Title: RELATIONSHIP-OBJECTIVE ANALYSIS
1RELATIONSHIP-OBJECTIVE ANALYSIS
- Getting Full Value From Earned Value With a
Value-Added Way of Looking at Performance
Measurement
Presented By Will Gran Windmill International,
Inc. Nashua, New Hampshire 03060-5830 (603)
888-5502
Presented at the 14th Annual International
Integrated Program Management Conference Tysons
Corner Sheraton Premiere Hotel November 19, 2002
2Value-Added From Earned Value
- Review some basics
- Traditional analyses
- Line graph presentation
- EAC formula
- Relationship-Objective Analysis
- Variances
- Efficiencies
- Resource use rates
- Estimates at completion
- Some closing thoughts . . .
3When I Say . . . I Mean . . .
- Planned Value BCWS
- Completed Value BCWP
- Resources Used ACWP
- Remaining Planned Value BCWR
- Baseline Total Value BAC
- Resource Value Variance CV
- Time Value Variance SV
- Resource Use Efficiency Index CPI
- Time Value Efficiency Index SPI
- Contract At Cost TC
- Contract At Price TP
- Contract Liability CP
4EVMS 32 Criteria
- Industry Standard EIA 748, paragraph 2.4.f
- Develop revised estimates of cost at completion
based on performance to date, commitment values
for material, and estimates of future conditions.
Compare this information with the performance
measurement baseline to identify variances at
completion important to company management and
any applicable customer reporting requirements
including statements of funding requirements.
5Performance Analysis Process
- Objective analysis from the data
- Status performance to time now
- Look for performance trends
- Compare tends with a baseline plan
- Project performance trends into the future
- Relate projected trends to some meaningful
objective - Subjective analysis from information
- Investigate root causes of variances
- Identify future influencing factors and risk
- Adjust projected trends
- Assess resource requirements
- Compare with contract parameters
6Traditional Performance Analysis
- The Line Graph
- X-Axis Passage of time
- Years, quarters, months, weeks, days, etc.
- Y-Axis Measure of Resources
- Dollars, items, lengths, volumes, etc.
7The Line Graph
8Line Graph Charts
- The presentation is limiting . . .
- Depicts absolute values versus a time scale
- That focus on performance history
- Difficult to identify trends
- Difficult to compare trends to a baseline plan
- Difficult to develop credible cost projections to
completion
9Estimate At Completion Formula
- EAC Actuals PF X Remaining Planned Value
- Assumes Performance Factor will be a constant
- And 1 unit of Planned Value will convert to 1/-
unit of Actual - The Estimate At Completion Formula
- Provides a point estimate
- Is a limited predictive metric
- That inherently underestimates overruns
- And inherently underestimates underruns
10The Traditional Analyses
- Line Graph Charts
- and the
- Estimate At Completion Formula
- Provide partial value from Earned Value
11Why The Difference In EACs?
12A Different Look At Performance
- Relationship-Objective Analysis
- X-Axis Value of work completed
- Y-Axis Progress toward an (Objective)
13Relationship-Objective Graph
An X - Y Scatter Diagram
14An (Objective) May Be
- Baseline Total Value
- Estimate At Completion
- Contract At Cost
- Contract At Price
- Contract Liability
- Or any general (Objective) that is a specific
resource value
15Variance As Percent
Line Graph
16Variances As Of Baseline Plan
- Deviation from baseline time plan
- Deviation from baseline resource plan
- Reduces volatility of variance trends in early
periods of the project.
17Variances As Of Baseline Plan
An X - Y Scatter Diagram
18Performance Efficiency Since Start
- Value of work completed with resources used
- History of past performance efficiency
- Efficient gt 100
- Inefficient lt 100
19Resource Use Efficiency Since Start
An X - Y Scatter Diagram
20Performance Efficiency To Finish
- Ability to accomplish work within (Objective)
- Future performance required
21Resource Use Efficiency To Finish
22Rate Of Using Resources
- History of a resource burn rate
23Rate Of Using Resources
24Estimate At Completion (EAC)
- EAC Actuals PF X Remaining Planned Value
- Assumes Performance Factor will be a constant
- And 1 unit of Planned Value will convert to 1/-
unit of Actual - The Estimate At Completion Formula
- Provides a point estimate
- Is a limited predictive metric
- That inherently underestimates overruns
- And inherently underestimates underruns
25Performance Factors
- Should be related to performance
Cumulative Resource Use Efficiency Index
Running Average Resource Use Efficiency Index
(Period of Time)
Product Resource Use Efficiency Index X Time
Value Efficiency Index
Weighted 0.8 Resource Use Efficiency Index
0.2 Time Value Efficiency Index
Time Value Kicker Resource Use Efficiency Index
0.2 Time Value Efficiency Index
26Estimate At Completion
27Trend Line Projection Analysis
- Identify performance trend
- Select set of data to project trend
- Determine best fit line
- Y-Axis intercept
- Slope of best fit line
- Extrapolate to 100 complete
Projects performance trend to end of effort
28Resource Use Trend Projection
29EAC Trend Projection
30Best Case - Worse Case - Most Likely
31Thoughts While Showering . . .
- Focus on the BIG picture first, then dig deeper
- Volatility indicates poor baseline plan, poor
discipline, or both - Watch for front loading due to optimistic
planning - Significant change in scope creates a new
baseline - Dont be fooled by the early resource variance
hump - Time variances are associated with
Work-In-Progress - Time variances disappear when work is completed
- Resource variances accumulate when work is
completed - Time variances lead resource variances
- Look for long term trends and assess impacts
32Thoughts While Shaving . . .
- An Index produces a ratio
- EAC formula produces a point estimate
- EAC as percent of an (Objective) produces a rate
of change - Trends usually appear before 20 Complete
- Relationship-Objective Analysis extrapolates rate
of change trend to completion . . . - . . . And gives you Full Value from Earned Value
33Thoughts While Sitting . . .
- The Performance Factor is not constant as the
Estimate At Completion formula assumes - The trend of the Performance factor is the key
determining parameter for the most realistic
Estimate At Completion - Understand which Performance factor should be the
best predictor and why
34Agathe Christie Says . . .
- Getting Full Value from Earned Value with
Relationship-Objective Analysis is like a good
detective story. - The main characters are introduced, the plot is
established, and the clues to Who Dunit emerge in
the first 20 of the story.