Title: PETE 411 Well Drilling
1PETE 411 Well Drilling
- Lesson 3 The Rig - Drilling Equipment
2Contents
- Rig Pumps
- Solids Control Equipment
- Air Drilling
- The Rotary System
- The Swivel
- The Well Control System
- The Well Monitoring System
- Offshore Drilling
3Assignments
- READ ADE Ch. 1, to p.30
- HW 1 ADE 1.1, 1.2, 1.3
- Due Monday, Sept. 9, 2002
- at the beginning of class
- NOTE Answers in book are not always
correct...
4Schematic of Rig Circulating System for liquid
drilling fluid
5(No Transcript)
6Example 1.3
- Compute the pump factor in units of barrels per
stroke for a double-acting duplex pump having - 6.5-inch liners (dL)
- 2.5 inch rods (dr)
- 18-inch strokes (LS)
- and a volumetric efficiency of 90. (EV)
7Solution
- The pump factor for a duplex pump can be
determined using Equation 1.10
8Recall
- There are 231 in.3 in an U. S. gallon and 42
U.S. gallons in a U.S. barrel. Thus converting to
the desired field units yields - 1991 in.3/stroke gal/231 in.3 bbl/42 gal.
- 0.2052 bbl/stroke.
- Thus Pump Factor 0.2052 bbl/stroke
9Pump Factor 3 p/4 dL2 LS EV/(231 42)
10Example Pump Factor for Triplex Pump
11Example Pump Rate
- Pump Factor Strokes/min
- 0.09442
-
- 7.554 bbl/min
- 317.3 gal/min
Pump Rate 317 gal/min
12- Hydrocyclone
- desander
- desilter
No moving parts Low cost
Pressure drop Diameter
13 Decanting Centrifuge
Use?
14Use?
15 Fig. 1.33 Schematic of Rotary System
16 Fig. 1.34 Cutaway View of Swivel
Seals Bearings
ROTATING
17PIN BOX TJ Shoulder
Fig. 1.38 Cutaway View and Dimensions for
Example Tool Joint
18 Fig. 1.39 Stabilizer
Keeps pipe in center of hole Aids in drilling
straight hole Prolongs bit life
19 Fig. 1.41 Kick Detection During Drilling
Operations
3
GAIN IN PIT VOLUME EQUAL TO KICK VOLUME
2
KICK
1
20 Fig. 1.46 Remote Control Panel for operating
Blowout Preventers
CHOKE
What to do if KICK occurs?
21DP TJ DC OH Press
Fig. 1.44 Annular Blowout Preventer
22Ram Blowout Preventer
23SHEAR / BLIND RAM ASSEMBLY
Ram Blowout Preventer - contd
24Fig. 1.48 Rotating Blowout Preventer
25 Fig. 1.51 High-Pressure Circulating System for
Well Control Operations
Kick
Keep BHP const.
26 Fig. 1.56 Subsurface Well Monitoring System
MWD
27OFFSHORE DRILLING
Fig. 1.57 Spread Mooring Systems
28 Fig. 1.58 Schematic of Equipment for Marine
Drilling
29Fig. 1.59 Operation of a Heave Compensator
30Fig. 1.60 Subsea BOP Stack
31Fig. 1.63 Subsea Equipment Installation
Procedure
32Typical Casing Strings
Water Level Depth Seafloor Below
ML Conductor pile 36 30
200 Conductor Casing 26 20
1000 Surface Casing 17 1/2 13 3/8
4000 Hole Csg.
Depth
33Some Typical Casing Strings
Depth Below ML Conductor
pile 36 30 200 Conductor Casing
26 20 1000 Surface Casing 17 1/2 13
3/8 4000 Hole
Csg. Depth
34Capacity Area Length
35What is the capacity of 10,000 ft of 5 OD, 19.50
lb/ft drillpipe?
Capacity Area Length Area p/4 d2 p/4
4.2762 14.36 in2 Length 10,000 ft
120,000 in Capacity 14.36 120,000 in3
/(23142 in3 /bbl) Capacity 177.6
bbls
36What is the displacement of 10,000 ft of 5 OD,
19.50 lb/ft drillpipe?
Capacity Area Length Area p /4 (od2 -
id2 ) p /4 (52 - 4.2762) 5.275
in2 Length 10,000 ft 120,000 in Displ.
5.276 120,000 in3 /(231 42 in3 /bbl)
Displacement ? Bbls