Malpasset dAm Failure - PowerPoint PPT Presentation

1 / 8
About This Presentation
Title:

Malpasset dAm Failure

Description:

December 2, 1959, France Manh Tung Nguyen, James Neville Introduction to The Dam Geology Profile The Failure Engineering Solution – PowerPoint PPT presentation

Number of Views:633
Avg rating:3.0/5.0
Slides: 9
Provided by: Richard1926
Category:

less

Transcript and Presenter's Notes

Title: Malpasset dAm Failure


1
Malpasset dAm Failure
  • December 2, 1959, France

Manh Tung Nguyen, James Neville
  • Introduction to The Dam
  • Geology Profile
  • The Failure
  • Engineering Solution

2
Malpasset Dam
  • Southeast of France in the Var Region, the dam
    was founded on the River Reyran, 7km NE of Frejus
  • Designed by Andre Coyne, the God of arch dam
    designs
  • A double curvature arch dam with a height of 60 m
    and a crest length of 223 m
  • Began construction in April 1952 and finished in
    1954

3
Site Geology
  • The dam is situated in the crystalline Tanneron
    Massif.
  • Mainly metamorphic gneissic rock
  • Massive Augen Gneiss
  • Schistose Gneiss

Gneiss
  • General trend of foliation lies between 30o and
    50o to SW

Schist
  • Two set of faults form a wedge failure at the
    left abutment.
  • Geological foliation at left abutment almost
    parallel to the arch thrust of the dam.

Mined Coal Deposits
4
The Failure
  • Exceptional rainfall levels, Autumn 1959
  • 9.30pm 2nd Dec, 1959. Sudden failure without
    warning
  • 50,000,000 m3 of water released
  • Water wall of 40m height, moving at 20m/s
  • Causes flooding in Frejus , 7km downstream
  • Over 400 people was killed instantly and rising
    to 700.

5
Causes of Failure
  • Concentrated arch thrust at left abutment
  • Deformation and crack forming at the bottom of
    the left abutment.
  • Seepage under the dam, hence uplift force
  • Separation of right abutment from foundation rock
  • Evidence of uplift below right abutment

15m
6
Engineering Solutions
  • Engineering solutions at the time were, TO DO
    NOTHING!
  • Nothing was done which has caused the uplifting
    of the a dam section due to the hydrostatic
    pressure.
  • Only FOS designed for the dam was mass shear and
    relatively weak rock has a large margin.
  • A vibratory wire extensometer was embedded in the
    concrete, this was deemed efficient.
  • This failure radicalized dam design bringing
    design attention to
  • - Mechanical effects of water seeping into the
    foundation.
  • - Normal practice to make a methodical
    inventory of the rock structure in depth.

7
Overcoming Seepage
  • Little work can to increase the friction of the
    fault line in the in rock due to the hydrostatic
    pressure, a more applicable dam design would have
    been more appropriate for the insitu case.
  • However another method would be to reduce the
    Hydrostatic pressure to prevent the uplifting of
    the wedge of rock.
  • Method 1)
  • Grout the foundation rock of concrete gravity
    dams.
  • Grouting will reduce seepage through the rocks
    and disclose
  • the presence of any unsuspected weaknesses in
    the foundations

8
Overcoming Seepage
  • Most Common Design- Grout Curtain.
  • Single line of grout holes located near the
    upstream face of the dam at 5 foot centre's.
  • A corresponding line of drainage is drilled a few
    feet downstream from the grout curtain.
  • Essential to control the grouting pressures so
    that splitting and lifting of rock will occur.
Write a Comment
User Comments (0)
About PowerShow.com