Title: Quality Assurance and NSTX/U Startup
1NSTX-U
Supported by
Quality Assurance Readiness for Operations Review
Coll of Wm Mary Columbia U CompX General
Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar
MIT Lehigh U Nova Photonics Old
Dominion ORNL PPPL Princeton U Purdue U SNL Think
Tank, Inc. UC Davis UC Irvine UCLA UCSD U
Colorado U Illinois U Maryland U Rochester U
Tennessee U Tulsa U Washington U Wisconsin X
Science LLC
Culham Sci Ctr York U Chubu U Fukui U Hiroshima
U Hyogo U Kyoto U Kyushu U Kyushu Tokai
U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res,
Kiev Ioffe Inst TRINITI Chonbuk Natl
U NFRI KAIST POSTECH Seoul Natl
U ASIPP CIEMAT FOM Inst DIFFER ENEA,
Frascati CEA, Cadarache IPP, Jülich IPP,
Garching ASCR, Czech Rep
Judy Malsbury, Head of QA
Princeton Plasma Physics Laboratory NSTX Upgrade
LSB B318 December 9-11, 2014
2PPPL Quality Assurance
- Independently funded by overhead, not NSTX/U
- Procurement QA
- gt200 separate procurements for NSTX/U
- Helps assure that quality requirements for
procurements are properly specified and
satisfied, e.g. baffles, lead extensions,
windows, coatings, mirror assemblies, . - Suspect and counterfeit items
- Receipt Inspection New position added for
NSTX/U as a result of a problem vendor. - Performs supplier visits to detect problems early
in the manufacturing process - Performs receipt inspection at PPPL to assure
that we received what we ordered.
3PPPL Quality Assurance (contd)
- Quality Control
- Monitors work in the field to assure compliance
with requirements - Covers welding, permeability, electrical
installations, critical lifts, control of
configuration - Audits and Assessments
- Programs, processes, and events
- Technical, quality, and ESH related
- Causal analyses
- Tracking and verification
- Corrective actions from audits/assessments/causal
analyses, NCRs, ORPS/NTS action items, design
review chits - Generates agenda for and minutes from monthly
Assessments and Actions Items Meetings - 781 lbs of weld wire was bought by PPPL for
welding on the vessel.
4NSTX/U Startup Process Audit
- Performance Objective PPPL is able to
demonstrate that it has successfully performed or
will be ready to perform the defined start-up
tests for NSTX prior to the scheduled start-up. - Governing documents
- OP-NSTX-02, Rev. 14, Start Up of NSTX-U (draft)
and associated spreadsheet of procedures and
documentation status - OP-NSTX-12, Rev. 5, NSTX Operations Training
- A snapshot review of the readiness of the project
to perform a start-up review - Performed last half June, 2014
- Report dated July 11, 2014
- Audit requested by the Chair of the ACC
5Observation 1 - Procedures
- At the time of the audit (June 2014), the
schedule for performing pre-operational test
procedures was not well defined. - Audit recommendation was to generate and maintain
a tracking system for all the procedures. - The project developed a tracking spreadsheet
(excerpt shown)
6Observation 2 - Training
- The audit team questioned the training for COEs
and Physics Operators adequate given the high
energy levels that NSTX/U will achieve and the
new systems being installed. - The project response indicated that
- The COEs are trained by the cognizant system
engineers (and in some cases, are in fact the
system engineers) prior to operation including
"at-the-controls" training during testing. - The Physics Operations will direct previously
approved machine or experimental proposals, but
all machine operating limits remain under the
control of the COE and engineered protection
systems.
7Observation 3 Design Issues
- At the time of the audit, it was not clear if all
design issues, identified via design chits, would
be resolved prior to installations and
operations. - The project response indicated that design review
chits were diligently being tracked with closure
confirmed by QA.
8Questions?