Title: Southeastern Inter-Regional Planning Update (SIRPP)
1(No Transcript)
2Southeastern Inter-Regional Planning Update
(SIRPP)
Entergy Transmission SummitAugust 11, 2009Astor
Crown PlazaNew Orleans, Louisiana
3Presentation Overview
- SIRPP Southeast Inter-Regional Participation
Process - www.southeastirpp.com
-
4SIRPP consist of the following members
- Southeastern Region (SERTP)
- Power South
- Dalton Utilities
- Georgia Transmission Corporation (GTC)
- Municipal Electric Authority of Georgia (MEAG)
- South Mississippi Electric Power Association
(SMEPA) - Southern Companies
- Duke Energy Carolinas
- Entergy Companies
- E. ON U.S.
- Progress Energy Carolinas
- Santee Cooper
- South Carolina Electric Gas (SCES)
- Tennessee Valley Authority (TVA)
5SIRPP Activity
- November 13, 2008 Stakeholders Conference Call
to discuss study scope - March 16, 2009- Stakeholders Conference Call to
finalize scope of revised study - August 19, 2009- Review/Present Report of Step 1
Study Results to Stakeholders - Q4 2009- Final Posting of Step 1
- Q1 2010- Process for Step 1 and 2 begins
6STEP 1 Study Assumptions
- Methodology
- Run Study Case (A) without transfer, and (B) with
transfer. Each Transmission Owner applies TPL
criteria to identify upgrades in Case B vs.
upgrades in Case A. - Upgrades associated with Transfer
- Compare Case B vs. Case A to identify any
upgrades at 115 kV and above - Comments
- Upgrades are identified by each Transmission
Owner that experiences a flow impact using its
TPL criteria. Upgrades would be identified
independent of any ultimate contract path
selected
7Stakeholders Comments to Transmission Owners on
the Five Economic Scenarios
- Stakeholders would like each scenario to be
looked at in a way that identifies the upgrades
needed on the collective SIRPP systems to
accommodate the requested economic transfer. - The stakeholders are looking for a flow-based
analysis as opposed to a contract path based
analysis. - For example, on the requested 3000 MW PJM Classic
to SOCO transfer, simulate a 3000 MW generation
increase in PJM Classic and 3000 MW generation
decrease in SOCO and determine - How the 3000 MW of flow distributes across the
system (i.e., how much flows through TVA, though
Duke, through Entergy, through systems outside
the SIRPP, etc.) - What are the limitations / associated upgrades
identified on the SIRPP systems
8SIRPP Step 1 Economic Studies for 2008/2009
GA Integrated Transmission System (GAITS)
2000 MW
Entergy
3000 MW
PJM (classic)
Southern Company
2000 MW
PJM (west)
Southern Company
3000 MW
Southern Company
PJM (classic)
5000 MW
SPP
SIRPP
9For additional information or to sign up to be
part of SIRPP
10Southeast Regional Transmission Planning Process
(SERTP)
- December 16, 2008 Final 2008 study results were
presented at Southeast Transmission Summit
available on SERTP website http//www.southeaster
nrtp.com/ - March 25, 2009 2009 transfer studies selected
- Savannah gt GA 60, AL 20, MS 20 - 1000 MW
- Gulfport gt Georgia - 1000 MW
- Ties to SCEG gt Georgia - 1000 MW
- Murray 500 gt Florida Border - 650 MW
- Washington County gt Georgia - 5000 MW
- June 24, 2009 Presentation of Southeast
Expansion Plan - 2009Q4 Final 2009 study results will be
presented at the Southeastern Transmission Summit
date/location TBD
11Eddie FilatSenior Engineer, ICT
Planning501-688-1708efilat_at_SPP.org
Questions / Comments