2Model 20 story steel moment-frame building
- 20 story steel moment-frame building plus one
basement. - Designed according to the 1994 UBC
- Natural period is 3.5 sec
- H77.88 m
Frame Elevation
Floor Plan
320-story SMRF
46-story SMRF (1.54 sec period)
5Faults Modeled
Day and others, 2005
- 1. Sierra Madre (7.0)
- 2. Santa Monica SW (6.3)
- 3. Hollywood (6.4)
- 4. Raymond (6.6)
- 5. Puente Hills I (6.8)
- 6. Puente Hills II (6.7)
- 7. Puente Hills (all) (7.1)
- 8. Compton (6.9)
- 9. Newport-Inglewood (6.9)
- 10. Whittier (6.7)
6Coordination Scheme
UCB -LLNL UCSB CMU URS (RG) URS (AP)
S. Madre F,R,S C
S. Mon. F,R C
HollyW F,R C
Raym F,R C
P.Hills6.8 F,R C
P.Hills6.7 F,R C
P.Hills7.1 F,R,R,S C
Comp F,R,S C
N-I N. R,S F C
Whit N. R F C
R 1D rock reference simulation S 1D
basin-profile simulation
F 6 3D scenarios C single cross-check
7Puente Hills M 7.1
8Puente Hills M 7.1 (2sec. Bandpass)
9Downtown LA site for M 7.1 Puente Hills
DLA
10Puente Hills (M7.1) LA downtown 6-story with
perfect welds
11Puente Hills (M7.1) LA downtown 6-story with
brittle welds
12Puente Hills (M7.1) LA downtown 20-story with
perfect welds
13Puente Hills (M7.1) LA downtown 20-story with
brittle welds
14 Mid-city site for M 7.1 Puente Hills
MC
15Puente Hills (M7.1) mid-city 6-story with
perfect welds
16Puente Hills (M7.1) mid-city 6-story with
brittle welds
17Puente Hills (M7.1) mid-city 20-story with
perfect welds
18Puente Hills (M7.1) mid-city 20-story with
brittle welds
19West LA site for M 7.1 Puente Hills
WLA
20Puente Hills (M7.1) West LA 6-story with perfect
welds
21Puente Hills (M7.1) West LA 6-story with brittle
welds
22Puente Hills (M7.1) West LA 20-story with
perfect welds
23Puente Hills (M7.1) West LA 20-story with
brittle welds
24Puente Hills M 7.1 6-story with perfect welds
25Puente Hills M 7.1 6-story with brittle welds
26Puente Hills M 7.1 20-story with perfect welds
27Puente Hills M 7.1 20-story with brittle welds
28Graves
29Comparison of Graves motions vs SCEC motions for
downtown LA
30Comparison of Graves motions vs SCEC motions for
Whittier
31Graves scenario and 6-story with perfect welds
32Graves scenario and 6-story with brittle welds
33Graves scenario and 20-story with perfect welds
34Graves scenario and 20-story with brittle welds
35Are We Addressing the Right Questions in
Earthquake Engineering?
- Current methodology assumes 1) architecture and
2) seismic hazard. - Simplified assumptions about nonlinear building
response (ductility factors) are used to produce
a design. - collapse mechanisms are rarely defined.
- Earth scientists are almost never asked if it is
possible that the site will experience motions
that can trigger the collapse mechanisms. - Choose designs that are least susceptible to
poorly predicted ground motions. - Its really tough to predict fault slip and hence
long-period ground motions.
36(No Transcript)
37Graves
38Graves
39Puente Hills (East segment, M 6.8,epi 2)
SCEC/PEER
40Puente Hills (East segment, M 6.8,epi 2)
SCEC/PEER
41Puente Hills (East segment, M 6.8) SCEC/PEER
slip models
42Puente Hills (East segment, M 6.8)6-story with
brittle welds
43Puente Hills (East segment, M 6.8)6-story with
brittle welds
44Puente Hills (East segment, M 6.8)6-story with
perfect welds
45Puente Hills (East segment, M 6.8)6-story with
perfect welds
46Puente Hills (East segment, M 6.8)20-story with
brittle welds
47Puente Hills (East segment, M 6.8)20-story with
brittle welds
48Puente Hills (East segment, M 6.8)20-story with
perfect welds
49Puente Hills (East segment, M 6.8)20-story with
perfect welds
50Puente Hills LA Segment (M 6.7)
51Puente Hills LA Segment (M 6.7)
52Puente Hills LA Segment (M 6.7)Slip
53Puente Hills LA Segment (M 6.7) 6-story with
brittle welds
54Puente Hills LA Segment (M 6.7) 6-story with
brittle welds
55Puente Hills LA Segment (M 6.7) 6-story with
perfect welds
56Puente Hills LA Segment (M 6.7) 6-story with
perfect welds
57Puente Hills LA Segment (M 6.7) 20-story with
brittle welds
58Puente Hills LA Segment (M 6.7) 20-story with
brittle welds
59Puente Hills LA Segment (M 6.7) 20-story with
perfect welds
60Puente Hills LA Segment (M 6.7) 20-story with
perfect welds
61Puente Hills M 7.1
62Puente Hills M 7.1 6-story with brittle welds
63Puente Hills M 7.1 6-story with perfect welds
64Puente Hills M 7.1 20-story with brittle welds
65Puente Hills M 7.1 20-story with perfect welds
66Graves downtown site 1 20-story with brittle welds
67Graves downtown site 2 20-story with brittle welds
68Graves downtown site 3 20-story with brittle welds
69Graves downtown site 4 20-story with brittle welds
70Graves downtown site 5 20-story with brittle welds
71Graves downtown site 6 20-story with brittle welds
72Graves downtown site 7 20-story with brittle welds
73Graves downtown site 8 20-story with brittle welds
74Graves downtown site 9 20-story with brittle welds