Networks - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Networks

Description:

Networks Adding to our Project – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 25
Provided by: OWCC1
Category:
Tags: networks | pert

less

Transcript and Presenter's Notes

Title: Networks


1
Networks
  • Adding to our Project

2
PERT and CPM
  • PERT
  • Program Evaluation and Review Technique
  • Activity on Arrow (arc)
  • CPM
  • Critical Path Method
  • Activity on Node
  • See Chapter 6
  • Note that it prefers the AoN, we will still do
    AoA
  • Spend more time with the conceptual in the chapter

3
Network Diagrams
  • Describe work in terms of sequences, Activities
    and events
  • All derive from simple logic diagrams
  • Must know
  • Activities
  • Dependencies
  • Durations

4
AoN vs. AoA
  • Activity on Node
  • Activity represented by a node
  • Arrows show precedence
  • Finish to Start
  • Start to Start
  • Finish to Finish

5
AoN vs. AoA
  • Activity on Arrow (Arc)
  • Activity represented by an arrow
  • Arrows and Dummys show precedence
  • Finish to Start
  • Start to Start
  • Finish to Finish

6
Steps
  • Some trial and error!
  • Start with activity that has no predecessors
  • Add nodes for activities with start predecessor
  • And so-on and so-on

7
Slack
  • Difference in the latest allowable date and the
    earliest possible date
  • Activities with slack are where we can manage!

8
Standard Labeling
  • EF Early Finish
  • Earliest possible Finish date of event
  • LF Late Finish
  • Latest possible Finish date for an event without
    extending the due date for a project
  • S LF - EF
  • Time we can wait (time we can manage!)

9
Standard Labeling
  • ES Early Start
  • Earliest possible Start date of event
  • LS Late Start
  • Latest possible Start date for an event without
    extending the due date for a project
  • S LS - ES
  • Time we can wait (time we can manage!)

10
Depiction on Chart
Name or Identification
Early Start
Early Finish
A(8,10)
2(15,17)
Duration
Late Finish
Late Start
11
Example
  • Activity Predecessor Duration
  • A -- 3
  • B -- 2
  • C A 3
  • D A 7
  • E B 5
  • F C 6
  • G D,E 5

12
Draw the Network
  • Activity on Arrow

A
S
B
13
Draw the Network
  • Activity on Arrow

C
A
D
S
B
E
14
Draw the Network
  • Activity on Arrow

C
A
F
D
F
S
B
G
E
15
Steps Front Pass
  • All numbers at start are 0
  • Front Pass
  • Early Start (ES) is the Highest of the Early
    Finishes for all predecessors
  • Early Finish (EF) for an activity
  • ES for an activity its own duration
  • EF/LF for finish is always the same

16
Steps Back Pass
  • All numbers at Finish are equal to the highest
    early finish of predecessors
  • We will find late start and late finish
  • Late Finish (LF) for an activity
  • Lowest of late starts of all successors
  • Late start (LS) is LF its own duration

17
Slack
  • Slack LF EF
  • Slack LS ES
  • These should be the same
  • Critical Path is where slack is 0

18
Depiction on Chart
Name or Identification
Early Start
Early Finish
A(8,10)
2(15,17)
Duration
Late Finish
Late Start
19
Draw the Network
  • You make the call!

C(3,6) 3(6,9)
A(0,3) 3(0,3)
F(6,12) 6(9,15)
D(3,10) 7(3,10)
F
S
G(10,15) 5(10,15)
B(0,2) 2(2,5)
E(2,7) 5(5,10)
20
Cost
  • Duration of activities can be affected by
    resources expended
  • The expected range of cost varies
  • There is a relationship that can be defined by a
    function
  • We will stick to linear relationships

21
Crash
  • We define these relationships
  • Range between costs at normal time and the
    fastest possible time (Crash)
  • Normal time/Crash time TN/TC
  • Normal Cost/Crash Cost CN/CC
  • Cost Slope

CC - CN Cost slope TC - TN
22
Cost Slope
Activity TN TC CN CC A 8 5 9
18
CC - CN Cost slope TC TN
18 - 9 5
8 -3
Cost of Activity
18
9
5
8
Duration of activity
23
Cost Slope
  • Slope of -3 means?
  • For every day (unit of time) that you speed up
    and activity it will cost you 3
  • Each activity can be sped up
  • It costs money!
  • Where do we want to spend our money??

24
Assignment
  • Do a network of your project.
  • Activity listing with
  • Durations (normal/crash)
  • Predecessors
  • Costs (normal/crash
  • ES, EF, LS, LF for normal durations
  • Suggest a cost savings step in your project
Write a Comment
User Comments (0)
About PowerShow.com