires the government to take further
reasonable steps if any are available.
18Sufficient Notice - Posting
- in most cases, the secure posting of a notice
on the property of a person is likely to offer
that property owner sufficient warning of a
pendency of proceedings possibly affecting his
interests. - posted service accompanied by mail service is
constitutionally preferable to posted service
alone. - Quoting Greene v. Lindsey, 456 U.S. 444, 102
S.Ct. 1874, 72 L.Ed.2d 249 (1982)
19Sufficient Notice - Mail
- Under most circumstances, notice sent by mail is
deemed reasonably calculated to apprise
interested parties that their property rights are
in jeopardyBut in some special circumstances,
mailed notice may be inadequate - 1. government knows that the party does not
reside at the address and does not have access
to the address - 2. recipient is known to be a person who
cannot understand the notice - 3. government learns the mailed notice is
returned by the post office before the
taking occurs
20Reasons Why Citys Notices Failed
- Posted Notice failed
- It was likely that Plaintiff did not see the
posted notice (inspector acknowledged that
squatters and vandals frequently removed boards
and notices from condemned buildings in the area
and that, in fact, City had to board the building
up at least twice within 3 months) - Mailing failed
- Mailed notice was returned to the City. Other
City departments accomplished mailings to
Plaintiff. - City had other avenues to reach Plaintiff
21Lack of Notice to Mortgagee
- First National Acceptance Company v. City of
Utica, New York, 612-CV-1622 (N.D. New York) - Pending Case
- Mortgage Company filed 1983 action against City
for demolishing structure subject to Deed of
Trust without notice to the company and an
opportunity for the company to be heard. - Last month, Court denied citys Motion for
Summary Judgment on procedural due process claims
and granted mortgagees Motion for Summary
Judgment.
22Municipal liability is limited under Section 1983
by Monell v. Dept of Social Services, 436 U.S.
658, 98 S.Ct. 2018, 56 L.Ed.2d 611
(1978) Municipal liability exists where the
citys policies or customs led to an independent
constitutional violation. If a plaintiff shows
that the citys policy or custom was the
moving force behind the violation, then he/she
will prevail. Here, the City of Utica did not
require its code enforcement officers to search
real estate records, determine the identity of
mortgagees and provide them of notice of any
process that could lead to destruction of a
significant asset on the property. The
violation of mortgagees rights was a result of
an official policy or custom therefore, City
subject to 1983 liability.
23Defective Hearing
- Village of Blodgett v. Rhymer, 279 S.W.3d 242
(Mo.App.S.D. 2009) - July 2005 storm caused the roof of defendants
building to cave in - One Month later letter sent to owner ordering
him to remedy and remove the dangerous building
or appear before the Municipal Courtto be heard
and present evidence as to why defendant is not
in violation of the Ordinance.
24Three months later City demolishes building but
leaves basement portion and debris January, 2006
City sends 2nd letter to defendant ordering him
to remedy the existing conditions February 4,
2006 defendant appears at Board meeting and
asked if installing fence would remedy the
violations February and March, 2006 letters to
defendant ordering him to perform the work April
2006 City pays to have basement filled and
debris removed
25City cannot recover abatement costs
- In Citys action to enforce its tax lien, the tax
lien was determined to be invalid because
defendant was not afforded an adequate hearing - no hearing was ever scheduled for Appellant.
Rather, Appellant took affirmative steps to
attend a regular meeting of the board of
trustees. It is unclear from the record what type
of process Appellant received there, but what is
clear is that Village never provided Appellant
with the type of hearing required by either of
its ordinances.
26No Adequate Hearing
- Goe v. City of Mexico, 64 S.W.3d 836 (Mo/App.E.D.
2001) - Process to demolish dangerous structure.
- Section 67.410 requires ordinance to provide for
a full and adequate hearing upon the matter,
giving the affected parties at least ten days
written notice of the hearingAfter the
hearingsthe building commissionershall issue an
order making specific findings of fact, based
upon competent and substantial evidence, which
shows the building or structure to be a nuisance
and detrimental to the health, safety, or
welfare
27Opportunity to ask for hearing is not enough
- Following the code officials original notice and
order to demolish the structure, the aggrieved
party had the right to appeal the decision of the
code official. - If no appeal was requested, then no hearing was
held. - Because the demolition ordinance did not provide
for a hearing to be held automatically, it did
not comply with the requirements of section
67.410 and was therefore invalid. - Owner did not waive due process challenge by not
appealing the original decision. - Trial courts dismissal reversed and cause for
damages remanded.
28Defective Notice and Hearing
- McNeill v. City of Kansas City
- Building on Citys dangerous building list since
August, 2001 - McNeill purchased property in 2008 and then
- - paid delinquent taxes and fees for the
property - - notified the City of his plans to renovate
- - began renovating by obtaining architectural
plans, gutting the building, removing the old
roof, re-decking the roof, reframing the
building and demolishing the brick and concrete
patio which had collapsed - By June, 2009, work stalled because of trouble
with McNeills construction loan
29June 2009 City sends letter to McNeill
instructing him to remove some debris that was
sitting on the property along with weeds that had
begun to grow there June 24, 2009 McNeill meets
with code enforcement inspectors and
representatives. McNeill tells them of his plans
to obtain other financing. Code enforcement
informs McNeill that he will have more time to
obtain financing and instructs him to remove a
pile of debris on the side of the
building. July, 2009 McNeills contractor
removed the debris and graded the yard. Upon
completion, McNeill notified code enforcement on
July 20, 2009. July 31, 2009 McNeill receives
preliminary commitment for a construction loan
and began notifying subcontractors. August 8,
2009 City demolished the building without
having any further contact with McNeill,
disregarding the policy of the Dangerous
Buildings Division to send the property owner a
pre-demolition notice.
30 McNeill sues the City for wrongful demolition
under Section 67.450 and City files counterclaim
seeking the costs incurred with respect to the
demolition
31Initial jury trial - 4 days Judgment in favor of
McNeill Damages 150,000 Motion for New Trial
granted / affirmed (372 S.W.3d 906) (Flawed jury
instruction) 3 day jury trial April 15, 2014
April 17, 2014 Judgment in favor of
McNeill Damages 151,000 for property
damages 55,000 for personal injury Prejudgment
interest (9) on property damage amount
commencing September 2, 2010 Costs assessed to
City 1,900.65
32Defective Findings and Conclusions
- Woodson v. City of Kansas City, 80 S.W.3d 6
(Mo.App.W.D. 2002) - Department issued order to demolish storage
garage which was appealed to the Citys Property
Maintenance Appeal Board. The Board held
evidentiary hearing. - Following evidence, the Board voted and issued
Findings and Conclusions merely affirming the
previous demolition order. The Board did not set
forth specific conditions and defects which
caused the garage to be dangerous.
33Ordinance set forth several conditions which
showed a structure to be dangerous, such
as 1. The exterior walls or other vertical
structural members list, lean or buckle to such
an extent that a plumb line passing through the
center of gravity does not fall inside the
middle one-third of the base. 2. A portion
thereof has wrecked, warped, buckled or settled
to such an extent that wall or other structural
portions have materially less resistance to
winds or snow Neither the Departments
demolition order or the Boards decision made
findings which set forth these conditions to
support a decision that the building was
dangerous. Case remanded back to Board with
instructions to remand matter to department for
specific findings as to particular conditions of
building. Demolition delayed.
34NO WARRANT
35Administrative Search Warrants
-
- Camara v. Municipal Court of the City and County
of San Francisco, 387 U.S. 523 87 S.Ct. 1727, 18
L.Ed.2d 930 (1967) -
- Bezayiff v. City of St. Louis, 963 S.W.2d 225
(Mo.App.E.D. 1997) -
-
36Warrants
- Necessity of warrant
- Requirements
- Probable cause
- Affidavit
- Application for the warrant
- Definition of area and work covered
- Warrant
- Execution
- Return
37Process Is Not MeantTo Be Easy
- An individualized review is necessary to
provide the traditional safeguards which the
Fourth Amendment guarantees to the individual.
38Public goals and need for expediency considered
- Camara
- it is vigorously argued that the health and
safety of entire urban populations is dependent
upon enforcement of minimum fire, housing, and
sanitation standards, and that the only effective
means of enforcing such codes is by routine
systematized inspection of all physical
structureswe think this argument misses the
mark. The question is not, at this stage at
least, whether these inspections may be made, but
whether they may be made without a warrantIt has
nowhere been urged that fire, health, and housing
code inspection programs could not achieve their
goals within the confines of a reasonable search
warrant requirement.
39Liability Considerations
- Is it the policy or custom of the City NOT to
obtain warrants? - Procedure to obtain warrants
- Adequate training of code enforcement officers
- No Qualified Immunity
- Haefner v. City of Philadelphia Summary
Judgment based on qualified immunity of
inspector and Department Head denied - Camara case was decided in 1967
- building code inspector had been involved in
another - lawsuit concerning lack of warrant
- city had warrant provisions in Code
- City had conducted training session
- Department Head did not object to employees
conduct -
40SELECTIVE ENFORCEMENT AND SUMMONS OVERKILL
41Generally, the failure of municipal authorities
to enforce a zoning ordinance against some
violators does not preclude its enforcement
against others. Kansas City v. Wilhoit, 237
S.W.2d 919 (Mo.App. 1951). But, selective
enforcement or using the process to a greater
extent than is necessary may lead to a Section
1983 action. Williams v. City of Carl Junction,
Missouri, 480 F.3d 871 (8th Cir.
2007) and 523 F.3d 841 (8th Cir. 2008) (award
of attorneys fees to City reversed) Garcia v.
City of Trenton, Missouri, 348 F.3d 726 (8th
Cir. 2003)