SURVEY AND GRADING SURVEY AND GRADING Surface drainage Especially from house Toward drain inlet SURVEY AND GRADING Design berms and slopes INSTRUMENTS OF SURVEYING ... – PowerPoint PPT presentation

Number of Views:191
Avg rating:3.0/5.0
Slides: 34
Provided by: INFORMATI620
Category:
Tags: grading | survey | slopes

less

Transcript and Presenter's Notes

Title: SURVEY and GRADING


1
SURVEY and GRADING
2
SURVEY and GRADING
  • Surface drainage
  • Especially from house
  • Toward drain inlet

3
SURVEY and GRADING
  • Design berms and slopes

4
INSTRUMENTS OF SURVEYING
  • Tape measure
  • gt100
  • Feet/inches or feet/tenths

5
INSTRUMENTS OF SURVEYING
  • Builders level
  • Tripod mounted scope
  • Leveled so view is perfectly level in all
    directions

6
INSTRUMENTS OF SURVEYING
  • Transit
  • A builders level that also measures angles

7
INSTRUMENTS OF SURVEYING
  • Laser levels

8
INSTRUMENTS OF SURVEYING
  • Spinning laser beam and sensor

9
INSTRUMENTS OF SURVEYING
  • Surveryors rod, big yard stick, to estimate
    spot elevation

10
INSTRUMENTS OF SURVEYING
11
SURVEY and GRADING
  • What is elevation?
  • Height above average sea level

12
SURVEY and GRADING
  • Benchmark
  • Permanent reference point
  • Manhole cover, curb, fire hydrant

13
SURVEY and GRADING
14
SURVEY and GRADING
  • Contour lines
  • Connect points of similar elevation
  • The closer together contour lines, the steeper
    the slope
  • The farther apart, the flatter the slope

15
SURVEY and GRADING
  • Contour lines

16
SURVEY and GRADING
  • Whats elevation of X(a) and X(b)?

17
SURVEY and GRADING
18
SURVEY and GRADING
  • Contour lines based on spot elevations

19
SPOT ELEVATIONS
  • Backsite
  • Reading on benchmark (BM)
  • BM has a known elevation
  • Backsite Benchmark Elevation Height of
    Instrument
  • 6.12 100
    106.12

106.12
20
Spot elevations
  • Foresites
  • Readings at unknown elevations
  • Height of Instrument Foresite Elevation
  • 106.12 3.98
    102.14

106.12
102.14
21
Spot elevations
  • Construction stake at spot elevation
  • Mark stake to indicate grade change
  • 0.0 (increase ground level in inches)
  • -0.0 (decrease level)

Lets say a construction plan proposes Foresite A
to be 101.00 The existing elevation was
determined to be 102.14.
1.14
Existing elevation Proposed elevation Grade
Change 102.14
101.00 1.14
22
GRADING
  • Rough grading uses stakes with proposed changes
    marked

23
GRADING
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
Laser leveling
  • Tractor adjusts box leveler according to laser
    level

31
Laser leveling
32
DETERMING SLOPES (39)
  • (VH) X 100 OF SLOPE
  • Vertical (V) distance between 2 points
  • Horizontal (H) distance
  • V 3.14 1.21 1.93
  • H 150
  • (1.93 150) x 100 1.29

33
CREATING A SLOPE ()
  • H X Desired Slope Change in Elevation
  • H 120
  • Slope 3 (or 0.03)
  • 120 x 0.03 3.6
  • Slope needs to drop a total of 3.6 to be 3

3.6