Branch: Finance - PowerPoint PPT Presentation

About This Presentation
Title:

Branch: Finance

Description:

... to conduct a situation assessment Team of Experts (ToE) findings in Report: Mine Water ... Public Private Partnership ... Status Basin Mine water ... – PowerPoint PPT presentation

Number of Views:77
Avg rating:3.0/5.0
Slides: 11
Provided by: pil138
Category:

less

Transcript and Presenter's Notes

Title: Branch: Finance


1
CONCISE UPDATE ON ACID MINE DRAINAGE IN THE
WITWATERSRAND 17-18 April 2012
UPDATE BY Mr. MARIUS KEET
2
Background / Introduction
  • Inter-Ministerial Committee (IMC) on AMD first
    convened on 1 Sep 2010
  • DWA and DMR DGs appointed a Team of Experts (DWA,
    DMR, CGS, CSIR, WRC, MINTEK and academic
    reviewers) to conduct a situation assessment
  • Team of Experts (ToE) findings in Report Mine
    Water Management in the Witwatersrand Gold Fields
    with Special Emphasis on Acid Mine Drainage (IMC
    AMD Report) accepted by IMC
  • Cabinet approved IMC AMD Report on 9 Feb 2011
  • DWA tasked to implement certain recommendations
    in IMC AMD Report

2
3
Background / Introduction
  • DWA appointed TCTA as Implementing Agent on 6 Apr
    2011 to
  • Install pumps for mine water extraction
  • Construction of on-site treatment plants with
    option to refurbish existing plants
  • Convey treated water to nearby watercourse
  • Facilitate operation of pumps and treatment
    plants
  • TCTA appointed PSPs to undertake Due Diligence on
    Wits AMD
  • Due Diligence report finalized on 7 July 2011 -
    specified immediate and short-term solutions for
    Wits AMD

3
4
Immediate solution
  • Construction works nearing completion
  • Stage 1 commissioning of treatment plant by 20
    April 2012 increase treatment capacity from 12
    to 24 ML/day
  • Stage 2 commissioning by end-April 2012 achieve
    maximum capacity of 35 ML/day
  • Agreements with Rand Uranium (treatment plant)
    and Mogale Gold (sludge disposal) to be finalised
    by end-April 2012

5
Short-term solution
  • Four (4) bids for short-term solution received by
    the TCTA
  • Evaluation of bids to be finalized by 20 April
    2012
  • TCTA to follow internal bid adjudication approval
    processes
  • Based on current funding (R433 million), TCTA
    will recommend plausible options to DWA
  • Current funding limitations may imply a phased
    (modular) implementation of short-term solution
  • TCTA intend to award bid by mid-May 2012
  • Construction projected to commence by end-May 2012

5
6
Long-term feasibility study
  • PSP team appointed in January 2012.
  • Contract period 13 Months until 28 February 2013.
  • Study objective
  • Investigate and recommend a feasible long-term
    solution to the AMD problems emerging in the
    study area, in order to ensure long term water
    supply security and continuous fitness for use of
    Vaal River water.
  • Study registered with National Treasurys PPP
    unit.
  • Processes followed is flexible and will enable
    conventional implementation as well as
    implementation through Public Private Partnership
    or Public-Public Partnership.

6
7
Long-term feasibility study (continue)
  • Study status
  • Team mobilised.
  • Data collection continuous.
  • Key stakeholders Identified engagement well
    advanced.
  • Two Study management meetings held.
  • Meetings held with key stakeholders for eg.
    Federation for Sustainable Environment,
    Universities, Rand Water, Treasury, etc.
  • Study Stakeholder Committee meeting scheduled
    for early May and members invited.

7
8
Long-term feasibility study (continue)
  • Initial findings regarding Implementation
  • Urgency of implementation of desalination of AMD
    is driven by the possible reduced assurance of
    supply in the Vaal River System by 2014/15
  • Serious risk that Vaal River requirement will not
    be met if Conventional project implementation
    processes are followed after the completion of
    the Feasibility Study.
  • Alternate Implementation methods will be needed
  • ie parallel activities such as EIA, and rapid
    Procurement procedures, etc. will be required.
  • Dedicated project officer unit in DWA to be
    considered to coordinate different activities
    during rapid implementation.
  • Close coordination with National Treasury will be
    required for any PPP processes

8
9
Long-term feasibility study (continue)
  • First steps for Request for Proposals
  • Call for registration is in the process to be
    issued in order to enable possible service
    providers to register interest in providing
    services such as
  • Technology solutions,
  • Funding for implementation,
  • Providing Treatment processing Plant
  • Providing Operations and Maintenance of AMD
    infrastructure
  • Care is taken that this call for registration
    will not compromise prescribed procurement
    processes.

9
10
Current Mine Water Status
Basin Mine water level (metres below surface) mbs Environmental critical level (ECL) (mbs) Est. date to ECL
Eastern Feb 2012588 290 Jun 2014
Central March 2012353 174 Jun-Jul 2013
Western At surface 160 ECL currently breached resulting in surface decant
ECL The highest level that mine water can be
allowed to rise in the mine void before adverse
environmental impacts can be detected
Write a Comment
User Comments (0)
About PowerShow.com