Title: Branch: Finance
1CONCISE UPDATE ON ACID MINE DRAINAGE IN THE
WITWATERSRAND 17-18 April 2012
UPDATE BY Mr. MARIUS KEET
2Background / Introduction
- Inter-Ministerial Committee (IMC) on AMD first
convened on 1 Sep 2010 - DWA and DMR DGs appointed a Team of Experts (DWA,
DMR, CGS, CSIR, WRC, MINTEK and academic
reviewers) to conduct a situation assessment - Team of Experts (ToE) findings in Report Mine
Water Management in the Witwatersrand Gold Fields
with Special Emphasis on Acid Mine Drainage (IMC
AMD Report) accepted by IMC - Cabinet approved IMC AMD Report on 9 Feb 2011
- DWA tasked to implement certain recommendations
in IMC AMD Report
2
3Background / Introduction
- DWA appointed TCTA as Implementing Agent on 6 Apr
2011 to - Install pumps for mine water extraction
- Construction of on-site treatment plants with
option to refurbish existing plants - Convey treated water to nearby watercourse
- Facilitate operation of pumps and treatment
plants - TCTA appointed PSPs to undertake Due Diligence on
Wits AMD - Due Diligence report finalized on 7 July 2011 -
specified immediate and short-term solutions for
Wits AMD
3
4Immediate solution
- Construction works nearing completion
- Stage 1 commissioning of treatment plant by 20
April 2012 increase treatment capacity from 12
to 24 ML/day - Stage 2 commissioning by end-April 2012 achieve
maximum capacity of 35 ML/day - Agreements with Rand Uranium (treatment plant)
and Mogale Gold (sludge disposal) to be finalised
by end-April 2012
5Short-term solution
- Four (4) bids for short-term solution received by
the TCTA - Evaluation of bids to be finalized by 20 April
2012 - TCTA to follow internal bid adjudication approval
processes - Based on current funding (R433 million), TCTA
will recommend plausible options to DWA - Current funding limitations may imply a phased
(modular) implementation of short-term solution - TCTA intend to award bid by mid-May 2012
- Construction projected to commence by end-May 2012
5
6Long-term feasibility study
- PSP team appointed in January 2012.
- Contract period 13 Months until 28 February 2013.
- Study objective
- Investigate and recommend a feasible long-term
solution to the AMD problems emerging in the
study area, in order to ensure long term water
supply security and continuous fitness for use of
Vaal River water. - Study registered with National Treasurys PPP
unit. - Processes followed is flexible and will enable
conventional implementation as well as
implementation through Public Private Partnership
or Public-Public Partnership.
6
7Long-term feasibility study (continue)
- Study status
- Team mobilised.
- Data collection continuous.
- Key stakeholders Identified engagement well
advanced. - Two Study management meetings held.
- Meetings held with key stakeholders for eg.
Federation for Sustainable Environment,
Universities, Rand Water, Treasury, etc. - Study Stakeholder Committee meeting scheduled
for early May and members invited.
7
8Long-term feasibility study (continue)
- Initial findings regarding Implementation
- Urgency of implementation of desalination of AMD
is driven by the possible reduced assurance of
supply in the Vaal River System by 2014/15 - Serious risk that Vaal River requirement will not
be met if Conventional project implementation
processes are followed after the completion of
the Feasibility Study. - Alternate Implementation methods will be needed
- ie parallel activities such as EIA, and rapid
Procurement procedures, etc. will be required. - Dedicated project officer unit in DWA to be
considered to coordinate different activities
during rapid implementation. - Close coordination with National Treasury will be
required for any PPP processes
8
9Long-term feasibility study (continue)
- First steps for Request for Proposals
- Call for registration is in the process to be
issued in order to enable possible service
providers to register interest in providing
services such as - Technology solutions,
- Funding for implementation,
- Providing Treatment processing Plant
- Providing Operations and Maintenance of AMD
infrastructure - Care is taken that this call for registration
will not compromise prescribed procurement
processes.
9
10Current Mine Water Status
Basin Mine water level (metres below surface) mbs Environmental critical level (ECL) (mbs) Est. date to ECL
Eastern Feb 2012588 290 Jun 2014
Central March 2012353 174 Jun-Jul 2013
Western At surface 160 ECL currently breached resulting in surface decant
ECL The highest level that mine water can be
allowed to rise in the mine void before adverse
environmental impacts can be detected